The Line & NEOM Timeline: Construction, Progress and What Comes Next

📅 Last updated: August 22, 2026🏗️ ~2.4 km built · construction paused since Sept 2025💰 PIF-funded
Advertisement
In short

NEOM's The Line: 2021 launch, 2024 scale-back reports, the Sept 2025 pause, March 2026 contract cuts and where construction stands in August 2026.

The Line, the 170-kilometre linear city Saudi Arabia unveiled in January 2021 as the centrepiece of its wider NEOM development on the Red Sea, has spent five years moving between two different stories. One is the render: a mirrored, car-free city stretching from mountains to sea, housing up to a million residents inside a five-minute walk of everything they need. The other is the trench: roughly 2.4 kilometres of excavation and foundation work near the Gulf of Aqaba, construction paused since September 2025 pending a strategic review, and a Public Investment Fund governor telling reporters in April 2026 that hitting any date by 2030 is “not a must.” This page tracks both stories from the 2017 announcement of NEOM through 2026, and is explicit throughout about which claims are announced vision, which are contracted work, which were under construction, and which have since been paused or cancelled.

📌 Latest update — August 22, 2026: The Line’s construction remains paused. Saudi Arabia’s Public Investment Fund (PIF) halted work on the project around September 16, 2025 pending a strategic review, and a May 22, 2026 Semafor report said NEOM has effectively pushed any resumption past 2030. In March 2026, NEOM terminated a run of major contracts — including a roughly $1 billion tunnel package for The Line (Hyundai E&C, Samsung C&T, Archirodon) and a $1.15 billion steel contract for the Trojena ski resort (Eversendai) — worth a combined $5 billion or more, according to contractor disclosures reported by Dezeen, MEED and Reuters. PIF governor Yasir Al-Rumayyan pushed back publicly on April 15, 2026, telling reporters “no projects” had been cancelled and that completing The Line by 2030 “would be good to have, but it’s not a must.” Both facts are true at once: contracts tied to The Line and Trojena have been terminated, and PIF has not declared the wider project dead. This page reports both, with dates and sources, rather than picking a side.
🏠 What Is The Line in NEOM? The Line is a proposed linear urban development within Saudi Arabia’s wider NEOM project on the Red Sea. The original 2021 concept envisioned a 170-kilometre-long, car-free, mirror-clad city. As of August 2026, roughly 2.4 kilometres of foundation and earthworks have been built near the Gulf of Aqaba, and construction has been paused since September 2025 pending a strategic review — the full-length vision should not be confused with what has actually been built or is currently under construction.
⚡ NEOM & The Line Quick Facts
NEOM announcedOct 24, 2017, Riyadh · $500B original budget
The Line unveiledJan 10, 2021 · 170 km, zero-car concept
Verified construction~2.4 km of foundation/earthworks (~1.4% of 170 km)
Current statusPaused since Sept 2025; PIF says indefinite, past 2030
Leaked cost projectionUp to $8.8 trillion / 2080 completion (WSJ, unconfirmed by NEOM)
Funded bySaudi Arabia’s Public Investment Fund (PIF)
⚡ Quick Answers — AI Overview Ready

NEOM & The Line: Key Questions

Is The Line actually being built?
A roughly 2.4-kilometre stretch of foundation and earthworks was built near the Gulf of Aqaba before construction was paused around September 2025. As of August 2026 that pause is still in effect, with NEOM’s owner saying any resumption has been pushed past 2030.
Is The Line still 170 kilometres long?
170 km remains the long-term design vision, but it was never all under construction at once. Reports from April 2024 said Saudi officials had privately cut the near-term 2030 target to about 2.4 km — roughly what has actually been built.
Has NEOM been cancelled?
No official cancellation has been announced. PIF governor Yasir Al-Rumayyan said in April 2026 that no NEOM projects had been cancelled, even as several major contracts tied to The Line and Trojena were terminated the previous month.
How much will NEOM cost?
The original 2017 figure was $500 billion for all of NEOM. A leaked internal audit reported by the Wall Street Journal in March 2025 put full completion at up to $8.8 trillion by 2080 — a projection NEOM has not officially confirmed.
📚 Key Takeaways

