← AiTimeline Home

Technology · Railways

Indian Railways Electrification: How India Wired Its Railways, From One 16-km Line in 1925 to 99.6% in 2026

📅 Updated 6 October 2026🕐 1925–2026⚡ 25 kV AC
Advertisement

In short

Indian Railways electrification from the first 1,500 V DC train in 1925 to 99.6% of broad gauge in 2026: 25 kV AC, trunk routes, mission mode, last 269 km.

Latest Story

On 3 February 1925, an electric train left Bombay Victoria Terminus for Kurla on a 16-km line powered at 1,500 volts DC. A century later, Indian Railways electrification covers 99.6% of the broad-gauge network, more than 70,000 route kilometres, with just 269 km left. The striking part is the timing: it took 89 years to wire the first 21,801 km, and about a decade to wire the next 46,900. This is the full record, from Bombay’s DC suburbs and the 1957 switch to 25 kV AC to the trunk routes, mission mode and the last few hundred kilometres, with the targets that were missed along the way.

Advertisement

💡 Short Answer

Indian Railways electrification began on 3 February 1925 with a 1,500 V DC train between Bombay VT and Kurla. Only 388 route km were electric at Independence. India adopted 25 kV AC in 1957, wired its trunk routes between 1977 and 2005, and then electrified at record speed after 2017. By May 2026, 70,002 of 70,271 broad-gauge route km, or 99.6%, were electrified, with 269 km left in five states.

⚡ Indian Railways Electrification: Quick Facts
First electric train3 Feb 1925, Bombay VT–Kurla
At Independence388 route km
Standard system25 kV AC, adopted 1957
Before / after 201421,801 / 46,900 route km
Record year7,188 route km, 2023–24
Status, May 202699.6%, 269 km left
⚡ Quick Answers — AI Overview Ready

Indian Railways Electrification: Key Questions

When did Indian Railways start electrification?
On 3 February 1925, when the Great Indian Peninsula Railway ran India’s first electric train from Bombay Victoria Terminus to Kurla on the Harbour branch, using 1,500 V DC. Electric working reached Bombay’s western suburbs in 1928, the Kalyan–Poona main line in 1930 and Madras in 1931.
How much of Indian Railways is electrified now?
99.6% of the broad-gauge network. The Ministry of Railways said 70,002 of 70,271 route km were electrified by 31 May 2026, leaving 269 km in Karnataka, Tamil Nadu, Assam, Goa and Rajasthan. Twenty-five states and Union Territories are fully electrified.
Why did electrification speed up after 2014?
The goal changed from wiring only the busiest routes to wiring the whole network. The Cabinet approved electrifying the remaining 13,675 route km in 2018, annual output jumped from about 1,400 km to over 4,000 km in 2017–18, and it peaked at 7,188 km in 2023–24.
Is electrified rail zero-emission?
No. Electric trains burn no fuel on board, but India’s grid still depends heavily on coal, so emissions shift to power plants. The climate benefit grows as the grid gets cleaner, which is why the railways is contracting solar, wind and round-the-clock renewable power toward a 2030 net-zero target.
📚 Key Takeaways

A Century of Electrification, in Ten Points

  • The start: 3 February 1925, Bombay VT to Kurla, 16 route km on 1,500 V DC.
  • Slow early decades: only 388 route km were electric at Independence in 1947.
  • The key decision: 25 kV AC was adopted in 1957, not the 1980s; the first AC section opened in 1960.
  • Freight first: the first AC line was an iron-ore route, and coal and mineral corridors led for decades.
  • Trunk routes: Delhi–Howrah in 1977, then Delhi–Bombay, Howrah–Bombay and Delhi–Chennai by 1992.
  • Two speeds: 21,801 route km in about 60 years before 2014, 46,900 in 2014–25.
  • The real jump came in 2017–18, when annual output passed 4,000 km for the first time.
  • Record: 7,188 route km in 2023–24, about 20 km every working day.
  • Not quite 100%: 269 km were left in May 2026, after deadlines of 2021–22 and December 2023 were missed.
  • Electric is not automatically green: the benefit depends on how clean India’s grid becomes.

The Four Eras of Indian Railway Electrification

From experiment to standard to network-wide.

