← AiTimeline Home

Energy · India · Nuclear Capacity Tracker

India Nuclear Power Timeline 2026–2047: The 100 GW Race, Private Companies & SMRs

📅 Updated 27 August 2026Current fleet ~8.8 GW2047 target 100 GW
Advertisement

View as Web Story

In short

Track India's nuclear power push to 2047: current capacity, reactors under construction, Bharat SMRs, private-sector entry, the PFBR and the gap to 100 GW.

India’s nuclear-power challenge fits into two numbers: roughly 8.8 GW of installed capacity today and a 100 GW ambition for 2047. Closing that gap needs far more than a few extra large reactors. India would have to accelerate its indigenous 700 MW pressurised heavy-water reactor (PHWR) programme, demonstrate small modular reactors (SMRs), settle financing and liability questions under the new SHANTI Act, 2025, bring private companies such as Tata Power, Reliance and Adani into the sector, and unlock stalled foreign projects at Jaitapur and Kovvada. The 100 GW figure is a target, not a forecast — and this page tracks the distance between the two.

India Nuclear Power Timeline 2026–2047: The 100 GW Race, Private Companies & SMRs

Data verified: 27 August 2026. Capacity figures below lead with Department of Atomic Energy / NPCIL numbers; where the World Nuclear Association or IAEA differ, the difference is noted. Every future date is labelled target, sanctioned, under construction or expected — never as a certainty.

⚠️ How to read this page. Nuclear capacity is reported inconsistently by different bodies (gross vs net, whether long-shut units are counted). Figures below lead with the Department of Atomic Energy (DAE) / Nuclear Power Corporation of India (NPCIL) numbers and note where the World Nuclear Association or IAEA PRIS differ. Every future date is labelled target, sanctioned, under construction or expected — not as a certainty. This is an energy-policy explainer, not investment advice.

🧠 The 60-second answer

As of 27 August 2026 India operates roughly 24 nuclear reactors totalling about 8,780 MW (8.8 GW) gross — close to 3% of the country’s electricity generation and under 2% of installed capacity. The World Nuclear Association lists a lower net figure (~7.9 GWe) because it uses net output and excludes units in long shutdown. Eight reactors (~6 GW) are under construction. The official near-term goal is ~22,480 MW by 2031–32; the long-term goal, announced in the 2025–26 Union Budget, is at least 100 GW by 2047. Reaching it depends on the 700 MW PHWR fleet, five indigenous SMRs targeted for 2033, private-sector entry enabled by the SHANTI Act, 2025, and foreign large reactors that have not yet started construction. On today’s building pace, 100 GW by 2047 is possible but far from guaranteed.

⚡ India’s Nuclear Power Dashboard
~8.8 GW
Current capacity
24
Operating reactors
8 / ~6 GW
Under construction
~22.5 GW
2031–32 target
100 GW
2047 target
~8.8%
Of the 2047 goal
~91 GW
Still required
2033
First 5 SMRs (target)
Data verified: 27 August 2026 · Sources: DAE, NPCIL, Union Budget 2025–26, World Nuclear Association
⚡ Nuclear India Quick Facts
Installed capacity~8,780 MW, 24 reactors (DAE/NPCIL, 2026)
Share of India’s power capacity~1.8% of ~485 GW installed; ~3% of generation
OperatorNPCIL (all commercial units); BHAVINI (fast breeder)
Newest milestonePFBR first criticality, 6 April 2026, Kalpakkam
Nuclear Energy Mission₹20,000 crore for SMR R&D (Budget 2025–26)
Legal resetSHANTI Act, 2025 — enacted Dec 2025; rules in draft
⚡ Quick Answers — AI Overview Ready

India’s 100 GW Nuclear Target: Key Questions

How much nuclear power does India have in 2026?
About 8,780 MW (8.8 GW) from 24 operating reactors at seven sites, per DAE and NPCIL. The World Nuclear Association lists a slightly lower net figure (~7.9 GWe) because it excludes units in long-term shutdown and uses net output. Nuclear supplies roughly 3% of India’s electricity.
What is India’s 100 GW nuclear target?
In the 2025–26 Union Budget, the finance minister said developing at least 100 GW of nuclear capacity by 2047 is “essential” for India’s energy transition. It is a government aspiration for the centenary of independence, not a committed construction schedule.
Can India realistically reach 100 GW by 2047?
Possible, but far from guaranteed. It would require roughly a ten-fold increase in about 21 years, a much faster build rate than India has ever sustained, plus successful SMRs, large private investment and foreign reactors that have not yet broken ground.
What is a Small Modular Reactor (SMR)?
A smaller nuclear reactor, typically under 300 MWe, designed for factory-built modular assembly. India is developing three indigenous designs and targets at least five operational by 2033, aimed at captive industrial power and replacing retiring coal units.
📚 Key Takeaways

What to know about India’s nuclear expansion

  • Starting point: ~8.8 GW and 24 reactors in 2026 — about 8.8% of the 2047 goal.
  • Nearer test: the official ~22.5 GW target for 2031–32 is far more measurable than 2047, and even it needs every under-construction reactor finished on time.
  • Workhorse: the indigenous 700 MW PHWR, built in “fleet mode,” carries most of the near-term additions — Kakrapar, Rajasthan, Kaiga, Gorakhpur, Mahi Banswara.
  • Stage 2 unlocked: the 500 MWe Prototype Fast Breeder Reactor reached first criticality on 6 April 2026, decades behind its original schedule.
  • SMRs are still R&D: the ₹20,000 crore Nuclear Energy Mission funds three designs (BSMR, SMR-55, a gas-cooled unit); none is operating yet.
  • Bharat Small Reactors: a separate 220 MW PHWR-derived captive reactor offered to industry — six firms including Tata Power, Reliance and Adani Power have responded to NPCIL’s tender.
  • SHANTI Act, 2025 replaced the 1962 Atomic Energy Act and the 2010 liability law, introduced a sliding-scale operator liability cap and, for the first time, opened nuclear power to private and foreign investment — with foreign direct investment capped at 49% and the state keeping majority control. Its detailed rules were still in draft consultation in August 2026.
  • Foreign large reactors at Jaitapur (EDF) and Kovvada (Westinghouse) are still pre-construction; only Russia’s Kudankulam is actively building.
  • Scale check: China has roughly 55–60 GW operating and about 30 GW under construction; India’s under-construction fleet is a fraction of that, and China is adding reactors several times faster.
  • NPCIL alone targets about 54 GW by 2047 — the rest of the 100 GW must come from JVs, private reactors, foreign vendors and SMRs.

Can India really reach 100 GW of nuclear power by 2047?

The direct answer, then the reasons.

Possible, but far from guaranteed. India would need to add roughly 91 GW in about 21 years — close to a ten-fold expansion — against a historical record of adding a few hundred megawatts per year. The target requires several things to go right at once, none of them certain.