The Big Picture

  • NEOM (announced October 2017, $500 billion) is the wider Red Sea development; The Line (announced January 2021) is one project inside it — a proposed 170 km linear city. Treating every NEOM headline as a Line headline is the single most common factual error in coverage of this project.
  • The only construction figure that shows up consistently across independent reporting is ~2.4 kilometres of foundation and earthworks near the Gulf of Aqaba — about 1.4% of the original 170 km vision.
  • Construction on The Line has been paused since around September 16, 2025, when PIF ordered a strategic review; a May 2026 Semafor report said the pause now effectively extends past 2030.
  • Reports in April 2024 said Saudi officials had privately scaled the 2030 target from 170 km to about 2.4 km, and the population target from 1.5 million to 300,000 — this was reported, not officially announced, though it lines up with what was later actually built.
  • In March 2026, NEOM terminated a cluster of major contracts — a ~$1 billion Line tunnel package and a $1.15 billion Trojena steel contract among them — worth a combined $5 billion or more by contractor disclosures.
  • PIF’s own governor has publicly rejected the word “cancelled.” On April 15, 2026 he said completing The Line by 2030 “would be good to have, but it’s not a must,” and stressed The Line is one part of NEOM, not the whole project.
  • A leaked internal audit, presented to NEOM’s board in spring 2024 and reported by the Wall Street Journal in March 2025, put full-scope completion at up to $8.8 trillion and the year 2080 — roughly 17x the original budget. NEOM has not confirmed this figure.
  • Not every NEOM project has stalled. Oxagon’s green hydrogen plant was reported roughly 90%+ complete by April 2026, and a $5 billion first-phase AI data centre with DataVolt was signed in February 2025.
  • Sindalah, NEOM’s Red Sea resort island, held a VIP “grand opening” in October 2024 but was still not open to general public bookings as of mid-2026, per industry reporting.
  • NEOM’s CEO since 2018, Nadhmi Al-Nasr, was replaced in November 2024 by Aiman Al-Mudaifer, amid reporting linking the departure to conduct allegations and mounting doubts about the project’s near-term viability.

What Is Actually Being Built in 2026?

Separating confirmed construction from cancelled contracts from long-term vision — with dated sources for each.

StatusWhat it coversEvidence & date
Confirmed / built, activity paused~2.4 km of Line foundation & earthworks near the Gulf of Aqaba; NEOM Bay Airport (operational since 2021); Sindalah resort structures (VIP-opened Oct 2024, not public)PIF pause reporting, ~Sept 2025; NEOM Bay Airport GACA certification, 2021; Dezeen/Arab News, Oct 27, 2024
Active, unaffected so farOxagon green hydrogen plant (NEOM Green Hydrogen Co. — ACWA Power/Air Products JV), reported ~90%+ complete; DataVolt AI data centre first phase in early developmentIndustry reporting, ~April 2026; NEOM/SPA official signing, Feb 10, 2025
Contracted, then terminated (2026)The Line’s 12.5 km tunnel package (Hyundai E&C / Samsung C&T / Archirodon, ~$1B); Trojena Ski Village structural steel (Eversendai/Al Bawani, ~$1.15B); Trojena dams (Webuild, ~$5B)Contractor disclosures via Dezeen, MEED, Gulf Construction, Reuters/Zawya — all March 26, 2026
Long-term vision, no active constructionThe full 170 km Line corridor and mirrored facade; a 1–9 million resident population (figures vary by source/date); a citywide high-speed underground rail spine; Trojena as a year-round ski resort hosting the 2029 Asian Winter Games2021 NEOM launch materials; Asian Winter Games host withdrawal reported Jan 2026

NEOM vs The Line: What’s the Difference?

NEOMThe Line
What is it?A wider ~26,500 km² regional development in northwest Saudi ArabiaOne specific urban-development concept inside NEOM
AnnouncedOctober 24, 2017, at the Future Investment Initiative, RiyadhJanuary 10, 2021, as a standalone reveal
ScopeMultiple sub-projects across tourism, industry and residential zonesA single proposed 170 km linear city
Major componentsThe Line, Oxagon, Trojena, Sindalah, NEOM Bay AirportUrban modules, a mobility spine, supporting infrastructure
2026 statusMixed — Oxagon’s energy/data-centre projects active; tourism and Line construction paused or scaled backConstruction paused since ~Sept 2025; ~2.4 km built

NEOM is not The Line, and coverage that treats every NEOM headline as news about The Line specifically is a common source of confusion — this page keeps the two separate throughout.

Is The Line Still 170 Kilometres Long?

As a long-term design vision, 170 km is still the figure NEOM’s own materials use for The Line’s full concept. It has never been officially withdrawn or replaced with a shorter number in any NEOM or PIF statement. But 170 km was never a description of what was under construction at any given time — it was always the endpoint of a multi-decade build-out, and phased development means portions of the project were meant to be delivered well before the full length existed.

What changed is the near-term target. Reports from Bloomberg and other outlets in April 2024, citing people familiar with internal planning, said Saudi officials had privately cut the 2030 milestone from 170 km to roughly 2.4 km, and the associated population target from 1.5 million residents to about 300,000. Saudi Arabia did not officially confirm this change at the time — it was reported, not announced. What makes it notable in hindsight is that 2.4 km is almost exactly the figure independent reporting has since converged on as the actual amount of foundation and earthworks completed before the September 2025 pause. The leaked number and the built number line up, even though neither was ever an official NEOM statement.