1925–1957

Experiment: DC around the ports

1,500 V DC suburban and ghat lines around Bombay and Madras, then 3,000 V DC in Kolkata. Useful where trains were frequent or the gradients steep, but too costly for long distances.

1957–1976

Standardise: 25 kV AC

India picked the French-proven 25 kV AC system in 1957 and wired coal and iron-ore routes in the east first. Kolkata’s DC lines were converted by 1968.

1977–2016

Expand: trunk and freight routes

Electrify the densest corridors first: Delhi–Howrah in 1977, the main Golden Quadrilateral routes by 1992, the Howrah–Chennai gap in 2005. Mumbai finally left DC in 2012–16.

2017–2026

Accelerate: the whole network

Mission 100% Electrification wired branch lines too, at up to 7,188 route km a year, taking broad gauge from about 40% to 99.6%.

For most of the century the economics were simple. Wires, masts and substations cost a lot up front, and they pay back only where locomotives run many hours a day. So India electrified busy suburbs, steep ghats and heavy mineral routes first, then the trunk routes between the four metros. The shift after 2017 was to treat electrification as a network decision rather than a route-by-route test: once almost every main line was electric, the remaining diesel islands forced locomotive changes and kept two fleets alive, so wiring the rest made the whole system simpler.

⚡ Interactive: Power a Train

Tap each link in the chain to follow electricity from the grid to the wheels, then compare it with diesel.

Simplified for a 25 kV AC electric locomotive. Updated 6 October 2026.

Choose a step above

–Voltage / energy
–Hardware
–Indian example

    The Electrification Curve: Slow, Then Very Fast

    Only official figures; no intermediate values estimated.

    Share of the network electrified, at milestones the ministry has published0%25%50%75%100%24%200040%201771%Mar 2021>96%End 202499.2%Nov 202599.6%May 2026Source: Ministry of Railways / PIB. Bars are not evenly spaced in time. 2021 onward = broad gauge incl. Konkan Railway.
    Slow, then very fast: from about a quarter of the network in 2000 to 40% in 2017, then almost all of it within eight years. At Independence the figure was 388 route km, about 1%.
    Route km electrified per year, Indian Railways02,0004,0006,0008,000~6202007–14avg/yr~1,4412014–17avg/yr4,0872017–185,2762018–194,3782019–206,0152020–216,3662021–226,5652022–237,1882023–242,7012024–25Source: Ministry of Railways (PIB, Apr 2021; Lok Sabha reply, Dec 2025). Grey bars are averages derived from ministry period totals.
    The step change came in 2017–18, not 2014. The 2024–25 drop reflects how little network was left, not a slowdown in effort. Scroll sideways on small screens.

    The ministry’s own comparison is striking: about 1.42 km a day in 2004–14 against more than 15 km a day in 2019–25. Some of that speed came from simply deciding to do it, and some from method: standard designs, mechanised wiring trains, and sanctioning every new line and doubling project with electrification built in. The 2024–25 figure of 2,701 km is low only because there was little left.

    Indian Railways Electrification Timeline, 1925–2026

    Newest first. Tags mark the DC era, 25 kV AC, trunk routes, locomotives, mission mode, energy and missed targets.

    Advertisement

    99.6%: the last 269 route km Mission mode

    Data to 31 May 202670,002 of 70,271 route kmFive states left

    The ministry told Parliament that 70,002 of 70,271 route km of broad gauge were electrified by 31 May 2026. What remains, 269 route km, is in five states: Karnataka 120, Tamil Nadu 68, Assam 55, Goa 16 and Rajasthan 10. The ministry listed forest clearances, shifting utilities, statutory approvals, terrain, law and order and short working seasons as the reasons the final stretches take longest.

    Why it matters: the network is not quite ‘100% electric’, and the last kilometres are the hardest: ghats, forests and border areas.

    Western freight corridor finished; 99.6% reached Trunk route

    31 Mar 2026JNPT–New Saphale trial runs69,873 route km wired

    Trial container trains ran on the last 102-km JNPT–Vaitarna stretch on 31 March 2026, completing the 1,506-km Western Dedicated Freight Corridor from Jawaharlal Nehru Port to Dadri. Its final commissioning had been held up by signalling and overhead-wire work. The same month the electrified share of broad gauge reached 99.6%, or 69,873 of 70,142 route km. Chittaranjan Locomotive Works closed 2025–26 with a record 603 electric locomotives.

