India Semiconductor Timeline 2026–2030: Fabs, OSAT Plants, Tata, Micron & the Chip Manufacturing Race

📅 Updated 28 August 20262021–2030 spanDesign · OSAT · ATMP · Fabs · Packaging
Advertisement
In short

India's semiconductor timeline 2026: Micron, Kaynes and CG Semi are producing chips, the Tata-PSMC Dholera fab is under construction, plus Semicon 2.0.

For years, India’s semiconductor strength sat in the part of the industry most people never see: chip design. That is starting to change. In 2026, Micron opened an assembly-and-test plant at Sanand, Kaynes Semicon began production, and CG Semi entered commercial production — three plants packaging and testing chips on Indian soil. Meanwhile Tata Electronics is building a much harder piece: a 300 mm wafer fabrication plant at Dholera with Taiwan’s PSMC. Packaging a chip in India is a real manufacturing milestone. Fabricating the silicon wafer itself is a different level of difficulty. This India semiconductor timeline tracks both, from the 2021 policy blueprint to the 2030 test of whether the ecosystem holds together.

India Semiconductor Timeline 2026-2030: Fabs, OSAT Plants, Tata, Micron and the Chip Manufacturing Race

Fact-checked: 28 August 2026. Investment figures are approved project values from Government of India and company statements, not money already spent. Every future milestone is labelled target, expected or reported. This is not investment advice.

⚠️ How we classify each project. Proposed — announced only. Approved — formal Government of India approval under the semiconductor programme. Under construction — physical site work underway. Pilot / ramp — limited production or test line running. Commercial production — company or government confirms commercial operations. Full ramp — rated capacity reached. A ribbon-cutting is not the same as full-rate output, and an OSAT plant is not a wafer fab.

🧠 The 60-second answer

In 2026 India moved from promising chips to producing them. Micron (28 February 2026), Kaynes Semicon (31 March 2026) and CG Semi (4 July 2026) all began assembly, packaging and test operations in Gujarat — real semiconductor manufacturing, but not wafer fabrication. The Tata–PSMC fab at Dholera, India’s first pure-play silicon foundry, is under construction with first wafers targeted for late 2026 and commercial-scale output reported for around 2028. The government has approved about 10 manufacturing units (expanded toward a dozen) worth a cumulative ₹1.64 lakh crore, and in July 2026 cleared Semicon 2.0, a ₹1,27,500 crore programme aimed at deepening the ecosystem — equipment, materials, design IP and R&D — rather than only subsidising fabs.

📈 India Semiconductor Dashboard — August 2026 (verified)
~10→12
Approved manufacturing units
3
Plants in commercial production
1
Silicon wafer fab under construction
₹1.64 L cr
Cumulative approved investment
₹91,526 cr
Tata Dholera fab (approved value)
50,000
Dholera wafer starts / month (planned)
₹1,27,500 cr
Semicon 2.0 outlay (approved Jul 2026)
105
Startups with EDA-tool access
Last updated 28 August 2026 · Sources: PIB / Cabinet releases, PMIndia, India Semiconductor Mission, Micron, Tata Electronics, CG Power, Kaynes Technology, Business Standard, Reuters. Counts vary by what is bundled; “10→12” reflects 10 units approved through early 2025 plus four in August 2025 and two in May 2026.
Reading the status labels. Micron, Kaynes and CG Semi are in commercial production as assembly/test plants. Tata Dholera and Tata Assam are under construction. HCL–Foxconn, SiCSem and 3D Glass Solutions are approved and in early build. The proposed Adani–Tower fab in Maharashtra is not centrally approved under the semiconductor programme and is not counted here.
⚡ India Semiconductor — Quick Facts
ProgrammeIndia Semiconductor Mission (ISM), launched 2021, ₹76,000 crore
Phase 2Semicon 2.0 — ₹1,27,500 crore, approved 15 July 2026
First plant to produceMicron Sanand ATMP — inaugurated 28 February 2026
First pure-play fabTata–PSMC, Dholera, Gujarat — under construction
Fab technology300 mm wafers, 28 nm to 110 nm nodes
What India does not do yetLeading-edge logic or DRAM/NAND wafer fabrication
⚡ Quick Answers — AI Overview Ready

India’s chip push: key questions

Does India manufacture semiconductor chips in 2026?
Yes, in the backend sense. Micron, Kaynes Semicon and CG Semi run commercial assembly, packaging and test plants in Gujarat that turn fabricated wafers or dies into finished chips. India does not yet fabricate silicon wafers at commercial scale.
What is India’s first semiconductor fab?
The Tata Electronics–PSMC plant at Dholera, Gujarat, is India’s first pure-play silicon wafer fab. It is under construction, with a planned 50,000 wafers per month on 300 mm wafers at 28 nm to 110 nm nodes. First wafers are targeted for late 2026.
What does Micron make in Sanand?
Micron’s Sanand plant assembles and tests memory. DRAM and NAND wafers fabricated elsewhere in Micron’s global network are packaged into finished memory and storage products. It is an ATMP facility, not a wafer fab.
Can India manufacture Nvidia-class AI chips?
No, and no approved project claims to. Leading-edge AI accelerators need process nodes and advanced packaging India does not have. Dholera’s 28–110 nm range targets automotive, power, communications and industrial chips, which are large markets in their own right.
📚 Key Takeaways