So: the 170 km vision has not been formally cancelled, but no evidence supports describing 170 km of continuous active construction at any point in this project’s history. The honest description, as of August 2026, is a long-term 170 km concept, a scaled near-term target that was reported but never confirmed, and roughly 2.4 km of physical work on the ground.

NEOM & The Line: Full Timeline

Newest first — from the 2017 NEOM announcement through the 2026 construction pause.

NEOM Pushes Any Line Resumption Past 2030

PausedReported by Semafor

What happened: A May 22, 2026 Semafor report, citing people familiar with the matter, said NEOM has effectively made the September 2025 construction pause indefinite, with any resumption of work on The Line pushed past 2030, and Oxagon redesignated as the project’s priority node.

Why it matters: This is the clearest indication yet that the original 2030 first-phase target — already scaled back in 2024 — will not be met in any form.

Source: Semafor, May 22, 2026.

PIF Governor: “No Projects Cancelled,” 2030 “Not a Must”

Official statementPublic remarks

What happened: On April 15, 2026, PIF governor Yasir Al-Rumayyan told reporters that no NEOM projects had been cancelled, describing recent changes as a reassessment of spending priorities. On completing The Line by 2030, he said: “It would be good to have, but it’s not a must,” and stressed that The Line is one part of NEOM, highlighting Oxagon’s role instead.

Why it matters: This is the closest thing to an official response to a year of scale-back reporting — it does not deny delays, but it explicitly rejects “cancelled” as the right word.

Source: Construction Week, Arabian Business, Al Arabiya, Khaleej Times — April 15, 2026.

NEOM Terminates Contracts Worth $5B+ Across The Line and Trojena

Contracts cancelledTabuk Province

What happened: On March 26, 2026, contractor disclosures confirmed NEOM had terminated the ~$1 billion, 12.5 km Line tunnel contract (Hyundai E&C, Samsung C&T, Archirodon), the $1.15 billion Trojena Ski Village steel contract (Eversendai/Al Bawani), and Webuild’s roughly $5 billion Trojena dams contract. Eversendai attributed the termination to “the current geopolitical situation in the Middle East.”

Why it matters: Contract terminations are harder evidence of a real scale-back than any leak or satellite photo — these are legally binding agreements a company had to formally disclose as cancelled to its own shareholders.

Source: Dezeen, MEED, Gulf Construction, Reuters/Zawya — all March 26, 2026.

Saudi Arabia Withdraws as Host of the 2029 Asian Winter Games

Host status withdrawnTrojena

What happened: Saudi Arabia withdrew as host of the 2029 Asian Winter Games, which had been awarded to NEOM’s Trojena mountain resort district in 2022.

Why it matters: Trojena’s Winter Games bid was one of the most concrete, date-bound commitments in the entire NEOM portfolio; losing it removed a hard external deadline for the resort’s construction.

Source: Reported alongside the March 2026 contract cancellations.

PIF Pauses Line Construction Pending Strategic Review

Paused~2.4 km / ~1.4% of 170 km complete

What happened: Around September 16, 2025, PIF ordered a pause on Line construction pending a strategic review, by which point independent reporting placed completed foundation and earthworks at roughly 2.4 km — about 1.4% of the original 170 km plan.

Why it matters: This is the point at which “The Line is under construction” stopped being an accurate present-tense description, even though the site itself was not abandoned.

Source: Industry reporting via Semafor’s later May 2026 coverage and multiple 2025-2026 trade outlets.

PIF Discloses $8 Billion Writedown on Megaproject Investments

Financial disclosurePIF portfolio

What happened: On August 14, 2025, PIF disclosed an $8 billion writedown across its megaproject investments, of which NEOM is the largest.

Why it matters: A writedown is an accounting acknowledgment that assets are worth less than previously booked — a financial, not architectural, admission that the original plan’s economics had changed.

Source: CNBC, August 14, 2025.

WSJ Reports Leaked Audit: Up to $8.8 Trillion, Completion by 2080

Leaked, unconfirmed by NEOMInternal audit

What happened: The Wall Street Journal reported on a 100-page internal NEOM audit, presented to the board in spring 2024 and aided by consultancy McKinsey, projecting full-scope completion could cost up to $8.8 trillion and stretch to the year 2080. The WSJ’s reporting said the audit also found NEOM executives had built business-plan assumptions that understated costs to justify the project’s continuation.

Why it matters: $8.8 trillion is roughly 17.6x the original $500 billion figure and more than four times Saudi Arabia’s GDP — but this is a leaked internal projection reported by a newspaper, not a public NEOM or PIF statement, and should be treated with that distinction intact.

Source: The Wall Street Journal, reported March 9–12, 2025 (via New Civil Engineer, Middle East Monitor, TechCrunch summaries).