The constraints stack up:

  1. Construction rate. India has rarely commissioned more than one reactor a year. Fleet-mode standardisation of the 700 MW PHWR is meant to change that, but the first fleet units are only now pouring concrete.
  2. Financing. NPCIL’s balance sheet cannot fund 100 GW. That is the explicit reason for inviting private capital and forming the NPCIL–NTPC joint venture, ASHVINI.
  3. Manufacturing capacity. Heavy forgings, reactor pressure vessels, steam generators and specialty steel are supplied by a small group of firms (L&T, BHEL, Walchandnagar). Scaling the supply chain takes years.
  4. Sites and land. Large nuclear sites face local opposition (Jaitapur, Kovvada, Mithi Virdi). SMRs on retiring coal-plant land are proposed partly to sidestep this.
  5. Regulatory throughput. The Atomic Energy Regulatory Board (AERB) reviews every design and site; it received statutory status only under the SHANTI Act.
  6. Fuel. Domestic uranium is limited; imports cover much of the fleet. A ten-fold expansion multiplies the fuel-supply problem.
  7. Liability and private appetite. The SHANTI Act eased supplier liability, but private firms have not yet taken final investment decisions.
  8. Foreign technology. Jaitapur and Kovvada together represent ~20 GW of the plan and have not started.
  9. SMR commercialisation. No Indian SMR has been built. The 2033 target for five units is ambitious for a first-of-a-kind programme.

This page treats 100 GW as a government target and tracks whether the milestones that feed it — the next reactor to reach commercial operation, the next PFBR step, the first SMR demonstration, the 2031–32 capacity figure — are actually moving.

What does 100 GW actually mean?

100 GW is 100,000 MW — more than eleven times today’s ~8.8 GW nuclear fleet. For context, India’s total installed electricity capacity is about 485 GW (mid-2026), of which coal is roughly 218 GW, solar around 110 GW and wind about 51 GW. Nuclear is currently under 2% of installed capacity.

Capacity comparisons can mislead, because plants run at very different capacity factors — the share of the year they actually generate. Indian nuclear plants have run at roughly 75–85% in recent years; solar in India is around 20%; coal around 60–70%. So 100 GW of nuclear would generate far more electricity annually than 100 GW of solar. If India’s nuclear fleet reached 100 GW and ran at ~80%, it would produce on the order of 700 billion units a year — comparable to a large share of today’s total consumption. That is the scale of the ambition, and the reason it is a 22-year project rather than a five-year one.

The 100 GW gap, visualised

Four states of capacity — do not read planned capacity as operating.

Where the 100 GW would come from (approximate, 2026)

Toward 100 GW~8.8 operating · ~6 building · ~15 sanctioned · ~70 gap
Operating ~8.8 GW Under construction ~6 GW Sanctioned / approved ~15 GW Still unaccounted ~70 GW

Even counting every operating, under-construction and sanctioned reactor, roughly 70 GW of the 2047 target has no project attached to it yet. That is the capacity that must come from SMRs, large private and foreign reactors, and projects not yet announced. NPCIL’s own internal aim is about 54 GW by 2047; the remainder depends on ASHVINI, private Bharat Small Reactors, foreign large reactors and the SMR programme all succeeding.

India’s nuclear timeline: 1948 to 2047

Newest developments first; the institutional story runs to the bottom.

2047
TARGET

100 GW nuclear capacity — target, not forecast

Government aspirationCentenary of independence

Status: Aspirational target stated in the 2025–26 Union Budget. No committed year-by-year construction plan exists for the full 100 GW.

Why it matters: It frames every nearer-term decision — fleet-mode PHWRs, the SMR mission, private-sector entry and liability reform are all justified by reference to it.

Reaching 100 GW would need roughly 91 GW of new capacity in ~21 years — far above any pace India has sustained.
TARGET~11x today
2033
TARGET

At least five indigenous SMRs targeted for operation

Nuclear Energy Mission₹20,000 crore

Status: Target set in the 2025–26 Budget. As of August 2026 the designs (BSMR, SMR-55, a small high-temperature gas-cooled reactor) are in design and detailed-project-report stage; none is under construction.

Why it matters: SMRs are the government’s route to captive industrial power and to using retiring coal-plant sites. Missing 2033 would push the 100 GW maths further out.

A BSMR-300 detailed project report was released by BARC and NPCIL on 14 August 2026.
TARGETR&D STAGE
2031–32
OFFICIAL

~22,480 MW near-term capacity goal

DAE / NPCIL projectionParliament answers

Status: Official projection. Depends on completing Kudankulam 3–6, Rajasthan 7–8, the first fleet-mode PHWRs and the PFBR reaching commercial operation.

Why it matters: This is the checkpoint that will actually show whether the programme is accelerating — it is close enough that the reactors responsible already exist on site.

Going from ~8.8 GW to ~22.5 GW means roughly 2 GW of net additions per year through 2032 — itself a step change.
OFFICIAL PROJECTION

Gorakhpur first concrete; ASHVINI tenders Mahi Banswara

Haryana & RajasthanFleet-mode 700 MW PHWR

Development: First safety-related concrete for the Gorakhpur Haryana Anu Vidyut Pariyojana Units 1&2 (2×700 MW) began on 14 August 2026. The NPCIL–NTPC joint venture ASHVINI floated a ~₹28,000 crore Nuclear Island EPC tender for Mahi Banswara (4×700 MW, Rajasthan).

Why it matters: These are the first fleet-mode units where a JV and private EPC contracting model are being tested at scale.

Mahi Banswara’s foundation stone was laid in September 2025; first concrete for its initial two units followed in March 2026.
UNDER CONSTRUCTIONJV MODEL

Prototype Fast Breeder Reactor reaches first criticality

Kalpakkam, Tamil NaduBHAVINI · 500 MWe

Development: The 500 MWe PFBR attained first criticality on 6 April 2026 after AERB clearance, formally opening Stage 2 of India’s three-stage programme. Grid connection and commercial operation are expected later in 2026.

Why it matters: Fast breeders produce more fissile material than they consume, and are the bridge to Stage 3 thorium reactors. The PFBR is roughly 12 years behind its original target date.

It runs on a mixed uranium-plutonium oxide core with a thorium blanket — the first step toward using India’s large thorium reserves.
MILESTONESTAGE 2

SHANTI Act, 2025 enacted

ParliamentPassed 17–18 Dec; assent 20 Dec 2025

Development: The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India Act, 2025 replaced the Atomic Energy Act, 1962 and the Civil Liability for Nuclear Damage Act, 2010 with a single framework. It set a size-graded operator liability cap (about ₹100 crore for the smallest reactors and fuel-cycle facilities up to ₹3,000 crore for the largest plants), limited a supplier’s exposure to what the contract specifies, gave the Atomic Energy Regulatory Board statutory status, and opened nuclear power to private and foreign investment — with FDI capped at 49% and the state retaining majority control and all sensitive fuel-cycle steps.

Why it matters: It removed the single biggest legal blocker cited by foreign vendors since 2010. But the Act is a framework: the draft SHANTI Rules and draft AERB regulations that make it operational were out for public consultation into September 2026, so no private project could actually start yet.