What India’s semiconductor story looks like in 2026

  • 2026 is the production year. Three plants — Micron, Kaynes, CG Semi — began commercial assembly and test operations, replacing future-tense promises with physical output.
  • Packaging is not fabrication. Micron, Kaynes and CG Semi are OSAT/ATMP plants. They take fabricated wafers or dies and cut, bond, package and test them. The silicon is still made abroad.
  • The wafer-fab test is still ahead. Tata–PSMC Dholera is India’s first pure-play foundry, under construction. First wafers are a late-2026 target; commercial-scale output is reported for around 2028, and the starting node may be 90 nm before 28 nm.
  • PSMC is not TSMC. Tata’s fab partner is Powerchip Semiconductor Manufacturing Corporation, a Taiwanese foundry specialising in mature nodes — a different company from TSMC.
  • Semicon 2.0 changes the emphasis. The ₹1,27,500 crore phase approved in July 2026 targets equipment, materials, design IP, R&D and skills — the parts of the stack a single fab subsidy does not build.
  • The map is wider than Gujarat. Assam (Tata OSAT), Uttar Pradesh (HCL–Foxconn display drivers), Odisha (SiCSem silicon carbide, 3D Glass packaging), Punjab (CDIL) and Andhra Pradesh (ASIP) all have approved units.
  • 28 nm is not obsolete. Mature nodes run most automotive, power-management, microcontroller and industrial chips, where reliability and long product life matter more than transistor size.
  • Investment figures are approvals, not spending. The ₹1.64 lakh crore cumulative number mixes private investment, central incentives and state support across projects at very different stages.
  • The Adani–Tower fab is a proposal, not an approved plant. Maharashtra cleared it at state level in 2024; it never received central approval, and Adani paused talks with Tower in 2025.
  • Capacity numbers measure different things. 50,000 wafer starts a month is not 50,000 chips. 48 million packaged units a day is a different metric again. They cannot be ranked against each other.

India’s 2026 semiconductor production breakthrough

Three backend plants entered production in five months. The next test is wafer fabrication.

28 February 2026 — Micron, Sanand — assembly and test of DRAM and NAND memory begins; wafers come from Micron’s global fabs
31 March 2026 — Kaynes Semicon, Sanand — OSAT plant inaugurated and production starts; power modules for EV and industrial use
4 July 2026 — CG Semi, Sanand — commercial production begins at the G1 OSAT line; described as India’s third semiconductor plant to produce in 2026
Next: large-scale wafer fabrication — Tata–PSMC Dholera, under construction, first wafers targeted late 2026

All three 2026 milestones are backend manufacturing — packaging and testing. None of them fabricates a silicon wafer.

How a chip is actually made

The simplified journey from a design file to a device — and where Indian projects sit.

Chip design — the circuit is designed and verified in software, then taped out. India’s existing strength; 24 approved design projects, 105 startups with EDA access.
Wafer fabrication — transistors and circuits are built directly onto a silicon wafer through lithography, deposition and etch. Tata–PSMC Dholera (under construction); SiCSem in Odisha for silicon carbide.
Wafer test & dicing — the finished wafer is tested and cut into individual dies
Packaging / assembly — dies are bonded into protective packages with external connections. Micron, CG Semi, Kaynes, Tata Assam, ASIP, 3D Glass Solutions.
Final test — each packaged chip is tested for performance and reliability
Device — the chip goes into a phone, car, server, appliance or industrial system

India today is strong at the top of this chain (design) and building fast at the bottom (packaging and test). The middle step — wafer fabrication — is the hard gap Dholera is meant to close.

Fab vs OSAT vs ATMP: what’s the difference?

Fab (fabrication plant)

A fab starts with blank silicon wafers and builds the transistor structures and integrated circuits directly onto them, layer by layer, using photolithography, thin-film deposition, etching and doping. This is the most capital-intensive and technically demanding step. Example: Tata–PSMC, Dholera. SiCSem in Odisha is a fab too, but for silicon carbide rather than silicon logic.

OSAT (Outsourced Semiconductor Assembly and Test)

An OSAT facility receives fabricated wafers or dies and performs the backend: wafer dicing, die attach, wire bonding or flip-chip, encapsulation and final testing. It is real semiconductor manufacturing, with its own yield and reliability challenges, but it does not create the circuits. Examples: CG Semi, Kaynes Semicon, Tata Assam.

ATMP (Assembly, Testing, Marking and Packaging)

ATMP is the term Indian policy documents often use for the same backend activity, sometimes with the marking (laser-etched part numbers) step called out. Example: Micron Sanand, which packages and tests memory. Functionally, ATMP and OSAT describe the same part of the chain.