NEOM & DataVolt Sign $5B AI Data Centre Deal at Oxagon

Confirmed, activeOxagon

What happened: On February 10, 2025, NEOM and Saudi firm DataVolt signed an agreement to build a 1.5-gigawatt, net-zero AI data centre at Oxagon. The first phase carries a $5 billion investment and targets roughly 300 MW operational by 2028.

Why it matters: This is one of the few large NEOM commitments made after the 2024 scale-back reporting that has not been walked back or delayed — and it reinforces Oxagon, not The Line, as NEOM’s active near-term priority.

Source: NEOM/Saudi Press Agency official announcement, February 10, 2025.

NEOM Replaces CEO Nadhmi Al-Nasr

Leadership changeReported: conduct allegations, project doubts

What happened: On November 12, 2024, NEOM’s board announced Nadhmi Al-Nasr’s departure as CEO after leading the project since 2018, without stating a reason. Aiman Al-Mudaifer, previously PIF’s head of local real estate, was named Acting CEO. Trade press including New Civil Engineer reported the departure alongside “bad behaviour” allegations and mounting doubts about the project’s viability — a causal link that is reported, not confirmed by NEOM’s own statement.

Why it matters: A leadership change of the project’s only CEO since founding, arriving five months before the leaked $8.8 trillion audit became public, is a natural inflection point in the project’s public narrative.

Source: NEOM Board statement; Bloomberg, AGBI, The National, New Civil Engineer — Nov 12–13, 2024.

Sindalah Island “Opens” — to VIP Guests

Opened, not publicRed Sea, off Tabuk coast

What happened: Sindalah, an 840,000 m² resort island and NEOM’s first completed region, held a launch event on October 27, 2024 attended by invited guests including celebrities. Reported cost was roughly $4 billion, about 3x the initial budget. As of mid-2026, industry press (AGBI, July 2026) reported the island still had not opened to general public bookings.

Why it matters: Sindalah is the one NEOM sub-project that reached physical completion on a visible timeline — but “opened” and “operating as a public destination” turned out to be two different milestones, 20 months apart and counting.

Source: Dezeen, Arab News, October 27–29, 2024; AGBI, July 2026.

Major Infrastructure Contracts Awarded for The Line and Trojena

Contracted (later terminated 2026)Tabuk Province

What happened: Through 2024, NEOM awarded major construction packages including a roughly $1.15 billion structural steel contract to Eversendai (with Al Bawani Company) for the Trojena Ski Village, and a roughly $1 billion, 12.5 km tunnel contract to a Hyundai E&C / Samsung C&T / Archirodon consortium for The Line’s transport infrastructure.

Why it matters: These were real, signed, disclosed contracts — the strongest evidence at the time that construction was moving from earthworks into major infrastructure. Both were terminated roughly two years later, in March 2026.

Source: Construction Week, AGBI, ENR, Gulf Construction, 2024 contract-award reporting.

Reports: 2030 Target Cut From 170 km to 2.4 km

Reported, not officially confirmedRiyadh

What happened: Bloomberg and other outlets reported on April 8, 2024, citing people familiar with internal planning, that Saudi officials had scaled back the near-term Line target for 2030 from 170 km to about 2.4 km, and the population target from 1.5 million residents to roughly 300,000. Bloomberg’s sources also said NEOM’s 2024 budget had not yet been approved at the time of reporting.

Why it matters: This was the first major signal that the original scope and the actual near-term build had diverged — and in hindsight, the reported 2.4 km figure is almost exactly what was later confirmed as physically built.

Source: Bloomberg; New Civil Engineer, April 8, 2024.
2022
–23

Earthworks and Foundation Activity Begin

ConfirmedGulf of Aqaba site

What happened: Satellite imagery from late 2022 onward showed active site preparation, trenching and excavation at The Line’s site near the Gulf of Aqaba, consistent with reported foundation and piling work through 2023.

Why it matters: This is where the project moved from planning documents to a physically verifiable construction site — the ~2.4 km eventually completed traces back to this period.

Source: Satellite-imagery analyses reported by Newsweek and industry trackers, 2022–2024.

The Line Unveiled: 170 km, Zero Cars, Mirrored Facade

Announced visionRiyadh

What happened: Crown Prince Mohammed bin Salman announced The Line on January 10, 2021: a proposed 170-kilometre linear city with no cars or roads, built to preserve 95% of NEOM’s surrounding nature, and designed to run on 100% renewable energy. Launch materials cited up to 1 million residents at the time, with later NEOM materials referencing a longer-term design capacity of up to 9 million — the two figures come from different dates and should not be conflated.

Why it matters: Every subsequent claim about The Line — scaled back, paused, or otherwise — is measured against this original announcement.

Source: NEOM official release; Arab News, PR Newswire — January 10, 2021.