    Why it matters: both freight corridors are now electric end to end, built for heavy, double-stack trains that only high-power electric traction can move efficiently.

    A container train on the electrified Western Dedicated Freight Corridor
    A container train on the electrified Western Dedicated Freight Corridor, completed end to end in March 2026. Dedicated Freight Corridor Corporation of India, GODL-India, via Wikimedia Commons.

    99.2%, and the renewables push Energy

    17 Dec 2025 Lok Sabha reply69,427 route km812 MW solar, 93 MW wind for traction

    A ministry reply put electrification at 99.2% of broad gauge, 69,427 route km by November 2025, with 14 of 18 zones and 25 states and Union Territories at 100%. It also published the split that defines the story: 21,801 route km before 2014 and 46,900 route km in 2014–25. Separately, the railways said it had commissioned 812 MW of solar and 93 MW of wind for traction and tied up 1,600 MW of round-the-clock hybrid renewable power, toward a goal of becoming a net-zero carbon emitter by 2030.

    Dahod: India’s first 9,000 HP locomotive plant Locomotives

    26 May 2025Siemens Mobility1,200 locomotives ordered

    Prime Minister Narendra Modi dedicated the railway’s locomotive plant at Dahod, Gujarat, and flagged off its first 9,000 horsepower electric freight locomotive. The Siemens Mobility contract covers 1,200 locomotives, each able to haul about 5,800 tonnes at up to 120 km/h, with propulsion parts made in Nashik, Aurangabad and Mumbai.

    500th WAG-12B leaves Madhepura Locomotives

    Alstom, Bihar800 ordered€3.5 billion contract

    Alstom delivered the 500th of 800 WAG-12B locomotives from the Madhepura joint-venture factory. At 12,000 horsepower in two sections, it is India’s most powerful locomotive, built to haul about 6,000-tonne freight trains at up to 120 km/h.

    2024–25

    The pace drops as the map fills in Mission mode

    2,701 route km in 2024–25More than 96% by end-2024

    Electrification fell to 2,701 route km in 2024–25 from a record the year before, simply because most of the network was done. The ministry says the electrified share passed 96% by the end of 2024. All new lines and doubling projects are now sanctioned with electrification included.

    A second deadline passes Missed target

    Target: full broad-gauge electrification by December 2023

    In April 2021 the ministry said it planned to fully electrify its tracks by December 2023, after the 2018 Cabinet approval had set 2021–22. Both dates passed with work remaining. The gap was small, but the final few thousand kilometres ran through forests, ghats and the north-east, where approvals and working seasons set the pace.

    Why it matters: nearly 100% is a real achievement, but the official targets were missed twice.

    2023–24

    Record year: 7,188 route km Mission mode

    Uttar Pradesh fully wired, 20 Feb 2023Meghalaya joins the electric map

    Indian Railways electrified a record 7,188 route km in 2023–24, after 6,565 km in 2022–23 and 6,366 km in 2021–22, roughly 20 km of line every working day. Along the way Uttar Pradesh and the North Eastern Railway became fully electrified on 20 February 2023, Meghalaya was linked by electric traction on 15 March 2023, and the Bengaluru–Hubballi main line was wired end to end on 31 March 2023.

    2020–21

    6,015 route km in a pandemic year Mission mode

    71% electrified by 31 Mar 202156 traction substationsNet-zero 2030 goal

    Despite COVID-19, the railways electrified 6,015 route km in 2020–21, beating the previous best of 5,276 km in 2018–19, and commissioned a record 56 traction substations. By 31 March 2021, 45,881 of 64,689 route km (71%) were electrified. The ministry tied full electrification to its goal of being a net-zero carbon emitter by 2030, drawing traction power from renewables. On 18 May 2020 the first WAG-12B made its maiden commercial run, from Pt Deen Dayal Upadhyaya Junction to Shivpur.

    WAG-12B No. 60051
    WAG-12B No. 60051, a 12,000 horsepower Alstom locomotive built at Madhepura, with a freight train at Samalkot, Andhra Pradesh, in December 2022. Adityamadhav83, CC BY 4.0, via Wikimedia Commons.