The key point: OSAT and ATMP production is genuine manufacturing and a real milestone for India. It is still not the same thing as fabricating the wafer.

India semiconductor timeline: 2021 → 2030

Newest first. Forward items are labelled target or expected.

15 JUL
2026

Cabinet approves Semicon 2.0

Union Cabinet₹1,27,500 crore outlayStatus: approved

The government approved the second phase of the India Semiconductor Mission with an outlay of ₹1,27,500 crore. Its stated pillars span chip design and IP, equipment and materials (machinery, specialty chemicals, industrial gases), fabs (silicon, compound, discrete and display), ATMP and advanced packaging, R&D aimed beyond 28 nm, and talent. The FY2026–27 Union Budget had earlier set aside ₹1,000 crore toward launching the phase — an annual provision, separate from the total programme outlay.

Semicon 2.0’s design is a deliberate shift: Phase 1 mostly funded factories, Phase 2 tries to build the suppliers, tools, materials and IP an ecosystem needs around them.
POLICYAPPROVED
4 JUL
2026

CG Semi enters commercial production

CG Power + Renesas + Stars MicroelectronicsSanand, GujaratStatus: commercial production

The CG Semi OSAT facility began commercial production at its G1 line. The joint venture pairs CG Power (Murugappa Group) with Renesas Electronics of Japan and Stars Microelectronics of Thailand. Approved project value is about ₹7,584 crore, with planned capacity building toward roughly 15 million chips a day across G1 and G2, for automotive, industrial and consumer applications.

Official reporting described CG Semi as the third semiconductor plant in India to begin production during 2026, after Micron and Kaynes.
COMMERCIAL PRODUCTIONOSAT

ASML equipment deal; two more units approved

Tata Electronics / ISMStatus: agreements

Tata Electronics signed a lithography-equipment agreement with ASML (16 May 2026) for the Dholera fab — a reminder that even a domestic fab depends on the global tool base. Around the same time the government approved two further units: Crystal Matrix (compound semiconductors and displays, Dholera) and Suchi Semicon (discrete-device OSAT, Surat). SiCSem also signed its firm fiscal-support agreement with the mission (11 May 2026).

No fab is a fully domestic supply chain. Lithography (ASML), deposition and etch tools (Applied Materials, Lam Research, Tokyo Electron) and metrology (KLA) all come from a handful of global suppliers.
EQUIPMENT2 UNITS APPROVED
9 APR
2026

Dholera fab gets its SEZ notification

Dholera SIR, GujaratStatus: under construction

The Centre formally notified a 66-hectare Special Economic Zone in the Dholera Special Investment Region, with Tata Semiconductor as developer and around 21,000 jobs cited. Construction of the fab continued through 2026. Reports that the plant is “half complete” with a late-2026 pilot are project projections, not independently verified.

A fab shell can be finished long before the fab works. Tool install, process qualification, test wafers, yield ramp and customer qualification all come after the building.
SEZ NOTIFIEDUNDER CONSTRUCTION
31 MAR
2026

Kaynes Semicon starts production

Kaynes TechnologySanand, GujaratStatus: commercial production

The Kaynes Semicon OSAT plant at Sanand was inaugurated and began production, about 14 months after groundbreaking. Approved value is around ₹3,307 crore. The plant makes intelligent power modules and packaged devices for EV, industrial and consumer use, ramping from roughly 1.5 million units a day toward a planned peak near 6.3 million a day.

Kaynes was widely described as India’s second semiconductor unit to reach production, after Micron.
COMMERCIAL PRODUCTIONOSAT
28 FEB
2026

Micron opens the Sanand assembly-and-test facility

Micron TechnologySanand, GujaratStatus: commercial production

Micron inaugurated India’s first semiconductor assembly and test facility. The plant converts DRAM and NAND wafers fabricated elsewhere in Micron’s global network into finished memory and storage products. Micron expects tens of millions of units assembled and tested at Sanand in 2026, rising to hundreds of millions in 2027. The total project structure is about ₹22,516 crore (around $2.75 billion as announced in 2023), combining Micron investment with central and Gujarat government support.

This is an ATMP plant, not a memory fab. No DRAM or NAND wafers are made in Sanand.
FIRST TO PRODUCEATMP — MEMORY
21 FEB
2026

HCL–Foxconn breaks ground in Uttar Pradesh

HCL–Foxconn JVJewar / YEIDA, Uttar PradeshStatus: under construction

Foundation work began on the HCL–Foxconn unit near Jewar, approved in May 2025 at about ₹3,706 crore. It is an ATMP plant focused on display driver chips for phones, laptops, TVs, wearables and vehicles — not a logic fab. Planned capacity is around 20,000 wafers a month, or tens of millions of packaged units a month. Operations are targeted for 2027.