Total damages from an incident remain backed by the Union up to 300 million SDR (about ₹3,900 crore), and India’s Nuclear Insurance Pool (₹1,500 crore, set up in 2015) still underwrites operator liability.
LAW ENACTEDRULES IN DRAFT

Nuclear Energy Mission and the 100 GW goal announced

Union Budget 2025–261 February 2025

Development: The finance minister announced a Nuclear Energy Mission with a ₹20,000 crore outlay for SMR research and development, a target of at least five indigenous SMRs operational by 2033, and the statement that 100 GW of nuclear by 2047 is “essential” for the energy transition. Amendments to the Atomic Energy Act and the liability law were promised in the same speech.

Why it matters: It was the moment nuclear moved from a slow state programme to a headline energy-policy priority with money and legal reform attached.

The announcement came days before the prime minister’s visits to the United States and France, both home to stalled reactor deals.
POLICY SHIFT
2017
& on

Fleet mode sanctioned; PFBR core-loading begins

New Delhi & Kalpakkam

Development: In 2017 the Union Cabinet sanctioned ten indigenous 700 MW PHWRs in “fleet mode” (Kaiga 5&6, Gorakhpur 1–4, Mahi Banswara 1–4, Chutka 1&2) — identical design, bulk procurement and repeat contractors to cut build time. Core-loading of the PFBR’s first fuel began in 2024, ahead of its April 2026 criticality.

Why it matters: Fleet mode is the mechanism meant to lift India’s build rate; its success or failure over 2026–2032 will largely determine the 2047 trajectory.

Fleet mode aims to bring each 700 MW unit’s construction time closer to five years from first concrete.
SANCTIONED
2023
& 2024

First indigenous 700 MW PHWRs enter service at Kakrapar

Kakrapar, Gujarat

Development: Kakrapar Unit 3 reached first criticality in 2020 and commercial operation in June 2023; Unit 4 followed in March 2024. These are India’s first 700 MW PHWRs, scaled up from the proven 540 MW design with added passive safety systems.

Why it matters: The 700 MW PHWR is the standard design for the entire near-term expansion — Rajasthan 7&8, Kaiga, Gorakhpur, Mahi Banswara all use it.

Rajasthan Unit 7, another 700 MW PHWR, reached its full 700 MW output for the first time in February 2026.
700 MW ERA
2013
+

Kudankulam: Russian VVER reactors come online

Tamil NaduRosatom cooperation

Development: Kudankulam Unit 1 (1,000 MW VVER) was connected to the grid in 2013 and Unit 2 in 2016. Units 3&4 and 5&6 are under construction under successive India–Russia agreements.

Why it matters: Kudankulam is India’s only large foreign-technology site actively building, and is planned to become its single largest nuclear station at six units.

Fuel for Units 3&4 was delivered in December 2025; the reactor vessel for Unit 6 shipped from Russia in January 2025.
FOREIGN TECHUNDER CONSTRUCTION

Civil Liability for Nuclear Damage Act

Parliament

Development: India enacted a nuclear liability law with a ~₹1,500 crore operator cap and, controversially, a supplier right-of-recourse (Section 17b) that let operators claim against equipment suppliers after an accident.

Why it matters: The supplier clause — a response to the Bhopal disaster — deterred Westinghouse, GE and Areva/EDF from proceeding, freezing the reactor imports the 2008 deal was meant to enable. It was the problem the SHANTI Act set out to fix 15 years later.

No foreign-supplied large reactor has begun construction in India in the 15 years since this law passed.
FRICTION POINT

India–US civil nuclear agreement and NSG waiver

Washington & Vienna

Development: After separating its civilian and military facilities and accepting IAEA safeguards on civilian reactors, India received a Nuclear Suppliers Group waiver in September 2008, ending the trade embargo imposed after its 1974 nuclear test.

Why it matters: It restored India’s access to imported uranium and foreign reactor technology — but the immediate wave of reactor construction it promised did not materialise, largely because of the 2010 liability law.

The waiver let India sign uranium-supply agreements with Russia, Kazakhstan, Canada, Australia and others.
DIPLOMATIC MILESTONE
1969
& on

Tarapur, then the indigenous PHWR programme

Maharashtra, Rajasthan, Tamil Nadu

Development: India’s first commercial nuclear station, Tarapur (two US-built boiling water reactors), started in 1969. After the 1974 test and the resulting embargo, India shifted to indigenous pressurised heavy-water reactors fuelled by natural uranium, commissioning units at Rawatbhata, Kalpakkam, Narora, Kakrapar and Kaiga through the 1980s and 1990s.

Why it matters: Isolation forced self-reliance. The PHWR became the backbone of the fleet precisely because it does not need enriched uranium, which India could not import.

Around 90% of India’s current reactors are indigenous PHWRs.
INDIGENOUS CAPABILITY
1948
& 1954

Atomic Energy Commission and Department of Atomic Energy

MumbaiHomi Bhabha

Development: India set up the Atomic Energy Commission in 1948 and the Department of Atomic Energy in 1954, both driven by physicist Homi Bhabha, who also framed the three-stage programme built around India’s thorium reserves.

Why it matters: The institutional architecture — state-owned, DAE-led, secrecy-bound — shaped the sector for 75 years. The SHANTI Act and private-sector entry are the first structural break from it.

Bhabha’s 1954 three-stage plan — PHWR, then fast breeder, then thorium — is still the official roadmap.
FOUNDATION

India’s nuclear reactor tracker

Operating, under construction, sanctioned and proposed — kept in separate categories.

Site / unitsStateTechnologyCapacityStatusOperator
Tarapur 1–4MaharashtraBWR (1–2), PHWR (3–4)2×160 + 2×540 MW🟢 OperatingNPCIL
Rawatbhata (RAPS) 1–6RajasthanPHWR~1,180 MW total in service🟢 Operating (RAPS-1 in long shutdown)NPCIL
Kudankulam 1–2Tamil NaduVVER-1000 (Russia)2×1,000 MW🟢 OperatingNPCIL
Kakrapar 1–4GujaratPHWR (220 & 700 MW)2×220 + 2×700 MW🟢 Operating (Unit 4 commercial 2024)NPCIL
Kaiga 1–4KarnatakaPHWR4×220 MW🟢 OperatingNPCIL
Madras / MAPS 1–2Tamil NaduPHWR2×220 MW🟢 OperatingNPCIL
Narora 1–2Uttar PradeshPHWR2×220 MW🟢 OperatingNPCIL
Rajasthan 7–8 (RAPP)RajasthanPHWR-7002×700 MW🟢/🟠 Unit 7 at full power Feb 2026; Unit 8 commissioningNPCIL
Kudankulam 3–6Tamil NaduVVER-1000 (Russia)4×1,000 MW🟠 Under constructionNPCIL
Kaiga 5&6KarnatakaPHWR-7002×700 MW🟠 Under construction (first concrete 2026)NPCIL
Gorakhpur (GHAVP) 1&2HaryanaPHWR-7002×700 MW🟠 Under construction (first concrete Aug 2026)NPCIL
PFBRTamil Nadu (Kalpakkam)Fast breeder (FBR)500 MWe🟠 Criticality Apr 2026; commercial operation pendingBHAVINI
Mahi Banswara 1–4RajasthanPHWR-7004×700 MW🔵 Sanctioned; early works under ASHVINIASHVINI (NPCIL–NTPC)
Chutka 1&2Madhya PradeshPHWR-7002×700 MW🔵 SanctionedNPCIL
Gorakhpur 3&4HaryanaPHWR-7002×700 MW🔵 SanctionedNPCIL
Jaitapur 1–6MaharashtraEPR (France)6×~1,650 MW (~9,900 MW)⚫ Proposed; pre-constructionNPCIL / EDF
Kovvada 1–6Andhra PradeshAP1000 (US)6×~1,100 MW⚫ Proposed; pre-constructionNPCIL / Westinghouse
Bharat Small ReactorsMultiple (16 sites shortlisted)PHWR-derived ~220 MWPer-unit ~220 MW⚫ Proposed; industry tender stageNPCIL + private captive users

