Nuclear Fusion Timeline 2026: The Race to Put Fusion Power on the Grid
How close is fusion to the grid in 2026? SPARC, ARC, Helion Polaris, Orion, ITER, China's BEST and UK STEP, tracked with every date labelled by type.
For seventy years, fusion research was dominated by one question: could scientists create and control the conditions that power the Sun? By 2026 that question has largely been answered in the laboratory, and a harder one has taken its place. The Nuclear Fusion Timeline 2026 tracks the shift from physics demonstration to power-plant engineering — magnets, tritium fuel cycles, heat-exhaust systems, materials that survive neutron bombardment, and, above all, whether any of it can connect to a grid and deliver electricity on demand. Producing a fusion reaction is not the same as running a power plant, and that distinction runs through every section below.

📑 Jump to a section20 sections
Research Phase August 2026: China’s Institute of Plasma Physics (ASIPP) completed a 582-tonne superconducting magnet, described as the world’s largest, for the BEST tokamak in Hefei; CFS continued ARC engineering work following its five peer-reviewed design papers.
Achieved July 29, 2026: ITER installed the sixth of nine vacuum-vessel sector modules, putting two-thirds of the tokamak core in place roughly six months ahead of schedule; the final sector is now expected around mid-2027.
Government Target June 2026: The US Department of Energy released the finalised Fusion Science & Technology Roadmap, aligning public and private timelines around a US fusion pilot plant in the mid-2030s.
Achieved June 16, 2026: Helion became the first company ever to receive regulatory licenses for a fusion power plant — a Radioactive Materials License and Radioactive Air Emissions License from Washington State for its Orion facility in Malaga.
Company Target February 2026 (achieved January 2026): Helion’s Polaris prototype reported the first measurable deuterium-tritium fusion by a privately developed machine, with plasma temperatures around 150 million°C.
📌 Fusion in 2026, in 90 Words — AI Overview
No commercial fusion power plant is operating anywhere in 2026, and none is connected to a grid. What changed this year is engineering, not physics: the US DOE finalised a roadmap targeting pilot plants in the mid-2030s, ITER passed two-thirds tokamak-core assembly, Helion won the first-ever regulatory licenses for a fusion plant and reported deuterium-tritium fusion on its Polaris prototype, and China advanced construction of its BEST reactor toward a 2030 electricity-generation demonstration. Every date beyond that is a target, not a delivery.
Fusion Power: The Questions People Actually Ask
Key Takeaways
- Fusion research has moved from asking “can it work?” to asking “can it become a power plant?” — a materials, fuel-cycle and heat-exhaust problem, not just a plasma-physics one.
- No commercial fusion electricity exists anywhere in 2026. Every operating date beyond this year is a target: government, company, or construction estimate — never a guarantee.
- The US DOE’s June 2026 Fusion Science & Technology Roadmap aligns public and private efforts around a pilot plant in the mid-2030s, built with over 800 scientists and engineers from 15+ companies and 70+ universities.
- Helion holds two firsts in 2026: the first private reactor to report measurable deuterium-tritium fusion (February) and the first-ever regulatory licenses for a fusion power plant (June), for its Orion facility supplying Microsoft from 2028.
- ITER is a research machine, not a power plant — it will never sell electricity. Its tokamak core passed two-thirds assembly in July 2026, and deuterium-tritium operations remain scheduled for 2039 under its current baseline.
- China’s BEST reactor is targeting a fusion electricity-generation demonstration around 2030, backed by the world’s largest fusion magnet, completed in August 2026.
- Private fusion companies raised a record $4.48 billion in the 12 months to July 2026, per the Fusion Industry Association — bringing cumulative private+public investment to $14.24 billion.
- Scientific energy gain (a plasma or laser target producing more energy than was delivered to it) is not the same as whole-facility net energy, which is not the same as electricity actually exported to a grid. This page keeps the three separate throughout.
- India is a founding ITER member, supplying the project’s largest single component — the 3,850-tonne cryostat — plus in-wall neutron shielding, through the Institute for Plasma Research.
- AI data centres are adding urgency to fusion’s business case as a source of firm, 24/7 clean power — but AI did not start fusion research, and no data centre runs on fusion electricity today.