Display drivers are a high-volume, unglamorous product category — exactly the kind of established market a first-wave ecosystem is built on.
DISPLAY DRIVERSUNDER CONSTRUCTION

Four more units approved: Odisha, Punjab, Andhra Pradesh

Union Cabinet₹4,594 crore combinedStatus: approved

The government approved four projects: SiCSem (Bhubaneswar, Odisha — India’s first commercial silicon carbide fab plus packaging, ~₹2,067 crore, with UK partner Clas-SiC); 3D Glass Solutions (Odisha — glass-substrate advanced packaging, ~₹1,943 crore); CDIL (Mohali, Punjab — discrete power-semiconductor expansion); and ASIP (Andhra Pradesh — system-in-package assembly, with Korean partner APACT).

SiCSem matters because silicon carbide, not silicon, is the material of choice for EV powertrains, fast chargers and grid electronics.
4 UNITS APPROVEDCOMPOUND SEMI
2024
→25

India moves from policy to construction

Union Cabinet approvalsStatus: approved → building

In February and September 2024 the Cabinet approved the first big wave: the Tata–PSMC Dholera fab, the Tata assembly-and-test plant in Assam, the CG Power OSAT and, in September, Kaynes. In May 2025 it approved HCL–Foxconn. Together these projects account for the bulk of the ₹1.64 lakh crore cumulative figure.

This is the point at which the mission stopped being a scheme document and became construction sites in Gujarat, Assam and Uttar Pradesh.
FIRST WAVE

India Semiconductor Mission launched

Semicon India Programme₹76,000 croreStatus: completed launch

The government launched the India Semiconductor Mission with a ₹76,000 crore outlay, offering fiscal support for fabs, compound-semiconductor and packaging units, and a display fab, alongside a design-linked incentive scheme. Early proposals stalled — a Vedanta–Foxconn plan collapsed — before the 2024 approvals gave the programme real projects.

India had a chip-design industry for decades before 2021. The mission was about the manufacturing India had never had.
PROGRAMME START

2027–2028: the wafer-fab test

Forward-looking. Dates are company and government targets and can move.

The next phase is about Tata Dholera and the other fab projects moving from construction to qualified production. Tata and government messaging points to first or trial wafers by late 2026 and a commercial ramp across 2027–2028. Some industry reporting is more cautious: that the fab may start at 90 nm rather than 28 nm and that commercial-scale output slips to around mid-2028. Both are targets, not facts. The measurable questions for this window are equipment installation, process qualification, customer qualification and yield — not ribbon-cuttings. SiCSem’s silicon carbide fab in Odisha is targeting first wafers around the end of 2026 on a similar “target” basis.

What would ecosystem maturity look like by 2030?

Measured in output, not announcements.

2030 scorecard — what to measure

  • Number of fabs actually in sustained commercial production, and at what yield
  • Total wafer starts per month across all operating fabs
  • Number of OSAT and ATMP plants at or near rated capacity
  • Advanced-packaging capability — whether any Indian plant runs 2.5D or 3D integration in volume
  • Indian-designed chips actually in production, not just taped out
  • Local suppliers of specialty gases, chemicals, photoresists and equipment services
  • Export customers who have qualified Indian-made parts
  • Repeat private investment — second units, expansions, new entrants without fresh subsidy
  • A working fabless startup ecosystem shipping products, not prototypes

Notice what is not on that list: a specific process node. Semicon 2.0 can strengthen equipment, materials, design and packaging without any approved roadmap committing India to sub-20 nm production by 2030 — and no such commitment currently exists.

India semiconductor plant tracker — August 2026

Approved units under the India Semiconductor Mission. Values are approved project cost, not money spent.

Company / JVLocationTypeFocusApproved ₹ crStatus
MicronSanand, GujaratATMPDRAM / NAND memory packaging & test22,516🟢 Commercial production (Feb 2026)
Kaynes SemiconSanand, GujaratOSATPower modules, auto / industrial3,307🟢 Commercial production (Mar 2026)
CG SemiSanand, GujaratOSATAuto / industrial / consumer packaging7,584🟢 Commercial production (Jul 2026)
Tata–PSMCDholera, GujaratFab (300 mm)28–110 nm logic, PMIC, display, MCU91,526🟠 Under construction
Tata (TSAT)Morigaon, AssamOSAT / ATMPAuto, EV, communications, consumer27,120🟠 Under construction
HCL–FoxconnJewar / YEIDA, UPATMPDisplay driver ICs3,706🟠 Under construction
SiCSemBhubaneswar, OdishaFab + ATMPSilicon carbide (compound semi)2,066🟠 Approved, early build
3D Glass SolutionsBhubaneswar, OdishaAdvanced packagingGlass substrates, 3D integration1,943🟣 Approved
CDILMohali, PunjabDiscretePower semiconductors (Si & SiC)~117🟣 Approved (expansion)
ASIPAndhra PradeshOSATSystem-in-package assembly~480🟣 Approved
Crystal MatrixDholera, GujaratCompound fab + ATMPGaN, mini / micro-LEDpart of 3,936🟣 Approved (May 2026)
Suchi SemiconSurat, GujaratOSATDiscrete devicespart of 3,936🟣 Approved (May 2026)

🟢 commercial production   🟠 under construction   🟣 approved / not yet building   CDIL and ASIP values are approximate; the four August-2025 units total about ₹4,594 crore.