Capacities are indicative and drawn from NPCIL, DAE and World Nuclear Association data as of August 2026. A reactor is only ever counted in one category; when a unit moves from “under construction” to “operating,” this table and the dashboard are updated.

What powers India’s nuclear fleet today?

PHWR (pressurised heavy-water reactor) — India’s workhorse. Uses natural (unenriched) uranium and heavy water as moderator and coolant. About 90% of the fleet. Indigenous 220, 540 and now 700 MW designs.

VVER (Russian pressurised water reactor) — the 1,000 MW units at Kudankulam. Uses enriched uranium and light water; fuel supplied by Russia.

BWR (boiling water reactor) — the two original 1969 units at Tarapur, US-built, now the oldest running reactors in India.

Fast breeder reactor (FBR) — the PFBR at Kalpakkam, which reached criticality in April 2026. Uses a plutonium-uranium oxide core and breeds more fuel than it burns; Stage 2 of the three-stage plan.

SMRs and future designs — the Bharat Small Modular Reactor, SMR-55 and a high-temperature gas-cooled reactor are all in development. None is operating.

India’s three-stage nuclear strategy

Bhabha’s 1954 roadmap — and where each stage actually stands.

Stage 1 — PHWRsMature

Natural-uranium heavy-water reactors that also produce plutonium in spent fuel. This is essentially the entire operating fleet today.

Stage 2 — Fast breeder reactorsJust started

Reactors fuelled by the plutonium from Stage 1, wrapped in a thorium “blanket” that breeds uranium-233. The PFBR reached criticality in April 2026; two larger commercial breeders are planned at Kalpakkam.

Stage 3 — Thorium systemsResearch

Reactors running on uranium-233 bred from thorium, aimed at exploiting India’s large thorium reserves. The Advanced Heavy Water Reactor design is complete but unbuilt; the KAMINI research reactor at Kalpakkam is the only U-233-fuelled reactor operating anywhere.

Thorium is central to India’s long-term energy security, but no thorium reactor supplies the grid today, and commercial Stage 3 power is realistically decades away. Claims that India “runs on thorium” or could “switch to thorium” are wrong: thorium is fertile, not directly fissile, and must first be converted to uranium-233 inside a reactor.

Small modular reactors: what India is actually building

An SMR is a nuclear reactor of roughly 300 MWe or less, designed for factory manufacture and modular on-site assembly. India is interested in SMRs for captive power at hard-to-abate industries (steel, aluminium, cement), for siting on retiring coal-plant land with existing grid connections and water, and for remote or off-grid industrial demand. Globally SMRs are still at an early commercial stage; none is yet operating in India.

Bharat Small Reactor vs Bharat Small Modular Reactor

The two terms are different programmes and are easy to confuse:

  • Bharat Small Reactor (BSR) — a ~220 MW reactor derived from the proven indigenous PHWR, offered to industrial users for captive power. NPCIL builds and operates it; the industrial partner funds it and takes the electricity. NPCIL issued a request for proposals in December 2024; the deadline was extended to 31 March 2026.
  • Bharat Small Modular Reactor (BSMR) — a genuinely new modular design in the ~200–300 MWe range being developed by BARC and NPCIL. A BSMR-300 detailed project report was released on 14 August 2026. This is the design meant to be replicable and, eventually, exportable.
  • SMR-55 — a 55 MWe design aimed at smaller or remote loads.
  • High-temperature gas-cooled reactor — a small (~5 MW-thermal) unit aimed at hydrogen production.

Published specifications for these designs are still evolving; figures here follow BARC, NPCIL and Budget documents and should be treated as provisional.

₹20,000 crore Nuclear Energy Mission

Announced: Union Budget 2025–26, 1 February 2025. Outlay: ₹20,000 crore, primarily for SMR research, development and demonstration. Target: at least five indigenously developed SMRs operational by 2033. Legal support: amendments to the Atomic Energy Act and the liability law — delivered through the SHANTI Act, 2025.

Large reactor vs SMR

FactorLarge reactorSMR
Typical output700–1,650 MWe per unitUp to ~300 MWe per unit
Project scaleLarge, multi-year civil worksSmaller per unit; modular assembly
Total project capitalHigher per projectLower per project (but often built in groups)
Cost per kWProject-specific; benefits from scaleUncertain; first-of-a-kind premium likely
Deployment maturityEstablished worldwideEarly commercial stage globally
Grid roleLarge baseloadBaseload, captive power, coal-site replacement
Industrial captive powerLess typicalA core proposed use case

SMRs are not automatically cheaper per unit of electricity. Their appeal is a smaller, more financeable project size and shorter on-site construction, not a lower cost per kilowatt-hour — which for first-of-a-kind units may be higher. The distinction between lower total project cost and lower cost per unit of electricity matters and is often blurred in promotional material.

Why private companies matter to the 100 GW target

For 75 years, nuclear generation in India was reserved for the state — effectively NPCIL and BHAVINI. The SHANTI Act, 2025 changed that in principle: it lets private and foreign investors take equity in nuclear power projects (capped at 49%, with the state keeping majority control) and lets private firms lead engineering, procurement, construction and plant operation. The reason is capital — NPCIL cannot finance 100 GW alone — plus manufacturing, project-execution capacity and captive industrial demand. How far this goes in practice depends on the SHANTI Rules, still in draft as of August 2026.

What is actually happening, by category:

  • Joint venture: ASHVINI (Anushakti Vidyut Nigam Ltd), an NPCIL–NTPC JV, has been assigned the Mahi Banswara project (4×700 MW, Rajasthan) and has floated a ~₹28,000 crore Nuclear Island EPC tender for it.
  • Bharat Small Reactor tender: six firms — Hindalco, Jindal Steel & Power, Tata Power, Reliance Industries, JSW Energy and Adani Power — have submitted documents to NPCIL’s BSR request for proposals, identifying 16 candidate sites across six states.
  • NTPC’s own ambition: the state power giant has spoken of building around 30 GW of nuclear capacity by 2047 and joined the World Nuclear Association.