Fusion Milestones Are Not All the Same
This is the single most misunderstood part of fusion reporting — a plasma “gain” headline and a power-plant milestone are different things.
| Term | What It Means | Achieved? |
|---|---|---|
| Fusion reaction | Atomic nuclei physically fuse, releasing energy | Yes, routinely, since the 1950s |
| Plasma / scientific breakeven (Q) | Fusion energy output compared with energy delivered to heat the plasma or target | Achieved in specific, defined experiments (e.g. NIF 2022) |
| Scientific energy gain | Fusion energy exceeds energy delivered to the fuel target, under a stated measurement boundary | Demonstrated in specific shots, not routinely repeatable yet |
| Facility net energy | The entire facility, including lasers/magnets/cooling, produces more usable energy than it consumes | Not yet achieved anywhere |
| Net electricity | A plant exports electricity to the grid | Not yet commercially demonstrated by any fusion facility |
| Pilot plant | An integrated, first-of-a-kind prototype intended to produce electricity | Under construction (Orion, BEST) or in design (ARC, STEP, ST-E1) |
| Commercial fusion | Repeatable, economically viable electricity sold to a grid | Not yet achieved; 2028–2040 target range across all programmes |
What does fusion “Q” actually mean? Reports often say a machine “achieved net energy” without specifying which energy boundary. NIF’s December 2022 shot delivered 2.05 megajoules of laser energy to its target and got 3.15 megajoules of fusion energy back — a real, independently verified result. But the lasers themselves drew roughly a hundred times that much electricity from the wall to fire, because today’s laser systems are highly inefficient at converting grid power into light. So the same experiment was simultaneously a landmark for target-level scientific gain and nowhere close to facility-level net energy. Whenever this page uses “gain,” it specifies which boundary is meant.
Nuclear Fusion Timeline: From Laboratory Physics to the Grid
Chronological. Each entry is tagged by what kind of claim it is — see the legend above.
Eddington Proposes Stellar Fusion
British astrophysicist Arthur Eddington suggests stars generate energy by fusing hydrogen into helium, laying the theoretical foundation everything below builds on.
60s
Magnetic Confinement Takes Shape: Stellarator and Tokamak
Lyman Spitzer’s Project Sherwood (1951) develops the stellarator concept in the US; Soviet scientists led by Lev Artsimovich unveil striking plasma results from the T-3 tokamak in the 1960s, which the wider field rapidly adopts as the standard magnetic-confinement design.
ITER Is Proposed, Then Signed
Reagan and Gorbachev propose a joint international tokamak in 1985; after site negotiations, Cadarache, France, is chosen and the ITER Agreement is signed in 2006 by the EU, US, Russia, China, Japan, South Korea and India.
NIF Achieves Fusion Ignition
The National Ignition Facility delivers 2.05 megajoules of laser energy to a fuel target and measures 3.15 megajoules of fusion energy back — the first laboratory demonstration of target-level scientific gain. The facility itself still drew far more electricity than it produced; see the definitions table above.
Helion Signs the World’s First Fusion Power-Purchase Agreement
Microsoft agrees to buy at least 50 MW of electricity from Helion’s planned Orion plant starting in 2028 — the first commercial contract for fusion power anywhere, years before the plant exists.
STEP Moves to Delivery; India Completes Cryostat Milestones
The UK’s STEP programme advances from concept design toward delivery at West Burton; India’s ITER-India programme continues manufacturing progress on the ITER cryostat and in-wall shielding, its largest in-kind contributions.
Helion’s Polaris Reports Deuterium-Tritium Fusion
Helion announces (achieved in January, announced February 13) that its seventh-generation Polaris prototype became the first privately developed machine to demonstrate measurable D-T fusion, with plasma temperatures around 150 million°C — a company-reported milestone, not yet independently replicated by a third party.
DOE Roadmap and Helion’s Regulatory Licenses
The US DOE finalises its Fusion Science & Technology Roadmap targeting a mid-2030s pilot plant; days later, Helion becomes the first company ever to hold regulatory licenses (RML and RAEL) for a fusion power plant, at Orion in Malaga, Washington.
ITER Passes Two-Thirds Tokamak-Core Assembly
ITER lowers its sixth of nine vacuum-vessel sector modules into the tokamak pit on July 28–29, roughly six months ahead of schedule — a construction milestone, not an operating one. ITER remains an experimental facility that will never sell electricity.
China Completes the World’s Largest Fusion Magnet
China’s Institute of Plasma Physics finishes a 582-tonne superconducting magnet for the BEST tokamak, clearing a major hurdle toward the reactor’s targeted 2027 construction completion.
Near-Term Targets: BEST Completion, SPARC Plasma, Orion Power
China aims to finish BEST construction by end-2027; Commonwealth Fusion Systems is targeting first plasma on SPARC around 2027; Helion is targeting at least 50 MW of electricity from Orion starting in 2028, ramping over roughly one year.