Major proposals not equivalent to approved plants

ProjectLocationReported valueCentral ISM approval?Status
Adani – Tower SemiconductorPanvel, Maharashtra~₹83,947 croreNo — appraisal stage onlyState-cleared 2024; Adani paused talks with Tower in 2025; no revival confirmed

This distinction matters. A state cabinet clearance and a memorandum of understanding are not the same as central approval under the semiconductor programme, and this project has never had the latter. It should not be counted among India’s approved fabs or described as under construction.

Tata–PSMC Dholera: India’s biggest fab bet

The Tata Electronics–PSMC plant at Dholera, Gujarat, is India’s first pure-play semiconductor foundry — a fab that manufactures chips designed by customers rather than selling its own branded products. The customer designs the chip; the foundry makes it.

Technology partner: Powerchip Semiconductor Manufacturing Corporation (PSMC) of Taiwan, a mature-node specialist. This is not TSMC — a different Taiwanese company with a similar-sounding name. Wafer size: 300 mm (12-inch). Planned capacity: up to 50,000 wafers per month. Technology range: 28 nm to 110 nm, covering power-management ICs, display drivers, microcontrollers and high-performance-computing logic, for automotive, computing, communications and data-storage customers. The approved project value is ₹91,526 crore (Tata’s own wording is “up to ₹91,000 crore”), roughly $11 billion.

Status, August 2026: under construction. A 66-hectare SEZ was notified in April 2026 and an ASML lithography-equipment agreement signed in May. Claims that the fab is around half built with a late-2026 pilot are project projections. First wafers are a target for late 2026; industry reporting suggests the fab may open at 90 nm and reach commercial scale around 2028. Until wafer production actually begins, the correct status is under construction, not operating.

Why Assam matters to India’s chip strategy

The Tata Semiconductor Assembly and Test facility at Morigaon (Jagiroad), Assam, is an OSAT / ATMP plant — assembly, packaging and test — not a wafer fab. Approved value is about ₹27,120 crore, with a planned full-scale capacity of 48 million packaged units a day — 4.8 crore units — serving automotive, EV, communications and consumer markets. That figure is a target for full ramp, not current output.

An earlier government roadmap expected Phase 1 to begin around April 2026. As of August 2026, the minister’s language is that the plant is “likely to begin operations within FY2026–27” — commissioning has not been confirmed as complete, and there is no verified first-chip event. The strategic value is regional: it puts a large, skilled-manufacturing employer in the north-east and diversifies the packaging base beyond Gujarat.

Beyond Gujarat: the wider semiconductor map

Uttar Pradesh

HCL–Foxconn, Jewar

India’s first display-driver-focused ATMP plant, near the new Noida International Airport. Approved May 2025 at ~₹3,706 crore; construction started February 2026; operations targeted 2027.

Odisha

SiCSem + 3D Glass, Bhubaneswar

SiCSem is India’s first commercial silicon carbide fab plus packaging (~₹2,067 crore, UK partner Clas-SiC). 3D Glass Solutions builds glass-substrate advanced packaging for RF, defence, HPC and photonics.

Punjab

CDIL, Mohali

An expansion of Continental Device India’s existing discrete-semiconductor plant, adding MOSFETs, IGBTs, Schottky diodes and transistors in both silicon and silicon carbide.

Andhra Pradesh

ASIP

A system-in-package assembly unit with South Korean partner APACT, approved August 2025, adding another backend node in a new state.

Semicon 1.0 vs Semicon 2.0

What the second phase changes.

 Semicon 1.0 (2021)Semicon 2.0 (2026)
Main aimCreate an initial manufacturing baseDeepen the ecosystem around it
Outlay₹76,000 crore₹1,27,500 crore
ManufacturingFabs and packaging unitsSilicon, compound, discrete and display fabs; advanced packaging
DesignDesign-linked incentive schemeStronger push on full-stack Indian chip IP
Equipment & materialsNot a focusNamed pillar — machinery, chemicals, gases
R&DLimitedFrontier tech beyond 28 nm; global institution tie-ups
TalentUniversity programmesIndustry-led research and training centres

The strategic logic: subsidising one more fab adds capacity, but does not create the tool vendors, gas suppliers, materials makers and IP houses a real semiconductor cluster runs on. Phase 2 is aimed at those gaps.

India vs Taiwan, Korea, China and the US

Different starting points, not a league table.

FactorIndiaTaiwanSouth KoreaChinaUnited States
Leading-edge fabsNot yetStrongStrongDeveloping under constraintsStrong design, expanding fabs
Memory manufacturingPackaging onlyLimitedGlobal leaderExpandingMicron
OSAT / packagingRapidly expandingMatureStrongStrongExpanding
Chip designStrongStrongStrongStrongGlobal leader
Equipment & materialsEmergingDeep supply baseStrongExpandingStrong

A more useful question than “can India replace Taiwan?” is “can India become a second major manufacturing base?” Supply chains tend to diversify rather than relocate wholesale, driven by geopolitics, resilience, subsidies, customer diversification, talent and cost — not by a single “China plus one” slogan.