Who wants to enter India’s nuclear market?

CompanyType of interestVehicle / routeStatus
NTPCLarge PHWRs + SMRsASHVINI JV with NPCIL; BARC talksConfirmed JV; Mahi Banswara assigned
Tata PowerCaptive small reactorsNPCIL BSR tenderReported interest; documents submitted, no FID
Reliance IndustriesCaptive small reactorsNPCIL BSR tenderReported interest; documents submitted, no FID
Adani PowerCaptive small reactorsNPCIL BSR tenderReported interest; NDA stage, no FID
JSW EnergyCaptive small reactorsNPCIL BSR tenderReported interest; NDA stage, no FID
Jindal Steel & PowerCaptive power for steelNPCIL BSR tenderReported interest; documents submitted, no FID
HindalcoCaptive power for aluminiumNPCIL BSR tenderReported interest; documents submitted, no FID
Reported interest is not a project. “Company X is exploring nuclear” must not be read as “Company X nuclear plant coming in 203X.” None of the private firms above has taken a final investment decision, chosen a reactor design or begun construction. This section is updated only when a status genuinely changes.

Foreign reactor companies and India

CompanyCountryTechnologyIndian siteStatus
RosatomRussiaVVER-1000Kudankulam 3–6🟠 Under construction
EDFFranceEPR (6 units)Jaitapur, Maharashtra⚫ Pre-construction; techno-commercial talks; MoU with NTPC 2025
WestinghouseUSAAP1000 (6 units)Kovvada, Andhra Pradesh⚫ Pre-construction; US cleared Westinghouse to do licensing/design work in India (2025); no project agreement
HoltecUSASMR-160 / SMR-300Not sited⚫ US 10CFR810 authorisation to transfer SMR technology to Indian partners; no project
GE Vernova / GE HitachiUSA / JapanBWRX-300 SMRNot sited⚫ Reported interest / early discussions only

The main unresolved issue for every foreign vendor has been liability. The SHANTI Act eased it by limiting a supplier’s exposure to what its contract specifies. Foreign firms can also now take up to 49% equity in a project, but with an Indian entity as majority owner and licensed operator their core role stays technology supply and services. Kovvada and Jaitapur still need commercial and financing terms settled before any concrete is poured.

Kudankulam, Jaitapur and Kovvada

Kudankulam — the one that is building

Tamil Nadu’s Kudankulam site has two operating 1,000 MW Russian VVER units (2013, 2016) and four more under construction across two contracts. Fuel for Units 3&4 arrived in December 2025. Planned at six units, it is set to become India’s largest single nuclear station.

Jaitapur — approved on paper, not started

The Jaitapur project in Maharashtra would be the world’s largest single nuclear power station: six EDF EPR reactors, about 9,900 MW. An “Industrial Way Forward Agreement” was signed in 2018 and EDF submitted a binding techno-commercial offer, but no construction has begun. Financing, price and liability terms remain unresolved, and there is long-standing local opposition. EDF and NTPC signed an MoU in 2025 to explore Indian projects.

Kovvada — waiting on terms

The Andhra Pradesh site earmarked for six Westinghouse AP1000 reactors (~6,600 MW) has completed environmental assessment but not started construction. In 2025 Westinghouse and Larsen & Toubro formed a working group, and US export-control clearances advanced. The SHANTI Act removed the liability blocker; commercial terms are the next hurdle.

Nuclear liability and the SHANTI Act, 2025

If a nuclear accident causes damage, someone has to pay compensation. India’s 2010 liability law capped the operator’s liability at about ₹1,500 crore and — unusually — gave the operator a right to recover from equipment suppliers. Foreign vendors refused to accept open-ended supplier liability, and reactor imports stalled for 15 years.

The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India Act, 2025 (SHANTI Act) was passed by both houses of Parliament on 17–18 December 2025 and received Presidential assent on 20 December 2025, replacing both the Atomic Energy Act, 1962 and the 2010 liability law with a single framework. Key changes:

  • Size-graded operator liability: from about ₹100 crore for the smallest reactors and fuel-cycle facilities up to ₹3,000 crore for the largest plants (those above roughly 3,600 MW), replacing the flat ₹1,500 crore cap. Damages beyond the operator’s cap stay backed by the Union up to 300 million SDR (about ₹3,900 crore).
  • Supplier exposure limited to what the contract specifies, replacing the 2010 law’s open-ended right of recourse against equipment suppliers.
  • Private and foreign investment allowed for the first time, capped at 49% FDI under the automatic route, with the Central Government or a government company keeping majority control. Enrichment, reprocessing and fissile-material accounting stay exclusively with the state.
  • Regulator: the AERB was given statutory status rather than being replaced.

The Act is a framework. The draft SHANTI Rules 2026 and draft AERB regulations that make it operational — covering the single-window composite licence, insurance, financial security and decommissioning funds — were released for public consultation running into September 2026. Until they are notified, no private nuclear project can actually begin.

⚠️ A note on terminology

The SHANTI Act is real, enacted law — passed in December 2025. Its “rules,” sometimes cited as separate legislation, are the subordinate SHANTI Rules and AERB regulations made under it, which as of August 2026 are still in draft. This page treats the Act as in effect and the operational rules as pending.

Regulatory and legal timeline

YearDevelopmentEffect
2010Civil Liability for Nuclear Damage ActOperator cap + supplier recourse; froze foreign reactor deals
2015–16India Nuclear Insurance Pool; memorandum with the US on liabilityPartial workaround; did not fully reassure suppliers
Feb 2025Budget promises Atomic Energy Act + liability amendmentsSignalled structural reform and private entry
Dec 2025SHANTI Act, 2025 enacted (assent 20 Dec)New liability scale; private + up to 49% foreign investment allowed; AERB made statutory
2026Draft SHANTI Rules and AERB regulations out for consultationComposite licence, insurance, decommissioning funds; not yet notified — gates when private projects can start

Before 100 GW, India has a much closer test

The 2031–32 checkpoint — about 22,480 MW — is far more measurable than 2047. Every reactor meant to deliver it already exists on a construction site: Kudankulam 3–6, Rajasthan 8, Kaiga 5&6, Gorakhpur 1&2, plus the PFBR reaching commercial operation. Going from ~8.8 GW to ~22.5 GW is a jump from roughly a few hundred megawatts of additions per year to around 2 GW per year. If India misses the 2031–32 number, the 2047 target becomes arithmetic without a plan.

How much nuclear capacity is still missing?

Accounted for (approx.)