2030s
ARC, BEST Electricity Demo and the DOE Pilot Window
CFS targets its ~400 MW ARC plant beginning to supply grid power in the early 2030s; China targets a BEST net-fusion-power and electricity-generation demonstration around 2030; the DOE roadmap targets a US pilot plant across the “mid-2030s.”
ITER’s Research Operations
Under ITER’s 2024 baseline: Start of Research Operation in 2034, deuterium-deuterium plasma operation in 2035, full magnetic energy in 2036, and deuterium-tritium operation — the actual fusion fuel mix — from 2039. ITER will not generate commercial electricity at any point in this sequence.
UK STEP’s First Operations Target
The UK’s STEP prototype plant targets first operations in 2040, demonstrating at least 100 MW of net energy “as soon as practicable” — a deliberately conservative government target, not a race-to-be-first bet.
Fusion Race to the Grid — 2026 Dashboard
Every date here is a target. None is a delivery.
| Project | Technology | Current Machine | Next Milestone | Target Window | Status |
|---|---|---|---|---|---|
| Commonwealth Fusion Systems | Tokamak / HTS magnets | SPARC | ARC (~400 MWe design) | Early 2030s | SPARC construction |
| Helion | Pulsed FRC, direct conversion | Polaris | Orion, 50 MW+ | 2028 | Plant construction, licensed |
| China BEST | Tokamak, D-T burning plasma | Under construction | Electricity demonstration | ~2030 | Construction (magnet complete) |
| Tokamak Energy | Spherical tokamak / HTS | ST40 (upgrading) | ST-E1 pilot plant | Early 2030s (company target) | Design + DOE programme |
| UK STEP | Spherical tokamak prototype plant | Design/consultation | Grid prototype, 100+ MW | 2040 | Delivery phase, pre-construction |
| ITER | Large tokamak (research only) | Two-thirds assembled | D-T research operations | 2039 | Assembly, no electricity planned ever |
Commonwealth Fusion Systems: SPARC to ARC
CFS, spun out of MIT, builds compact high-field tokamaks using high-temperature superconducting (HTS) magnets. SPARC is the demonstration machine, meant to prove the physics case for net energy gain in a compact device; CFS installed SPARC’s first superconducting magnet in early 2026, and is now targeting first plasma around 2027 after earlier, more optimistic dates slipped. ARC is the separate, proposed commercial plant — do not confuse the two. CFS describes ARC as designed around approximately 400 MW of net electricity, enough for on the order of 150,000–300,000 homes by the company’s own estimate, targeting a Virginia site with Dominion Energy as a strategic partner. Under the DOE’s Milestone-Based Fusion Development Program, CFS has cleared preconceptual-design and technology-roadmap milestones for ARC, backed by five peer-reviewed papers examining the plant’s physics. CFS has raised over $4 billion to date, including an $863 million round in 2026 that brought in Nvidia’s venture arm alongside existing backers Google, Eni, Breakthrough Energy Ventures and a consortium of Japanese industrial firms; Google and Eni have separately signed power-purchase agreements covering more than half of ARC’s planned output — before the plant is built. ARC is being designed to deliver that output; it does not yet exist.
Helion: Racing to Deliver Fusion Electricity by 2028
Helion’s approach is not a tokamak. It uses a pulsed field-reversed configuration (FRC): magnetically confined plasmoids are accelerated and collided, compressed by pulsed magnetic fields, and the fusion reaction’s energy is captured largely through direct electromagnetic conversion rather than heating a coolant to drive a turbine. Polaris is the current, seventh-generation prototype; in a company announcement made February 13, 2026, Helion reported that Polaris achieved measurable deuterium-tritium fusion in January 2026, with plasma temperatures around 150 million°C — about three-quarters of what Helion believes it will need for commercial operation, by its own account. Orion is Helion’s proposed first grid-supplying plant, under construction in Malaga, Washington. It carries a 2023 power-purchase agreement with Microsoft for at least 50 MW starting in 2028, ramping to full output over roughly a year. In June 2026, Helion became the first fusion company ever to hold a Radioactive Materials License and Radioactive Air Emissions License from Washington State — a real regulatory milestone, but one that confirms safety-programme readiness, not that net power has been proven or that Microsoft is yet receiving electricity.