Isn’t 28 nm old technology?

No — not for most of what chips actually do. Leading-edge AI processors use much smaller nodes, but 28 nm-class technology runs the majority of automotive, power-management, microcontroller, communications and industrial chips, where a qualified, reliable, long-lived process matters more than transistor count. “Older than the leading edge” is not the same as “obsolete”. The better term is mature node, not “legacy”.

Will Dholera make Nvidia-class AI GPUs?

There is no basis to assume that. Frontier AI accelerators depend on sub-5 nm fabrication and advanced 2.5D/3D packaging ecosystems that India does not have. Dholera’s announced 28–110 nm range targets different but economically important markets. India’s realistic path toward AI silicon runs through design and domestic IP, then packaging and chiplets, then specialised accelerators — and possibly more advanced fabrication later. It does not jump straight from OSAT to GPUs.

What a semiconductor fab needs

Silicon wafers — largely imported
Specialty gases, wet chemicals, photoresist — mostly imported today; a Semicon 2.0 target
Lithography, deposition, etch, metrology tools — ASML, Applied Materials, Lam Research, Tokyo Electron, KLA
Cleanroom, ultra-pure water, uninterrupted power — built into the site
Process, yield, equipment and packaging engineers — the workforce gap Semicon 2.0 targets

Why water and power matter

Fabs repeatedly rinse wafers with ultra-pure water — municipal water treated to remove almost all ions, particles and organics — so a fab needs both a large water source and its own purification plant. It also needs stable, high-quality electricity: a power dip measured in milliseconds can ruin a batch of wafers, so fabs build in redundancy and backup. Project-specific consumption figures should come from environmental filings, not generic “millions of litres” claims.

Capacity numbers: read them carefully

What the numbers mean

  • 50,000 wafers/month at Dholera is a wafer-start figure — each wafer holds many chips
  • 48 million units/day at Tata Assam is a packaged-unit figure at full ramp
  • “Commercial production started” means a line is running, not that it is at rated output
  • Cumulative ₹1.64 lakh crore is approved investment across all stages

What not to do with them

  • Don’t treat 50,000 wafers as 50,000 chips
  • Don’t compare wafers/month against chips/day — different manufacturing stages
  • Don’t rank “Assam is X times bigger than Dholera” from mismatched units
  • Don’t read approved investment as money already spent

Is India making “Made in India chips”?

Yes, with a caveat about what the phrase means. For Micron, the wafer is fabricated abroad and the chip is assembled and tested in India. For a future Dholera chip, the silicon wafer itself is intended to be fabricated in India. Both are legitimate uses of “Made in India”, but they describe different depths of manufacturing. And no country is fully self-sufficient across design, EDA tools, equipment, materials, fabs, memory and packaging — the realistic goal is greater supply-chain resilience and domestic capability, not complete “chip sovereignty”.

Things worth knowing

  • PSMC (Tata’s fab partner) and TSMC are different companies — do not confuse them.
  • Micron, Kaynes and CG Semi are the three plants in commercial production; all three are backend, not fabs.
  • The India Semiconductor Mission began in 2021 with ₹76,000 crore; Semicon 2.0 adds ₹1,27,500 crore.
  • The FY2026–27 Budget’s ₹1,000 crore line for the mission is an annual provision, not the programme total.
  • Silicon carbide (SiCSem) is a compound semiconductor for EVs and power electronics, not a silicon-logic fab.
  • Even a domestic fab depends on ASML, Applied Materials, Lam Research, Tokyo Electron and KLA for tools.
  • The Adani–Tower Maharashtra fab has never had central approval under the semiconductor programme.

How AiTimeline tracks semiconductor projects

We use a fixed set of status labels so a ribbon-cutting is not mistaken for a mature industry. Proposed: announced only. Approved: formal Government of India approval. Under construction: physical site work underway. Pilot: a limited production or test line. Commercial production: company or government confirms commercial operations. Full ramp: rated production reached or formally reported. For each facility we separate announcement date, approval date, construction start, pilot and commercial-production date — they are different milestones and are often reported as if interchangeable.

Has Micron started production in India?
Yes. Micron inaugurated its Sanand assembly and test facility on 28 February 2026 and it is in commercial operation, packaging and testing DRAM and NAND memory. The wafers themselves are fabricated in Micron’s plants outside India.
Which semiconductor plants are producing in India?
Three as of August 2026: Micron Sanand (from February 2026), Kaynes Semicon Sanand (from March 2026) and CG Semi Sanand (from July 2026). All three are assembly, packaging and test plants, not wafer fabs.
When will Tata’s Dholera fab start production?
First or trial wafers are targeted for late 2026 by Tata and government sources, with a commercial ramp across 2027 and 2028. Some industry reporting expects commercial-scale output only around mid-2028. All of these are targets, not confirmed dates.
How much has India allocated to Semicon 2.0?
The Union Cabinet approved Semicon 2.0 on 15 July 2026 with an outlay of ₹1,27,500 crore. This is the total programme figure; the FY2026–27 Budget separately provided ₹1,000 crore toward launching it.
Is the Adani semiconductor fab approved?
Not centrally. Maharashtra approved the proposed Adani–Tower project at state level in 2024, and it reached appraisal stage under the India Semiconductor Mission, but it never received central approval. Adani paused talks with Tower Semiconductor in 2025.