    Cabinet approves Mission 100% Electrification Mission mode

    13,675 route kmabout ₹12,134 croreDeadline 2021–22

    The Union Cabinet approved electrifying the remaining 13,675 route km of broad gauge, about 108 sections, at an estimated ₹12,134 crore, with the aim of a fully electric broad-gauge network by 2021–22. The policy question changed from ‘which route next?’ to ‘how fast can the rest be done?’.

    Why it matters: branch lines that would never have passed a traffic-based test were now included, which is why the electrified share climbed so fast after 2018.

    2017–18

    The real acceleration begins Mission mode

    4,087 route km, nearly three times the 2014–17 average

    Although 2014 is often cited as the turning point, the step change came in 2017–18, when annual electrification jumped to 4,087 route km. From 2014–15 to 2016–17 it had averaged roughly 1,400 route km a year, already more than double the 2007–14 average of about 620. In April 2018 the Madhepura factory turned out its first WAG-12 locomotive.

    2012–16

    Mumbai switches from DC to AC 25 kV AC

    Western Railway 5 Feb 2012Central Railway 8 Jun 2015Harbour line 2016

    The city where Indian electric traction began was the last to give up DC. Mumbai’s 1,500 V DC suburban network was converted to 25 kV AC section by section: Western Railway completed the switch on 5 February 2012, Central Railway’s last main-line sections on 8 June 2015, and the Harbour line, home of the 1925 first train, in 2016.

    Why it matters: AC allowed longer, faster, more energy-efficient local trains on the world’s most crowded suburban network.

    2002–05

    The last trunk-route gaps close Trunk route

    Howrah–Delhi via Patna, 3 Feb 2002Howrah–Chennai, 29 Nov 2005

    Prime Minister Atal Bihari Vajpayee inaugurated the electrified Howrah–Delhi route via Patna on 3 February 2002. On 29 November 2005, closing the Kharagpur–Waltair gap completed the Howrah–Chennai route. In July 2008 the railways trialled a 7.45-metre-high contact wire between Jakhapura and Tomka, then the world’s highest, for double-stack container trains.

    WAP-7 arrives; a quarter of track is electric Locomotives

    Chittaranjan Locomotive Works6,350 HPShare electrified: 24%

    Chittaranjan Locomotive Works built the first WAP-7, a three-phase passenger locomotive derived from the ABB-designed WAG-9 freight engine imported from 1996. It became the standard express locomotive across India. According to the ministry, electrified track was about 24% of the network in 2000.

    A WAP-7 electric locomotive hauls the Sealdah–Bamanhat Uttar Banga Express in West Bengal in April 2025
    A WAP-7 electric locomotive hauls the Sealdah–Bamanhat Uttar Banga Express in West Bengal in April 2025. Kingshuk Mondal, CC BY 4.0, via Wikimedia Commons.
    1987–95

    The Golden Quadrilateral goes electric Trunk route

    Delhi–Bombay 1987Howrah–Bombay and Delhi–Chennai 19912 x 25 kV, 1994–95

    Trunk routes were commissioned one after another: Delhi–Bombay via Western Railway (1,388 route km) on 31 March 1987, Howrah–Bombay (1,976) on 31 January 1991, Delhi–Chennai (2,190) on 31 March 1991 and Delhi–Bombay via Central Railway (1,542) on 31 January 1992. In 1994–95 India commissioned its first 2 x 25 kV autotransformer system on the Bina–Katni and Katni–Bishrampur coal routes.

    Delhi–Howrah: the first electric trunk route Trunk route

    7 Jan 19771,445 route kmEastern and Northern Railways

    The Delhi–Howrah route, the busiest corridor linking the capital to Kolkata and the eastern coalfields, was commissioned with electric traction end to end. It set the pattern for the next 30 years: electrify the densest trunk and freight routes first, where locomotives work hardest.

    1966–68

    Kolkata’s 3,000 V DC converted to AC 25 kV AC

    Eastern and South Eastern Railways

    The Howrah–Burdwan and Sheoraphulli–Tarakeswar lines, electrified on 3,000 V DC in 1954–58, were converted to 25 kV AC in 1966 and 1968. With that, every system outside Bombay and Madras was on the single national standard.