ITER: The World’s Biggest Fusion Experiment
ITER, in Cadarache, France, is a joint research project of the EU, US, Russia, China, Japan, South Korea and India, built to demonstrate the scientific and technological feasibility of fusion — not to generate electricity. ITER will never sell power to a grid. Its mission is proving that a burning, self-sustaining plasma can be controlled at scale, informing every power-plant design that follows it. On July 28–29, 2026, ITER lowered the sixth of nine roughly 1,100-tonne vacuum-vessel sector modules into the tokamak pit, putting two-thirds of the core in place about six months ahead of schedule; the final sector is now expected around mid-2027. Under ITER’s 2024 baseline, Start of Research Operation begins in 2034, deuterium-deuterium plasma operation in 2035, full magnetic energy in 2036, and operation with the actual fusion fuel — deuterium-tritium — from 2039. That is roughly four years later than the 2016 baseline, attributed to the pandemic, quality issues, and, ITER’s own leadership has acknowledged, overly optimistic early planning for a first-of-a-kind machine.
China: EAST and BEST
EAST (Experimental Advanced Superconducting Tokamak), in Hefei, is China’s long-running research device, known for repeated long-duration, high-confinement plasma records that inform reactor design worldwide — it is a research tool, not a power plant. BEST (Burning Plasma Experimental Superconducting Tokamak), under construction at the same Hefei complex, is China’s next step: a machine explicitly designed to demonstrate actual burning deuterium-tritium plasma. In August 2026, China’s Institute of Plasma Physics completed what it describes as the world’s largest fusion magnet — a 582-tonne superconducting coil for BEST — alongside a 400-tonne-plus Dewar base, the largest vacuum component China’s fusion programme has produced. China is targeting BEST construction completion by the end of 2027, with a net fusion-power gain and electricity-generation demonstration targeted around 2030 — state media has called this “lighting humanity’s first nuclear-fusion-powered lamp.” That framing is a government target, not a confirmed outcome.
STEP: Britain’s Fusion Power Plant Programme
Run by the UK Atomic Energy Authority, STEP (Spherical Tokamak for Energy Production) aims to build a prototype fusion power plant at West Burton, Nottinghamshire, the site of a former coal power station. In 2026 the programme moved from concept design into delivery: a public consultation ran January 14 to March 11, a construction partner was appointed for a £200 million site redevelopment, and up to 10,000 jobs are projected by 2030 tied to the redevelopment. Plant assembly and infrastructure construction are planned to begin in the 2030s once planning permissions are secured, with first operations targeted in 2040, demonstrating at least 100 MW of net energy “as soon as practicable.” STEP is currently the only major government programme with an explicit 100 MW-plus grid target and a public date, deliberately set later than several private-company targets.
Tokamak Energy: Spherical Tokamaks and HTS Magnets
Tokamak Energy builds compact spherical tokamaks using high-temperature superconducting magnets. Through 2026, its ST40 device is undergoing a $52 million upgrade — jointly funded with the US DOE and the UK’s Department for Energy Security and Net Zero — adding lithium plasma-facing systems and RF heating. Its Demo4 magnet set reached 11.8 tesla at −243°C carrying seven million ampere-turns, a real HTS-engineering result. The company’s power-plant plan, ST-E1, targets up to 200 MWe delivered to a grid in the early 2030s — a company target pursued through the US Milestone-Based Fusion Development Program, alongside a magnet-technology role in STEP. A separate demonstration device, ST80-HTS, had not been confirmed complete as of mid-2026 and no longer features prominently in the company’s public roadmap.
Beyond CFS and Helion: The Wider Fusion Industry
TAE Technologies
Pursues aneutronic hydrogen-boron fusion using FRC plasmas; long-running R&D programme, no public grid date yet.
Zap Energy
Uses plasma current itself for confinement, avoiding large external magnets; targeting a compact, low-cost reactor design.
Type One Energy & Proxima Fusion
Both pursue stellarators — magnetically complex but potentially steadier-running than pulsed tokamaks; both in early design/prototype stages.
Pacific Fusion & Xcimer
Private laser/pulsed-power approaches building on NIF-style inertial confinement, aiming for higher repetition rates than NIF’s research lasers.
General Fusion
Combines magnetic confinement with mechanical compression; long-standing Canadian programme, pilot-plant design stage.
Marvel Fusion & Realta Fusion
Marvel pursues laser-driven proton-boron fusion in Germany; Realta develops mirror-confinement devices spun out of University of Wisconsin research.