Frequently asked questions

Does India manufacture semiconductor chips in 2026?
Yes, in the backend sense. Micron, Kaynes Semicon and CG Semi run commercial plants in Gujarat that assemble, package and test chips. India does not yet fabricate silicon wafers at commercial scale; the first fab, at Dholera, is under construction.
What does Micron make in Sanand?
Micron’s Sanand plant assembles and tests memory. DRAM and NAND wafers fabricated elsewhere in Micron’s global network are turned into finished memory and storage products. It is an ATMP facility, not a memory fab.
Does Micron fabricate DRAM wafers in India?
No. No DRAM or NAND wafers are fabricated in India. Micron’s Sanand facility only performs assembly, packaging, marking and test on wafers made in its fabs abroad.
What is India’s first semiconductor fab?
The Tata Electronics–PSMC plant at Dholera, Gujarat. It is a pure-play 300 mm foundry planned for 50,000 wafers per month at 28 nm to 110 nm nodes, and is under construction as of August 2026.
What chips will Tata Dholera manufacture?
Mature-node logic and specialty chips: power-management ICs, display drivers, microcontrollers and high-performance-computing logic, aimed at automotive, computing, communications and data-storage customers. Not leading-edge AI processors.
What is the difference between a fab and an OSAT?
A fab builds integrated circuits on silicon wafers using lithography, deposition and etch. An OSAT takes fabricated wafers or dies and does assembly, packaging and testing. Tata’s Dholera project is a fab; Micron, CG Semi and Kaynes operate backend assembly and test plants.
What is ATMP?
Assembly, Testing, Marking and Packaging — the backend of chip manufacturing, where fabricated dies are packaged into finished chips, marked with part information and tested. It is the same part of the chain that “OSAT” refers to. Micron Sanand is an ATMP plant.
How many semiconductor plants does India have?
About 10 manufacturing units were approved under the India Semiconductor Mission through early 2025, expanded toward a dozen with four approvals in August 2025 and two in May 2026. Three are in commercial production; the rest are under construction or approved.
What is the India Semiconductor Mission?
A government programme launched in 2021 with a ₹76,000 crore outlay to build domestic chip manufacturing — fabs, compound-semiconductor and packaging units, a display fab — plus a design-linked incentive scheme. It is run under the Ministry of Electronics and Information Technology.
What is Semicon 2.0?
The second phase of the India Semiconductor Mission, approved by the Cabinet on 15 July 2026 with a ₹1,27,500 crore outlay. It targets chip design and IP, equipment and materials, fabs, advanced packaging, R&D beyond 28 nm, and workforce development.
What is Tata’s Assam semiconductor plant?
The Tata Semiconductor Assembly and Test facility at Morigaon, Assam — an OSAT/ATMP plant, not a wafer fab, with an approved value near ₹27,120 crore and a planned full-ramp capacity of 48 million packaged units a day. It is under construction and not yet confirmed operational.
What is CG Semi?
An OSAT joint venture of CG Power (Murugappa Group), Renesas Electronics of Japan and Stars Microelectronics of Thailand, at Sanand, Gujarat. Approved value is about ₹7,584 crore. It began commercial production on 4 July 2026.
Has Kaynes started chip production?
Yes. The Kaynes Semicon OSAT plant at Sanand was inaugurated on 31 March 2026 and began production the same day, making power modules and packaged devices for EV, industrial and consumer use.
Is India making AI chips?
India designs AI chips and is building packaging capacity relevant to AI hardware, but it does not fabricate leading-edge AI accelerators. The realistic near-term path runs through design, domestic IP, chiplets and advanced packaging rather than frontier fabrication.
Can India manufacture Nvidia chips?
No. Nvidia’s data-centre GPUs are fabricated on sub-5 nm nodes with advanced packaging that no Indian plant can currently provide. Dholera’s planned 28–110 nm range targets automotive, power and industrial chips instead.
Why does India need semiconductor fabs?
To reduce import dependence for a critical input, capture more manufacturing value, support automotive and electronics industries, and build strategic resilience. Governments subsidise fabs because the capital cost and risk are high but the supply-chain and security value is judged higher.
Why do semiconductor fabs need so much water?
Fabs rinse wafers many times during manufacturing with ultra-pure water — municipal water treated to remove nearly all ions, particles and organic matter. A large fab needs both a reliable water source and its own on-site purification plant.
Why are semiconductor fabs so expensive?
A fab needs vibration-isolated cleanrooms, ultra-pure utilities and a full set of lithography, deposition, etch and metrology tools that each cost millions to tens of millions of dollars, plus years of process development before it produces sellable chips at good yield.
Can India compete with Taiwan?
Not at leading-edge fabrication in this decade. A more realistic goal is to become a second significant base for mature-node fabrication, packaging and test, adding resilience to a supply chain that is heavily concentrated in Taiwan and Korea.
What is a pure-play foundry?
A fab that manufactures chips designed by its customers and does not primarily sell its own branded chips. The customer owns the design; the foundry runs the process. Tata describes the Dholera fab as India’s first pure-play foundry project.
What is semiconductor yield?
The percentage of chips on a wafer that meet performance and quality requirements. Higher yield means more sellable chips per wafer, lower unit cost and more predictable output. A new process can be “in production” long before its yield is commercially mature.
Does 50,000 wafers a month mean 50,000 chips a month?
No. A single 300 mm wafer can carry hundreds or thousands of chips depending on chip size. Wafer-start capacity and chip output are different numbers, and one cannot be read off the other without knowing die size and yield.
Is silicon carbide the same as a normal chip?
No. Silicon carbide is a compound semiconductor used mainly for power electronics — EV inverters, fast chargers, grid equipment — because it handles high voltage and heat better than silicon. SiCSem in Odisha is India’s first commercial silicon carbide fab.
What is advanced packaging and why does it matter for AI?
Advanced packaging bonds multiple chips — logic, memory, chiplets — into one dense module using 2.5D or 3D integration. AI accelerators depend on it to place high-bandwidth memory next to compute. India’s 3D Glass Solutions project targets part of this space; today’s Indian OSAT plants do not run Nvidia-style CoWoS.
Is 28 nm obsolete technology?
No. It is a mature node, not a dead one. Most automotive, power-management, microcontroller and industrial chips are built on 28 nm-class or larger processes, where reliability and long supply life matter more than transistor density.
Who is PSMC and how is it different from TSMC?
PSMC is Powerchip Semiconductor Manufacturing Corporation, a Taiwanese foundry focused on mature nodes and Tata’s technology partner at Dholera. TSMC is Taiwan Semiconductor Manufacturing Company, a much larger leading-edge foundry. They are separate companies.
How many design startups is India supporting?
At the Semicon 2.0 approval the government cited 105 startups with access to electronic design automation tools, alongside 24 approved chip-design projects and training reaching hundreds of universities and tens of thousands of students.
Does India have chip sovereignty?
No country does. Design, EDA software, equipment, materials, fabs, memory and packaging are spread across many countries. India’s realistic aim is greater domestic capability and supply-chain resilience, not full self-sufficiency.
What should be measured by 2030?
Operating fabs and their yield, total wafer starts, OSAT plants at rated capacity, advanced-packaging capability, Indian-designed chips in production, local materials and equipment suppliers, export customers and repeat private investment — not the number of announcements.
Will India produce sub-20 nm chips by 2030?
No approved project or official roadmap currently commits to that. Semicon 2.0 supports equipment, materials, design, packaging and R&D without guaranteeing a specific process node by a specific year.

