Jeddah Tower is a mixed-use skyscraper under construction in North Obhur, Jeddah, Saudi Arabia, designed to exceed 1,000 metres and become the world's tallest…

Swipe to explore ›
AiTimeline Home
ORIGIN

Jeddah Economic Company Established, Design Competition Won

Kingdom Holding Company and its project vehicle, Jeddah Economic Company, commissioned a design competition won by architect Adrian Smith and structural engineer Thornto…

AiTimeline Home
CONSTRUCTION BEGINS

Groundbreaking on the North Obhur Site

Groundbreaking and early piling work began in April 2013 on Jeddah's North Obhur, Red Sea coastline - four years after the design competition concluded. Saudi Binladin G…

AiTimeline Home
CONSTRUCTION HALTS

Work Stops at Roughly 63 Floors

Construction halted around January 2018 amid contractor payment disruption and upheaval connected to Saudi Arabia's late-2017 anti-corruption campaign, which had detaine…

AiTimeline Home
RESTART PROCESS BEGINS

Jeddah Economic Company Opens Tender to Complete the Tower

In September 2023, Jeddah Economic Company opened a request-for-proposals process to find a contractor to complete the tower, beginning renewed negotiation with Saudi Bi…

AiTimeline Home
COMPLETION CONTRACT SIGNED

SAR 7.2 Billion Contract Awarded to Saudi Binladin Group

Jeddah Economic Company signed a completion contract with Saudi Binladin Group worth SAR 7.2 billion (about $1.9bn), including roughly SAR 1.1bn recognising previously c…

AiTimeline Home
OFFICIAL RESTART

Concrete Poured on Floor 64, Construction Resumes

On 21 January 2025, Kingdom Holding held a restart ceremony on site; Prince Alwaleed bin Talal and company leadership attended as concrete was poured on the tower's 64th…

AiTimeline Home
FLOOR 80

Tower Surpasses 80 Floors

Trade press confirmed on 6 January 2026 that construction had surpassed 80 floors by December 2025, underscoring the accelerating pace roughly one year after the restart.

AiTimeline Home
LEVEL 99

Kingdom Holding Q1 2026 Results: ≈398 Metres

Kingdom Holding's Q1 2026 earnings presentation disclosed Level 99 (≈398 metres), 274,000+ cubic metres of concrete poured (≈61% of plan), façade cladding across 36+ flo…

AiTimeline Home
LATEST VERIFIED STATUS

Floor 106-107, ≈430 Metres — Kingdom Holding Q2 2026 Results

Prince Alwaleed bin Talal confirmed the milestone on site on 23 July 2026; Kingdom Holding's Q2 2026 results, reported around 7 August 2026, put concrete poured above 30…