NEOM Company Incorporated

ConfirmedTabuk Province

What happened: NEOM Company was established as a closed joint-stock company wholly owned by PIF, with Nadhmi Al-Nasr appointed CEO.

Why it matters: This gave the project a corporate and regulatory structure independent of standard Saudi ministries, ahead of The Line’s 2021 unveiling.

Source: NEOM corporate filings, January 2019.

NEOM Announced at the Future Investment Initiative

ConfirmedRiyadh

What happened: Crown Prince Mohammed bin Salman announced NEOM at the first Future Investment Initiative conference, describing a $500 billion, PIF-backed economic zone in northwest Saudi Arabia as a pillar of Vision 2030’s economic diversification plan.

Why it matters: This is the origin point for every NEOM sub-project, including The Line, Oxagon, Trojena and Sindalah, and for the $500 billion figure that later cost reporting is measured against.

Source: Future Investment Initiative, Riyadh, October 24, 2017.

NASA ISS astronaut photograph of the Gulf of Aqaba coastline near NEOM, showing the Neom Residential Camp, roads and turquoise reef lagoons along the Red Sea

The Gulf of Aqaba coastline near NEOM’s Neom Residential Camp, photographed from the International Space Station on July 22, 2026. Credit: Earth Science and Remote Sensing Unit, NASA Johnson Space Center (public domain).

The Other Projects Around NEOM

NEOM is not The Line — here is how its other named components stand as of 2026.

Industrial port city

Oxagon

An automated port and industrial hub on the Red Sea coast. Reported NEOM’s current priority node as of May 2026, home to the NEOM Green Hydrogen Company plant (~90%+ complete, April 2026 reporting) and the $5 billion first-phase DataVolt AI data centre (signed Feb 2025).

Mountain resort

Trojena

A year-round ski and mountain-tourism district. Lost its 2029 Asian Winter Games host status in January 2026; its Ski Village steel contract and dams contract were both terminated in March 2026, and the main construction package is being re-tendered.

Resort island

Sindalah

NEOM’s first completed sub-project, an 840,000 m² Red Sea resort island. Held a VIP launch on October 27, 2024 at a reported cost of roughly $4 billion, but was still not open to general public bookings as of mid-2026.

Transport hub

NEOM Bay Airport

Operational since 2021, providing the primary air access point for engineers, investors and consultants travelling to NEOM’s remote northwest Saudi sites.

How Much Will NEOM and The Line Cost?

FigureScopeDateSourceStatus
$500 billionFull NEOM developmentAnnounced Oct 24, 2017MBS, Future Investment InitiativeOriginal target
Up to $8.8 trillion / 2080Full NEOM, per leaked internal auditAudit dated spring 2024; reported March 2025Wall Street JournalLeaked, unconfirmed by NEOM
$8 billion writedownPIF’s megaproject investment portfolioDisclosed Aug 14, 2025PIF financial disclosure, via CNBCConfirmed
$5B+ terminatedCancelled Line tunnel + Trojena steel + Trojena dams contractsTerminated Mar 26, 2026Contractor disclosures (Eversendai, Hyundai E&C, Webuild)Confirmed
$5 billion (phase 1)DataVolt AI data centre, Oxagon (1.5GW total)Signed Feb 10, 2025NEOM/SPA official announcementConfirmed, active
~$4 billionSindalah resort (~3x initial budget, per reporting)Opened Oct 27, 2024Industry press (Dezeen and others)Reported, not itemized by NEOM

NEOM is funded primarily through Saudi Arabia’s Public Investment Fund (PIF), the kingdom’s sovereign wealth fund, with contractor and joint-venture partners financing their own construction scopes rather than the project as a whole.

Has The Line Been Scaled Back?

The honest answer has two parts that are both true. First: no official Saudi or NEOM statement has ever announced a reduced scope for The Line, and PIF governor Yasir Al-Rumayyan explicitly said in April 2026 that no NEOM projects had been cancelled. Second: the reported April 2024 target cut from 170 km to 2.4 km by 2030 has, in effect, already happened on the ground — roughly 2.4 km is what independent reporting says was actually built before the September 2025 pause, and that pause has since been extended past 2030 per the May 2026 Semafor report. Contracts specifically tied to Line infrastructure (the 12.5 km tunnel package) and to Trojena (steel, dams) were formally terminated in March 2026, which is a harder fact than any leak: a contractor does not disclose a termination to its shareholders unless the contract is actually gone.

What this page will not do is call the project “cancelled.” Nothing in the public record supports that word being applied to NEOM as a whole, and PIF has explicitly rejected it for The Line specifically. What the record does support is that the near-term, 2030-dated version of The Line described in 2021 launch materials is not happening on that timeline, by any reasonable reading of the contract terminations, the funding writedown and the leaked audit together.