  • Operating: ~8.8 GW
  • Under construction: ~6 GW
  • Sanctioned / approved: ~15 GW
  • Subtotal: ~30 GW

Still to be found

  • 2047 target: 100 GW
  • Minus the ~30 GW above
  • Gap needing new projects: ~70 GW
  • Sources: SMRs, private BSRs, Jaitapur, Kovvada, unannounced

As a scale illustration only: ~70 GW is about 100 reactors of 700 MW each, or roughly 45 large 1,600 MW units. India’s real 2047 mix would combine PHWRs, large foreign reactors, fast breeders and SMRs — this is not a construction forecast, just a sense of the size of the task. Dividing ~91 GW of total additions by 21 years gives an average of about 4.3 GW per year — more than four times India’s best sustained rate.

Why is India pushing nuclear now?

Several pressures at once:

  • Electricity demand growth — among the fastest of any large economy, driven by industrialisation, air-conditioning and rising incomes.
  • Coal dependence — about 70% of generation. India wants firm low-carbon capacity that is not weather-dependent.
  • Decarbonisation — a net-zero-by-2070 pledge needs baseload that is not coal.
  • Renewables integration — as solar and wind grow, the grid needs firm capacity to balance them; nuclear is one option alongside storage and hydro.
  • Energy security — domestic reactors reduce exposure to imported fuel price shocks.
  • Industrial heat and hydrogen — high-temperature reactors and SMRs are being examined for process heat and green hydrogen.

Data-centre and AI electricity demand is part of the global backdrop, but India’s nuclear expansion is driven mainly by overall demand growth and coal substitution, not by data centres specifically.

Nuclear, solar and coal — not a straight contest

FactorNuclearSolarCoal
Operating CO₂Very lowVery lowHigh
Dispatch profileFirm, round-the-clockVariable (daytime)Firm
Indian capacity factor~75–85%~20%~60–70%
Build timeLong (years)Short (months)Medium
Land per unit of outputCompact plant footprintLarge generation footprintPlant plus mining
Air pollutionVery lowVery lowSignificant
WasteRadioactive waste, managedEnd-of-life panelsAsh plus emissions
Storage needNot inherentNeeded for firm supplyNot inherent

The useful framing is not “nuclear versus solar.” India’s plan uses both: solar and wind for cheap variable energy, nuclear for firm low-carbon capacity, and storage, transmission and demand management to tie them together. A 1 GW nuclear plant and 1 GW of solar do not produce the same annual electricity — the nuclear plant generates roughly four times as much, because it runs most of the year.

India vs China vs the world

CountryOperating capacityReactorsNuclear share of powerUnder construction
United States~97 GW~94~18%Minimal
France~61 GW56~65%1
China~58 GW~57~5%~30 (~30 GW)
Russia~28 GW~36~19%Several
India~8.8 GW24~3%8 (~6 GW)

Figures are approximate, drawn from IAEA PRIS and World Nuclear Association data through 2026, and every country’s fleet will change by 2047. The honest comparison with China is not “India is beating China” or “India is decades behind” — it is that China has several times more capacity under construction and is adding reactors far faster, and has itself set targets well above 100 GW for the 2030s. If India reaches 100 GW, that fleet would be comparable in size to France’s or the United States’ today — though every country’s fleet will also change by 2047.

Fuel, waste and thorium

Where India gets uranium

Domestic uranium comes mainly from Uranium Corporation of India mines in Jharkhand (Jaduguda) and Andhra Pradesh (Tummalapalle), but it is not enough for the full fleet. Under post-2008 safeguards agreements India imports uranium from Russia, Kazakhstan, Canada, Australia, Uzbekistan, Namibia and Mongolia. PHWRs use natural uranium; the Russian VVERs at Kudankulam use enriched fuel supplied by Russia.

What happens to the waste

India follows a closed fuel cycle: spent fuel is reprocessed to recover plutonium and uranium for reuse, rather than being sent straight to disposal. High-level waste is vitrified (turned to glass) and stored; a deep geological repository is a long-term plan, not an operating facility.

Why India doesn’t already run on thorium

Thorium is fertile, not fissile: it cannot sustain a chain reaction by itself. It must be placed in a reactor and converted to uranium-233 first, which is why thorium sits in Stage 3, after fast breeders. India has the design (the Advanced Heavy Water Reactor) but has not built a commercial thorium reactor.

Fission vs fusion — not the same thing

Every reactor discussed on this page uses nuclear fission — splitting heavy atoms like uranium and plutonium. Nuclear fusion — joining light atoms like hydrogen, the process that powers the Sun — is a separate technology still at the experimental stage worldwide, including at ITER, which India helps fund. Fusion is not part of India’s 100 GW plan. For that story, see our nuclear fusion timeline.

What a nuclear buildout means for Indian manufacturing

A large reactor programme pulls in a long domestic supply chain: heavy forgings and pressure vessels, steam generators, coolant pumps, control and instrumentation systems, specialty steel, turbines and generators, plus civil construction and decades of operations and maintenance jobs. India already has capable suppliers — Larsen & Toubro, BHEL, Walchandnagar Industries, Godrej & Boyce — and the fleet-mode and SMR plans are partly about giving them enough repeat orders to invest in capacity. Whether this scales to 100 GW is one of the open questions.

Not investment advice. This article discusses companies only to explain the sector. It is not a recommendation to buy or sell shares in any company, nuclear supplier or uranium producer.

Is nuclear power expensive? Is it safe?

Cost

It depends heavily on financing cost, construction time, reactor design and execution. Nuclear has high upfront capital and a long asset life (often 40–60 years), low fuel cost, and real value as firm capacity — but cost overruns and delays, which have hit Indian projects historically, can make the delivered electricity expensive. There is no single “₹ per unit” figure that describes nuclear power in general.

Safety

Indian plants are regulated by the AERB and designed with defence-in-depth: multiple independent barriers, containment structures, passive cooling on newer units, and off-site emergency plans. India’s operating record has been strong. That does not eliminate the fundamental character of nuclear risk — low probability, potentially high consequence — which is why regulation, siting and emergency preparedness matter. Note that a nuclear power plant accident, such as Fukushima or Chernobyl, is a reactor and radiation event, not a nuclear-weapon explosion; the two are physically different.

Road to 100 GW — live tracker

As of 27 August 2026

Operating~8.8 GW / 100 GW
Operating ~8.8 GW (~8.8%) Under construction ~6 GW Sanctioned ~15 GW Target gap ~70 GW

This module is updated when a reactor enters commercial operation, a project moves category, a PFBR milestone occurs, an SMR design is approved, a private firm signs a confirmed project, or a Budget changes the allocation.

Can India reach 100 GW of nuclear power by 2047?

Reader prediction — not a scientific poll. Results shown are reader opinion only.

Yes
No
Only with large private-sector participation
Only with major foreign technology partnerships
▶ Cast your prediction

Which technology will matter most for the target?

Reader opinion only — not a forecast.

Indigenous 700 MW PHWRs
Large foreign reactors (EPR, AP1000, VVER)
Small modular reactors
Fast breeder reactors
A combination of all of them
▶ Cast your vote

Nuclear India — things worth knowing

  • India’s first reactor, Apsara (1956), was Asia’s first research reactor.
  • The 1974 nuclear test triggered the technology embargo that forced India to develop its own PHWRs.
  • KAMINI at Kalpakkam is the only reactor in the world fuelled by uranium-233.
  • The PFBR took roughly two decades from sanction to criticality.
  • NPCIL says its reactors have cumulatively generated well over 1,000 billion units (kWh) of low-carbon electricity.
  • Jaitapur, if built as planned, would be the largest nuclear power station on Earth by capacity.