There Is More Than One Way to Build a Fusion Reactor
| Approach | Example | Basic Idea |
|---|---|---|
| Conventional tokamak | ITER, EAST/BEST | Doughnut-shaped magnetic confinement |
| Spherical tokamak | Tokamak Energy, STEP | Compact, more efficient magnetic confinement |
| Stellarator | Type One Energy, Proxima | Twisted, complex magnetic confinement, steadier plasma |
| Field-reversed configuration | Helion, TAE | Pulsed, self-contained magnetic plasmoids |
| Sheared-flow Z-pinch | Zap Energy | Plasma’s own current provides confinement |
| Inertial confinement | NIF, Pacific Fusion, Xcimer | Lasers compress a tiny fuel pellet |
| Magnetized target | General Fusion | Magnetic confinement plus mechanical compression |
If Fusion Powers the Sun, Why Is It So Hard on Earth?
The Sun fuses hydrogen using immense gravitational pressure at its core, at “only” around 15 million°C. Earth has no equivalent gravity well, so terrestrial reactors substitute much higher temperatures — often above 100 million°C — confined by magnetic fields or inertial compression, and must build every part of the physical environment gravity provides for free inside a star.
The engineering problems plasma success alone doesn’t solve
- Tritium: Deuterium is abundant, but tritium is scarce and radioactive. A commercial plant likely needs to “breed” its own tritium from lithium in a surrounding blanket — an unproven fuel-cycle loop at power-plant scale.
- Materials: 14.1 MeV neutrons from D-T fusion degrade and activate reactor-wall materials over time, driving embrittlement and maintenance needs that remain an active research area.
- Magnets: High-temperature superconductors let CFS, Tokamak Energy and others build much smaller, higher-field magnets than older designs — the single biggest engineering shift of the last decade.
- Heat exhaust: Removing extreme, concentrated heat flux from the plasma-facing “divertor” without destroying it is one of the least publicly understood, most stubborn bottlenecks in reactor design.
- Electricity conversion: Most tokamak-style designs still convert fusion heat to electricity the conventional way — neutrons heat a blanket, which heats a coolant, which drives a steam turbine. Helion’s FRC approach is the notable exception, using direct electromagnetic conversion instead.
Scientific Breakeven Is Not Economic Breakeven
A viable power plant must also pay for its reactor, magnets, fuel cycle, turbines or conversion hardware, cooling, ongoing maintenance, component replacement after neutron damage, financing, grid connection and staff. No commercial fusion fleet exists anywhere, so real market electricity costs remain unknown; where companies publish cost targets, they are projections, not observed prices, and this page does not repeat any of them as fact.
| Metric (Fusion Industry Association, 2026 report) | Figure |
|---|---|
| Private funding raised, 12 months to July 2026 | $4.48 billion — a record year |
| Cumulative funding to date | $14.24 billion total ($13.26B private + $980.7M public) |
| Fusion supply-chain spend, 2025 | $538 million (surveyed companies), up 24% year-on-year |
| Projected supply-chain spend, 2026 | $681 million (projected, +27%) |
| Suppliers investing to expand fusion capacity | 75% of surveyed suppliers, from $30,000 to $65 million each |
Fusion vs Nuclear Fission
| Fusion | Fission | |
|---|---|---|
| Basic reaction | Combines light nuclei | Splits heavy nuclei |
| Commercial today | No | Yes, since the 1950s |
| Self-sustaining chain reaction risk | No — reaction stops without continuous confinement | Yes, actively managed by design |
| Long-lived radioactive waste | Lower potential, but not zero — neutron-activated structural material | Significant, well-characterised |
| Fuel | Deuterium/tritium (or advanced fuels) | Uranium/plutonium |
| Reactor maturity | Experimental, pre-commercial | Commercial, mature |
Is fusion safe? Fusion avoids the risk of a runaway chain reaction because the reaction stops as soon as confinement is lost — a real, structural safety advantage over fission. But it is not risk-free: it involves tritium handling, neutron-activated materials, powerful magnetic fields, cryogenic systems and standard industrial hazards. Does fusion create radioactive waste? Yes, though the profile differs from fission — neutron activation of structural materials produces waste that is generally shorter-lived, but “zero waste” is not an accurate claim for any current design.
India’s Role in the Global Fusion Race
India has been a full ITER member since the project’s 2006 founding agreement, and its domestic fusion research is coordinated by the Institute for Plasma Research (IPR) in Gandhinagar, home to India’s own SST-1 superconducting tokamak. Through ITER-India, India delivered the project’s single largest component: the 3,850-tonne cryostat, a 30-metre vacuum chamber housing the entire tokamak, designed by ITER-India and manufactured with Larsen & Toubro. India also manufactured the in-wall shielding — roughly 8,900 individual blocks providing neutron shielding between the vacuum vessel’s double walls — through Avasarala Technologies of Bengaluru, plus cooling-water systems, high-voltage power supplies and diagnostic neutral-beam systems. India does not currently have a domestic commercial fusion power-plant programme; its role to date is as a major engineering and manufacturing contributor to the international research effort.