2026 Progress Scorecard

Component2026 statusEvidence
Site preparation / earthworksConfirmed, halted~2.4 km of Line corridor trenched before Sept 2025 pause
FoundationsConfirmed, haltedSame ~2.4 km stretch; no reported expansion since the pause
TunnelsContract cancelledHyundai/Samsung/Archirodon 12.5 km tunnel terminated Mar 2026
Rail infrastructureNot independently verified as builtNo confirmed rail construction reported beyond planning
Utilities / renewable energyActive at OxagonGreen hydrogen plant ~90%+ complete, April 2026 reporting
Sindalah resortBuilt, not open to the publicVIP opening Oct 2024; still not public as of mid-2026 (AGBI)
Trojena ski resortContracts terminated, re-tenderingSteel + dams contracts cancelled Mar 2026; lost 2029 Games host Jan 2026
Full 170 km visionLong-term, paused past 2030Semafor, May 22, 2026

Why Building The Line Is So Difficult

Even setting the funding and governance questions aside, The Line’s original design was an unusually hard engineering problem. A continuous structure running 170 km through desert terrain has to cross varied ground conditions along its entire length, each requiring its own foundation approach, rather than the single, well-characterized site a normal skyscraper or campus is built on. Concrete curing in a hot desert environment behaves differently than in temperate climates, requiring closer control of pour timing, cooling and logistics — a genuine constraint at any scale, though this page does not have verified figures for exact concrete volumes used to date and will not invent them.

The site’s remoteness compounds ordinary construction logistics: materials, workers and heavy equipment all have to reach a stretch of coastal desert with limited existing infrastructure, which is part of why NEOM built its own airport (2021) before major Line construction began. A citywide high-speed transit spine, water desalination and distribution, and renewable power generation all had to be built essentially from nothing, in parallel with the structure itself, rather than tapped from existing regional grids.

Energy and Water: NEOM’s Infrastructure Backbone

NEOM’s energy strategy centres on Oxagon rather than The Line specifically. The NEOM Green Hydrogen Company — a joint venture of ACWA Power, Air Products and NEOM — was reported roughly 90%+ complete by April 2026, targeting first hydrogen production and export in late 2026 or 2027. Separately, the February 2025 DataVolt agreement adds a 1.5-gigawatt AI data centre campus at Oxagon, with a $5 billion first phase targeting around 300 MW operational by 2028. Both of these are Oxagon projects, not Line infrastructure — a distinction this page keeps deliberately, since NEOM’s own materials sometimes present them under one energy narrative.

Water for the site relies on desalination, standard for large-scale development on the Red Sea coast, alongside planned wastewater recycling. This page does not have verified, dated figures for a NEOM-specific desalination plant’s current capacity or completion status, and will not present an estimate as fact.

Workforce, Land and Human Rights Questions

NEOM’s construction workforce and its effect on the local Huwaitat tribe have drawn sustained, independent scrutiny. Human rights organisation ALQST published a report, “The Dark Side of NEOM,” in February 2023, documenting forced displacement of Huwaitat families from land inside the project’s footprint. Abdul Rahim al-Huwaiti, a Huwaitat tribesman, was killed by Saudi security forces in April 2020 after refusing to leave his family’s land — an incident widely reported at the time (Al Jazeera and others) and cited since as a flashpoint in the displacement dispute. Rights groups, including the Business & Human Rights Resource Centre, have separately reported that dozens of Huwaitat tribe members were arrested for opposing displacement, with several sentenced to death in cases dating to 2020–2023; this page cites those as documented allegations tied to specific reporting dates, not as an independently verified current tally, since Saudi authorities have disputed elements of this coverage.

On working conditions, ITV’s undercover documentary “Kingdom Uncovered,” broadcast October 24, 2024, filmed workers on The Line describing 16-hour shifts across up to 14 consecutive days, unpaid commutes of roughly three hours, and around four hours of sleep per night, with several workplace accidents cited within a single month. Human rights researcher Nicholas McGeehan, interviewed for the documentary, said the reported hours were “way beyond international minimum standards.” A separate, frequently cited figure — roughly 21,000 migrant worker deaths — refers to Vision 2030’s broader construction sector since 2016, compiled from Indian, Bangladeshi and Nepali government data on their nationals’ deaths in Saudi Arabia generally; it is not a NEOM- or Line-specific death toll, and should not be presented as one.

⚠️ Editorial Note on Contested Claims

Displacement, worker-treatment and death-toll figures in this section come from human rights organisations and investigative journalism, not from NEOM or the Saudi government, which have disputed aspects of this reporting in the past. Where sources conflict or a figure cannot be independently re-verified, this page says so rather than presenting one side as settled fact.