People also ask

How many nuclear reactors does India have in 2026?
India operates 24 nuclear reactors at seven sites across six states, with a combined capacity of about 8,780 MW, per DAE and NPCIL. Eight more reactors are under construction. The World Nuclear Association cites a slightly lower net operable figure because it excludes units in extended shutdown.
Has India’s fast breeder reactor started?
Yes. The 500 MWe Prototype Fast Breeder Reactor at Kalpakkam, built by BHAVINI, attained first criticality on 6 April 2026 after clearance from the Atomic Energy Regulatory Board. Grid connection and commercial operation are expected later in 2026. It marks India’s formal entry into Stage 2 of its three-stage programme.
Can private companies build nuclear plants in India now?
In principle, under the SHANTI Act, 2025. It lets private and foreign investors take equity in nuclear power projects — capped at 49%, with the state keeping majority control — and lets private firms lead construction and operation. But the rules that make it work are still in draft, and as of August 2026 no private firm has taken a final investment decision. Several have responded to NPCIL’s Bharat Small Reactor tender.
What is the difference between a Bharat Small Reactor and a Bharat Small Modular Reactor?
The Bharat Small Reactor (BSR) is a ~220 MW reactor derived from India’s proven PHWR, built and operated by NPCIL for an industrial customer’s captive power. The Bharat Small Modular Reactor (BSMR) is a newer modular design, in the ~200–300 MWe range, being developed by BARC and NPCIL for wider and eventually export use.
Is nuclear power cheaper than solar in India?
Not per unit of electricity. Utility-scale solar in India is among the cheapest new generation, while nuclear has high upfront capital and long build times. Nuclear’s value is that it produces firm power around the clock: a 1 GW nuclear plant generates roughly four times the annual electricity of 1 GW of solar because it runs most of the year.

