Tata Dholera Fab: Every Stage of India's First Commercial Chip Plant

Tata Electronics is building India's first commercial semiconductor fab at Dholera, Gujarat: a Rs 91,526 crore, 300 mm plant with technology from Taiwan's PSMC…

Swipe to explore ›
AiTimeline Home
THE SITE

Gujarat creates Dholera SIR

A flat, low-lying stretch of Gujarat's Bhal region near the Gulf of Khambhat, designated a Special Investment Region in 2009.

AiTimeline Home
FAILED TRY

Two fabs approved, none built

Two consortia won in-principle approval in 2013. Neither raised the money; HSMC's letter of intent was cancelled in 2018.

AiTimeline Home
THE MISSION

Rs 76,000 crore chip programme

The India Semiconductor Mission programme approved in December 2021 pays up to half of a fab's project cost.

AiTimeline Home
FALSE START

Vedanta-Foxconn picks Dholera, then splits

Vedanta and Foxconn chose Dholera in 2022 for a Rs 1.54 lakh crore plan. Foxconn quit in July 2023.

AiTimeline Home
APPROVED

Cabinet clears India's first commercial fab

A 300 mm fab with Taiwan's PSMC, 50,000 wafer starts a month on 28 to 110 nm processes.

AiTimeline Home
GROUNDBREAKING

First chip promised for Dec 2026

At the foundation stone, minister Ashwini Vaishnaw said the first chip would come out in December 2026.

AiTimeline Home
PSMC

Taiwan's PSMC signs the definitive deal

Process technology licences from 28 to 110 nm, fab design and construction support, and engineering help.

AiTimeline Home
THE MONEY

Rs 91,526 crore support agreement

The Centre pays 50% of eligible cost in step with Tata's spending, under the March 2025 agreement.

AiTimeline Home
SOFT GROUND

Foundations redesigned

Studies found Dholera's reclaimed land had low load-bearing capacity. Tata redesigned the foundations.

AiTimeline Home
INTEL

Intel MoU to explore Dholera

Tata and Intel signed an MoU in December 2025 to explore making and packaging Intel products in India.

AiTimeline Home
SEZ

66-hectare fab SEZ notified

A 66.166-hectare special economic zone for Tata Semiconductor Manufacturing, notified on 9 April 2026.

AiTimeline Home
ASML

ASML backs the fab

ASML makes the lithography machines every fab needs. Its May 2026 MoU covers set-up, ramp-up and training.

AiTimeline Home
DATE MOVED

90 nm first, commercial output mid-2028

Production starts at 55 and 90 nm. The government now expects commercial operations in mid-2028.

AiTimeline Home
SEMICON

Suppliers sign up

Over 450 partners are engaged. Sumitomo Chemical, Kelington and Sojitz with NRS signed at SEMICON India 2026.

AiTimeline Home
VENDOR PARK

363 acres for 450 suppliers

Keeping chemicals, gases and spare parts beside the cleanroom so production never waits.

AiTimeline Home
WHAT TO WATCH

Tools in, first wafers, a customer

Watch for tool move-in, first wafers in 2027, named customers, and commercial output by mid-2028.