The harder milestones come after the ribbon-cutting

A ribbon-cutting ceremony is not the same as a mature semiconductor industry. The difficult milestones come afterward: equipment has to run reliably, production yields have to improve, customers have to qualify the chips, suppliers have to locate nearby, and factories have to keep producing at commercial scale for years.

That is why India’s semiconductor story should now be measured less by the number of announcements and more by what is actually coming off production lines.

India’s chip story has moved from announcements to production

India’s semiconductor push entered a different phase in 2026. Micron began assembly and test operations in Sanand. Kaynes moved into production. CG Semi began commercial output. Those milestones matter because they replace future-tense promises with physical production.

But the most technically difficult step is still ahead. India has to bring large-scale wafer fabs into reliable commercial operation, develop local materials and equipment suppliers, raise manufacturing yields and build deeper advanced-packaging capability. Tata’s Dholera fab will be one of the most important industrial tests of the decade. If it succeeds, India will no longer be only a place where chips are designed and packaged — it will also be a place where the silicon itself is manufactured at commercial scale.

2026 proved India can start producing semiconductor products. The next test is whether it can build an entire chip ecosystem around them.

Explore related timelines

⚠️ How AiTimeline tracks India’s semiconductor build-out

We classify each project as proposed, approved, under construction, pilot, commercial production or full ramp, and update status as facts develop. Investment figures are approved project values from Government of India and company statements, not money already spent, and mix private capital with central incentives and state support. This article is editorial and AI-assisted, compiled from public sources including PIB and Cabinet releases, PMIndia, the India Semiconductor Mission, Micron, Tata Electronics, CG Power, Kaynes Technology, Reuters, Business Standard, The Economic Times and TrendForce. It is not investment advice. Information may contain inaccuracies; corrections are made as the projects progress.