Who Says They Can Put Fusion on the Grid — and When?
| Project | Claim / Target | What Must Happen First | Status |
|---|---|---|---|
| Helion Orion | 2028 initial operation, 50 MW+ | Complete plant, validate Polaris net-power path | Company Target |
| China BEST | ~2030 electricity demonstration | Finish construction (targeted end-2027), operate burning plasma | Government Target |
| CFS ARC | Early 2030s | SPARC success (~2027 first plasma), ARC construction | Company Target |
| Tokamak Energy ST-E1 | Early 2030s, up to 200 MWe | ST40 upgrade complete, pilot-plant design finalised | Company Target |
| DOE pilot plant pathway | Mid-2030s | Sustained funding, private-sector milestones on schedule | Government Target |
| UK STEP | 2040, 100+ MW net | Design, planning permission, construction (2030s) | Government Target |
| ITER | Not commercial electricity, ever | D-T research operations from 2039 | Research Phase |
Is Fusion Always “30 Years Away”?
The old joke persists because fusion schedules have genuinely slipped for decades — ITER’s own baseline has moved roughly four years later than its 2016 plan, and CFS’s SPARC date has moved from earlier public estimates to around 2027. First-of-a-kind hardware, novel materials, complex regulation and global supply chains all slow first attempts; that is normal engineering history, not unique dishonesty. What has genuinely changed since the “30 years away” era: high-temperature superconducting magnets that shrink reactor size and cost, far greater computing power for plasma simulation and control, private capital exceeding $14 billion cumulatively, and, in 2026, the first-ever regulatory approval of a fusion plant. What has not disappeared: the fuel cycle, materials survivability, heat exhaust and economics. Both things are true at once — real progress, and continued reasons for scrutiny of any specific date.
Why AI Is Adding Urgency to the Fusion Race
AI did not start fusion research, which predates it by seven decades. But GPU-cluster data centres now demand enormous, continuous (“firm”) electricity, straining grids in ways utilities are actively planning around — and that demand is one factor behind Microsoft’s Helion contract and Google/Eni’s ARC power-purchase agreements. No data centre runs on fusion electricity today; these are forward contracts for plants still under construction. Separately, AI tools are genuinely used inside fusion labs — for real-time plasma-instability prediction and control, and for materials and reactor-design simulation — but AI has not “solved fusion,” and no credible lab claims it has.
People Also Ask
Frequently Asked Questions
Fusion in 2026: The Race Has Moved Beyond the Laboratory
Fusion has already crossed milestones that once seemed remote: high-performance plasmas, a genuine laboratory ignition result, advanced superconducting magnets, and now a private machine reporting deuterium-tritium fusion and the first-ever regulatory licenses for a fusion plant. But a commercial power plant demands far more than a good plasma shot: durable materials, a working fuel cycle, functioning heat exhaust, financing, regulation, and — the only test that actually matters commercially — electricity leaving the site often enough and reliably enough for a grid to depend on it.
The defining fusion breakthrough will not be another record plasma temperature. It will be a power plant that keeps sending electricity to the grid, day after day. That milestone has not happened yet, anywhere, as of August 2026.
⚠️ Editorial Note
This page distinguishes independently verified results from company-reported and government-target claims throughout, and avoids treating any future date as a guarantee. Compiled from the US Department of Energy, ITER Organization, UK Atomic Energy Authority (STEP), Chinese Academy of Sciences/ASIPP, Commonwealth Fusion Systems, Helion, Tokamak Energy, the Fusion Industry Association, and ITER-India/Institute for Plasma Research. Updated as new milestones are confirmed; not a substitute for primary sources.
Sources & References
US Department of Energy — Fusion Science & Technology Roadmap (June 2026) · ITER Organization — Two-Thirds Tokamak Core Assembly · Commonwealth Fusion Systems — SPARC · Helion Energy — Polaris D-T Fusion Milestone · Helion Energy — Orion Regulatory Licenses · Tokamak Energy · UK STEP Fusion Programme · Fusion Industry Association — 2026 Global Fusion Industry Report · ITER-India — India’s Contribution to ITER