Environmental Questions Around The Line

Independent academic research has raised specific, measurable concerns about NEOM’s coastal construction. A sediment-dispersal modelling study led by researchers at UCLouvain, presented at the EGU General Assembly in 2025, found that fine sediment disturbed by NEOM’s coastal development can remain suspended in the water column for up to a month and travel as far as 200 km from its release point — a mechanism that could threaten Gulf of Aqaba and northern Red Sea coral reefs otherwise known for unusual heat resilience. This is the strongest independently sourced environmental evidence available on NEOM’s coastal impact as of this update, and it is a modelling study, not a measured outcome, so it is presented here as such.

How The Line Compares With Other Megaprojects

The Line is unusual even among modern megaprojects for how much of its identity rested on a single geometric claim — a 170 km straight line — rather than a functional description. Saudi Arabia’s own high-speed rail comparisons internationally, like India’s Mumbai–Ahmedabad bullet-train corridor, show a more conventional megaproject pattern: a fixed route between two existing cities, phased station-by-station delivery, and a single primary technical challenge (in that case, elevated viaduct construction) rather than an entirely new city built from nothing. NEOM’s own architectural megaproject peer, the Jeddah Tower, offers a closer regional comparison: another Saudi vertical-scale project that has faced its own multi-year construction pauses, illustrating that funding and logistics — not just novelty of design — are the recurring constraint on the kingdom’s most ambitious builds.

People Also Ask

Is NEOM a real city yet?
Parts of NEOM exist and operate today — NEOM Bay Airport (since 2021) and Sindalah resort island (VIP-opened October 2024) among them — but The Line, NEOM’s flagship linear city, remains at roughly 2.4 km of foundation work, with construction paused since September 2025.
Why did NEOM’s cost estimate rise so much?
A leaked internal audit reported by the Wall Street Journal in March 2025 said executives had built overly optimistic cost assumptions into the business plan; when corrected, the audit projected up to $8.8 trillion and a 2080 completion date. NEOM has not officially confirmed this figure.
What is the Huwaitat tribe controversy?
Human rights groups including ALQST have documented forced displacement of the Huwaitat tribe from land inside NEOM’s footprint, including the 2020 killing of tribesman Abdul Rahim al-Huwaiti by Saudi security forces and the reported arrest and sentencing of other tribe members who opposed relocation.
Can tourists visit NEOM in 2026?
Sindalah, NEOM’s resort island, held a VIP launch in October 2024 but industry reporting says it was still not open to general public bookings as of mid-2026. Most of NEOM’s broader site remains an active or paused construction zone, not a tourist destination.
Is The Line cancelled?
No official cancellation has been announced. PIF governor Yasir Al-Rumayyan said in April 2026 that no NEOM projects had been cancelled, even though several major contracts tied to The Line were terminated the previous month and construction has been paused since September 2025.