India nuclear power: frequently asked questions

How much nuclear power does India have right now?
About 8,780 MW (8.8 GW) from 24 operating reactors, according to DAE and NPCIL figures for 2026. This is roughly 1.8% of India’s total installed electricity capacity of around 485 GW, and supplies close to 3% of the country’s electricity generation.
Why do sources give different numbers for India’s nuclear capacity?
DAE and NPCIL usually quote gross installed capacity of all licensed units (~8,780 MW, 24 reactors). The World Nuclear Association and IAEA PRIS list a lower net figure (~7.9 GWe) because they use net electrical output and exclude reactors in long-term shutdown, such as the oldest Rawatbhata unit. Both are correct for what they measure.
What is India’s 100 GW nuclear target?
In the 2025–26 Union Budget, the finance minister said developing at least 100 GW of nuclear capacity by 2047 — the centenary of independence — is essential for India’s energy transition. It is a stated government aspiration, not a funded, scheduled construction programme.
Is 100 GW by 2047 realistic?
It is possible but far from guaranteed. It implies adding roughly 91 GW in about 21 years, close to a ten-fold expansion, against a historical record of a few hundred megawatts a year. It needs fleet-mode PHWRs to accelerate, SMRs to work, large private investment, and foreign reactors at Jaitapur and Kovvada to actually start.
How much nuclear capacity will India have by 2031–32?
The official projection is about 22,480 MW, roughly 2.5 times today’s level. It depends on completing Kudankulam 3–6, Rajasthan 8, Kaiga 5&6 and Gorakhpur 1&2, and on the PFBR reaching commercial operation. This near-term figure is a better test of momentum than the 2047 number.
What is the ₹20,000 crore Nuclear Energy Mission?
Announced in the 2025–26 Budget, it is a ₹20,000 crore allocation mainly for research, development and demonstration of small modular reactors, with a target of at least five indigenously developed SMRs operational by 2033. It was paired with a commitment to amend the Atomic Energy Act and the nuclear liability law.
How many SMRs will India build?
The stated target is at least five indigenously developed SMRs operational by 2033. As of August 2026 the designs are still in development and detailed-project-report stage; none is under construction, so the number that will actually be operating by 2033 is uncertain.
What is a Small Modular Reactor?
A nuclear reactor of roughly 300 MWe or less, designed so that major components are factory-built and assembled on site in modules. The aim is a smaller, more financeable project, faster on-site construction, and flexible siting — for example on retired coal-plant land or next to an industrial plant needing captive power.
What is the PFBR and why does it matter?
The Prototype Fast Breeder Reactor is a 500 MWe reactor at Kalpakkam, operated by BHAVINI. It breeds more fissile material than it consumes and is Stage 2 of India’s three-stage nuclear plan, the bridge to thorium-based Stage 3 reactors. It reached first criticality on 6 April 2026, about 12 years later than originally targeted.
What is India’s three-stage nuclear programme?
A plan framed by Homi Bhabha in the 1950s: Stage 1 uses natural-uranium PHWRs; Stage 2 uses fast breeder reactors fuelled by the plutonium from Stage 1, with a thorium blanket; Stage 3 uses reactors running on uranium-233 bred from thorium. Stage 1 is mature, Stage 2 has just begun, Stage 3 is still research.
Why hasn’t India commercialised thorium?
Thorium is fertile, not fissile: it cannot sustain a chain reaction on its own and must first be converted inside a reactor to uranium-233. That requires a working fast-breeder stage to supply the initial fissile material, plus reactor designs India has drawn up but not yet built. Commercial thorium power is realistically decades away.
What is the SHANTI Act, 2025?
The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India Act, 2025 — passed by Parliament in December 2025, Presidential assent 20 December 2025. It replaced the Atomic Energy Act, 1962 and the Civil Liability for Nuclear Damage Act, 2010, set a size-graded operator liability cap of about ₹100 crore to ₹3,000 crore, limited a supplier’s exposure to its contract, gave the AERB statutory status, and opened nuclear power to private and up to 49% foreign investment. Its detailed rules were still in draft consultation in August 2026.
Does the SHANTI Act let foreign companies own nuclear plants in India?
Only a minority stake. The Act permits foreign direct investment in nuclear power projects capped at 49% under the automatic route, with the Central Government or an Indian government company holding majority control and acting as licensed operator. Foreign vendors such as EDF and Westinghouse mainly supply technology and services; the exact ownership and investment rules are being set in the draft SHANTI Rules.
Why was nuclear liability such a big issue?
India’s 2010 law let a plant operator recover compensation from equipment suppliers after an accident — an open-ended risk foreign vendors would not accept. As a result, reactor deals signed after the 2008 India–US agreement never moved to construction. The SHANTI Act limited supplier liability to contract terms, removing the main blocker.
Are Tata, Reliance and Adani entering nuclear power?
They have expressed interest. Tata Power, Reliance Industries and Adani Power are among six companies that responded to NPCIL’s Bharat Small Reactor tender for captive reactors. As of August 2026 none has taken a final investment decision, selected a design or begun construction. Reported interest is not a project.
What is ASHVINI?
Anushakti Vidyut Nigam Ltd (ASHVINI) is a joint venture between NPCIL and NTPC, created to develop nuclear capacity beyond what NPCIL can build alone. It has been assigned the Mahi Banswara project in Rajasthan (four 700 MW PHWRs) and has floated a large Nuclear Island EPC tender for it.
How many reactors are at Kudankulam?
Two 1,000 MW Russian VVER units are operating (since 2013 and 2016) and four more are under construction under successive India–Russia agreements. Planned at six units, Kudankulam is set to become India’s largest single nuclear power station.
What happened to the Jaitapur project?
The Jaitapur project in Maharashtra — six EDF EPR reactors, about 9,900 MW — has been approved in principle since 2018 but has not started construction. Financing terms, electricity price and liability were unresolved for years, and there is local opposition. EDF and NTPC signed an MoU in 2025 to explore Indian projects, but no concrete has been poured.
What about Kovvada and Westinghouse?
Kovvada in Andhra Pradesh is earmarked for six Westinghouse AP1000 reactors. Environmental assessment is done but construction has not begun. In 2025 Westinghouse and Larsen & Toubro formed a working group and US export-control steps advanced. The SHANTI Act removed the liability obstacle; commercial and financing terms are the next stage.
Where does India get its nuclear fuel?
Domestic uranium comes from mines in Jharkhand and Andhra Pradesh, run by the Uranium Corporation of India, but it does not cover the whole fleet. Under post-2008 safeguards agreements India imports uranium from Russia, Kazakhstan, Canada, Australia, Uzbekistan, Namibia and Mongolia.
How does India handle nuclear waste?
India uses a closed fuel cycle: spent fuel is reprocessed to recover plutonium and uranium for reuse rather than being disposed of directly. High-level waste is vitrified into a stable glass form and stored. A deep geological repository is a long-term plan, not an operating facility.
Is nuclear energy renewable?
No. Nuclear fission relies on uranium and plutonium, which are finite mined resources, so it is not renewable. It is, however, a low-carbon source: operating a nuclear plant produces almost no greenhouse gases, which is why it is often grouped with renewables as “clean” firm power.
Is nuclear power clean?
In operation, yes — it emits almost no carbon dioxide or air pollutants. The trade-offs are radioactive waste that must be managed for a long time, the water and materials used in construction, and the low-probability, high-consequence accident risk that regulation is designed to contain.
How safe are India’s nuclear plants?
They are regulated by the Atomic Energy Regulatory Board and built with defence-in-depth: multiple containment barriers, redundant cooling, passive safety systems on newer units, and off-site emergency plans. India’s operating safety record has been strong, but nuclear risk is inherently low-probability and high-consequence, which is why siting and preparedness matter.
Is nuclear power expensive?
It depends on financing cost, build time and execution. Nuclear has high upfront capital and a long asset life, low fuel cost, and value as firm capacity. Cost overruns and delays — which have affected Indian projects — can push the delivered cost of electricity up. There is no single price that describes nuclear power in general.
How does India compare with China on nuclear power?
China has roughly 55–60 GW operating from about 57 reactors and around 30 GW more under construction. India has about 8.8 GW operating and 8 reactors (~6 GW) under construction. China has many times more capacity being built and is adding reactors far faster; India’s 100 GW goal for 2047 is a scale China is targeting for the 2030s.
Which country has the most nuclear power?
The United States has the largest operating nuclear fleet by capacity, about 97 GW from roughly 94 reactors, followed by France and China. France has the highest share of its electricity from nuclear, around 65%. India ranks well outside the top five by capacity.
Will SMRs replace India’s coal plants?
It is a proposal, not a decided plan. Retiring coal sites have grid connections, water, land and a trained workforce, which makes them attractive for SMRs. Whether this happens at scale depends on the SMR designs being licensed, proving affordable, and being matched to specific sites — none of which has happened yet in India.
Are Indian data centres being powered by nuclear reactors?
Not yet. SMRs are being explored globally as firm low-carbon power for data centres, and India’s SMR programme mentions industrial demand, but no Indian data centre has signed a nuclear power purchase agreement. Treat any such claim as speculative unless a specific deal is announced.
What is fleet mode?
Fleet mode is a plan to build ten identical 700 MW PHWRs using standardised designs, bulk procurement and repeat contractors, so each unit is faster and cheaper than a one-off build. Kaiga 5&6, Gorakhpur 1–4, Mahi Banswara 1–4 and Chutka 1&2 are the fleet-mode reactors.
What is the difference between nuclear fission and fusion?
Fission splits heavy atoms such as uranium to release energy and powers every reactor operating today. Fusion joins light atoms such as hydrogen — the Sun’s process — and remains experimental worldwide. India’s 100 GW plan is entirely fission; fusion is not part of it.
How is the 100 GW target progressing?
As of August 2026, about 8.8 GW is operating (roughly 8.8% of the goal), around 6 GW is under construction and about 15 GW is sanctioned. That leaves roughly 70 GW with no project attached, which must come from SMRs, private reactors, foreign large reactors and projects not yet announced.
When will this page be updated?
Whenever a reactor reaches criticality or commercial operation, a project changes category, a PFBR milestone occurs, an SMR design is approved, a private company signs a confirmed project, the liability rules change, a foreign project advances, or a Union Budget changes the nuclear allocation.

100 GW is the destination. The 2030s will decide whether India gets there.

India’s 2047 nuclear ambition is easy to state and hard to execute: take today’s ~8.8 GW fleet to 100 GW. The route is complicated. India has to finish the reactors already under construction, accelerate the 700 MW PHWR programme through fleet mode, turn the PFBR from a milestone into a working power station, convert the SMR programme from R&D into licensed reactors, and find out how much capital and technology private and foreign companies can realistically bring under the new SHANTI Act framework.

So the 100 GW figure is best treated as a destination, not a prediction. The milestones that matter now are nearer: the next reactor to reach commercial operation, the next PFBR step, the first indigenous SMR demonstration, the next large project to move from approval to construction, and India’s actual nuclear capacity in 2031–32. Those will show whether the 2047 target is turning from a policy ambition into an executable construction programme.

⚠️ Editorial note — how we verify nuclear-project status

Operating: commercial generation officially confirmed. Under construction: physical construction officially underway. Sanctioned: government or project approval exists but construction has not clearly begun. Proposed: discussion or planning only. Figures are drawn from the Department of Atomic Energy, NPCIL, BHAVINI, the Atomic Energy Regulatory Board, Union Budget documents, Parliament answers, the IAEA and reputable reporting, and are marked “Data verified: 27 August 2026” where they are live values. This is an editorial explainer compiled from public sources, not investment or policy advice; where sources disagree, the disagreement is stated rather than resolved toward the most dramatic number.

Advertisement