Frequently Asked Questions

What is The Line in NEOM?
The Line is a proposed linear urban development within Saudi Arabia’s wider NEOM project on the Red Sea, unveiled in January 2021 as a 170-kilometre, car-free city. As of August 2026, roughly 2.4 kilometres of foundation work has been built, and construction is paused pending a strategic review.
Is The Line actually being built?
Construction produced roughly 2.4 km of foundation and earthworks near the Gulf of Aqaba before being paused around September 16, 2025. As of August 2026 that pause remains in effect, with resumption pushed past 2030 according to a May 2026 report.
How long is The Line supposed to be?
170 kilometres, per the original January 2021 announcement. That remains NEOM’s stated long-term vision, though reports from April 2024 said the near-term 2030 target had been privately cut to about 2.4 km.
How much of The Line has actually been built?
Independent reporting consistently cites roughly 2.4 kilometres of completed foundation and earthworks — about 1.4% of the original 170 km plan — as of the September 2025 construction pause, with no confirmed expansion reported since.
Is The Line still planned to be 170 km long?
170 km remains NEOM’s unretracted long-term design figure. No official statement has replaced it, but the near-term, 2030-dated version of that plan has effectively already been scaled down to what was actually built.
When will The Line be completed?
There is no credible, current completion date. Construction has been paused since roughly September 2025, and a May 2026 report said NEOM has pushed any resumption past 2030. A leaked 2024 internal audit, reported by the WSJ, projected full completion around 2080 — a figure NEOM has not confirmed.
What was built first in The Line?
Foundation and earthworks near the Gulf of Aqaba, starting with site preparation visible in satellite imagery from late 2022 and continuing through the September 2025 pause, totalling roughly 2.4 kilometres.
Is The Line a city?
As designed, yes — a linear urban development intended to house residents, businesses and infrastructure. As built, no part of it currently functions as an inhabited city; construction remains at the foundation stage and is paused.
Does The Line have roads?
The original design explicitly excludes conventional streets and private cars, relying instead on a high-speed transit spine. No such transit system has been independently verified as built as of August 2026.
How will people travel inside The Line?
The design calls for a high-speed underground transit system intended to connect any two points within a target travel time, replacing private cars entirely. This system remains a design concept; a related ~$1 billion tunnel contract for Line infrastructure was terminated in March 2026.
Will The Line have a high-speed railway?
That is the design intent, but no rail infrastructure for The Line has been independently confirmed as built. A 12.5-kilometre tunnel contract related to this system, held by Hyundai E&C, Samsung C&T and Archirodon, was cancelled in March 2026.
How much will The Line cost?
No official Line-specific cost figure exists. The wider NEOM project was originally budgeted at $500 billion in 2017; a leaked internal audit reported by the WSJ in March 2025 projected up to $8.8 trillion for full-scope completion, a figure NEOM has not confirmed.
Who is funding NEOM?
Saudi Arabia’s Public Investment Fund (PIF), the kingdom’s sovereign wealth fund, is NEOM’s primary funder. PIF disclosed an $8 billion writedown on its megaproject investments, NEOM included, in August 2025.
What is NEOM?
NEOM is a roughly 26,500 km² regional development in northwest Saudi Arabia, announced in October 2017 as a $500 billion pillar of Vision 2030’s economic diversification strategy. The Line is one project within it, alongside Oxagon, Trojena and Sindalah.
What is the difference between NEOM and The Line?
NEOM is the entire regional development; The Line is one specific 170 km linear-city concept inside it. Headlines about NEOM’s other projects, like Oxagon or Sindalah, are not automatically news about The Line’s own construction status.
Is The Line environmentally sustainable?
The design targets 100% renewable energy and minimal land disturbance, but independent research, including a 2025 UCLouvain sediment-dispersal study, has raised concerns that coastal construction sediment could travel up to 200 km and affect Red Sea coral reefs.
Has The Line been scaled back?
No official reduction has been announced, but reports from April 2024 described a near-term target cut from 170 km to 2.4 km, which matches what was later actually built. Construction is paused, and PIF’s governor said in April 2026 that a 2030 completion “is not a must.”
What is the latest NEOM construction update in 2026?
As of August 2026, Line construction remains paused since September 2025, with resumption pushed past 2030 per a May 2026 report. NEOM terminated over $5 billion in Line and Trojena contracts in March 2026, while Oxagon’s green hydrogen and AI data centre projects continue.
What has NEOM completed so far?
NEOM Bay Airport (operational since 2021), Sindalah resort island (VIP-opened October 2024, not yet public), and roughly 2.4 kilometres of Line foundation work are the project’s most concrete, independently verifiable completions to date.
Why is Saudi Arabia building The Line?
The Line was framed as a new model of car-free, high-density urban living and as a flagship project of Vision 2030, Saudi Arabia’s strategy to diversify its economy away from oil through tourism, technology and new industries.
Why was NEOM’s CEO replaced?
Nadhmi Al-Nasr, NEOM’s CEO since 2018, was replaced by Aiman Al-Mudaifer on November 12, 2024. NEOM’s own statement gave no reason; trade press reporting linked the change to conduct allegations and growing doubts about the project’s near-term viability.
What is Oxagon?
Oxagon is NEOM’s planned automated port and industrial hub on the Red Sea coast. As of May 2026 it was reported as NEOM’s priority node, home to a green hydrogen plant (~90%+ complete, April 2026) and a $5 billion first-phase AI data centre signed with DataVolt in February 2025.
What is Trojena and did it lose the Asian Winter Games?
Trojena is NEOM’s planned year-round mountain and ski resort. It was awarded the 2029 Asian Winter Games in 2022, but Saudi Arabia withdrew as host in January 2026, and Trojena’s Ski Village steel and dams contracts were both terminated in March 2026.
Is Sindalah open to visitors?
Sindalah held a VIP launch event on October 27, 2024, but industry reporting (AGBI, July 2026) said it still had not opened for general public bookings as of mid-2026, despite the island being physically complete.
What happened to NEOM’s construction contracts in 2026?
In March 2026, NEOM terminated a cluster of major contracts, including a ~$1 billion Line tunnel package and a $1.15 billion Trojena steel contract, worth a combined $5 billion or more according to contractor disclosures reported by Dezeen, MEED and Reuters.
Are there human rights concerns around The Line’s construction?
Yes. Human rights organisations including ALQST have documented forced displacement of the Huwaitat tribe from NEOM’s footprint, and an October 2024 ITV documentary filmed workers reporting shifts of up to 16 hours across 14 consecutive days. Saudi authorities have disputed elements of this reporting.

⚠️ Editorial Note

This page separates NEOM/Saudi official statements, contractor disclosures, independent journalism (Bloomberg, Reuters, WSJ, Dezeen, MEED and others) and human-rights reporting, and labels each accordingly. Figures describing leaked audits, reported scope changes or contested human-rights claims are presented as reported, not as confirmed fact, and are updated as official statements or stronger evidence become available. This is not investment, legal or travel advice.