    ‘Lokmanya’: the first Indian-built electric locomotive Locomotives

    14 Oct 1961Chittaranjan1,500 V DC, for Bombay

    Jawaharlal Nehru inaugurated Lokmanya, the first 1,500 V DC electric locomotive built at Chittaranjan, for the Bombay area. India introduced its first indigenous electric multiple units in September 1962. Domestic manufacture would later make the mass electrification of the 2010s possible without large-scale imports.

    First 25 kV AC section energised 25 kV AC

    11 Aug 1960Rajkharswan–Dongoaposi75 route km, South Eastern Railway

    Three years after choosing AC, India energised its first 25 kV section on an iron-ore route in the eastern mineral belt. Heavy mineral trains running all day were exactly the traffic that repaid the cost of wires and substations. A dedicated electrification project, later the Central Organisation for Railway Electrification (CORE), took charge of new schemes.

    A 132/25 kV traction substation at Vizianagaram
    A 132/25 kV traction substation at Vizianagaram, Andhra Pradesh: grid power is stepped down here and fed to the overhead line. Saiphani02, CC BY 4.0, via Wikimedia Commons.

    India adopts 25 kV AC 25 kV AC

    With French National Railways (SNCF)14 Dec 1957: Howrah EMUs on 3,000 V DC

    In 1955 SNCF had shown that 25 kV single-phase AC at the 50 Hz grid frequency needed far fewer substations than DC. Indian Railways adopted it in 1957, initially with SNCF as consultants. The decision came just as Kolkata’s 3,000 V DC lines opened: Nehru inaugurated Howrah–Sheoraphulli EMU services on 14 December 1957.

    Why it matters: one national standard, chosen early, is what let India later wire tens of thousands of kilometres with the same design.

    388 route km at Independence DC era

    Bombay and Madras onlyAll 1,500 V DC

    After two decades, India had just 388 route km electrified, around Bombay and Madras. Steam hauled almost everything else, and diesel had not yet arrived.

    1928–31

    Electric traction spreads from the Harbour line DC era

    Colaba–Borivali 5 Jan 1928Kalyan–Poona 1930Madras Beach–Tambaram 15 Nov 1931

    The Bombay, Baroda and Central India Railway electrified its suburban line from Colaba to Borivali in January 1928. In 1930 the GIPR opened electric working on the Kalyan–Poona main line over the steep Bhor Ghat, where electric locomotives could haul heavier loads uphill than steam. Madras followed on 15 November 1931 with Beach–Tambaram on metre gauge.

    India’s first electric train DC era

    3 Feb 1925Bombay VT–Kurla, Harbour branch16 route km, 1,500 V DC

    The Great Indian Peninsula Railway ran India’s first electric train from Bombay Victoria Terminus to Kurla on the Harbour branch, inaugurated by the Governor of Bombay, Sir Leslie Wilson. It used 1,500 V DC from overhead wires and British-built motor coaches. Frequent, crowded suburban trains that started and stopped every few minutes were the ideal first use.

    Why it matters: every one of today’s 70,000-plus electrified route km traces back to this 16-km line.

    A Great Indian Peninsula Railway steel motor coach for electric service
    A Great Indian Peninsula Railway steel motor coach for electric service, built by Cammell Laird, the type used on Bombay’s first electric suburban trains from 1925. Government of India (Railway Department), CC BY-SA 4.0, via Wikimedia Commons.
    Advertisement

    When Each Trunk Route Went Electric

    Commissioning dates from the Central Organisation for Railway Electrification. Swipe sideways on mobile.

    Electrified trunk routeCommissionedRoute km
    Delhi–Howrah7 Jan 19771,445
    Delhi–Bombay (via Western Railway)31 Mar 19871,388
    Howrah–Bombay31 Jan 19911,976
    Delhi–Chennai31 Mar 19912,190
    Delhi–Bombay (via Central Railway)31 Jan 19921,542
    Howrah–Delhi (via Patna)3 Feb 2002534 (final section)
    Howrah–Chennai (Kharagpur–Waltair link)29 Nov 20051,117 (final section)

    The Locomotives That Made It Work

    Electrification without domestic locomotive production would have meant decades of imports.

    ClassRoleIntroducedPowerWhere built
    Lokmanya (WCM-5)Mixed, Bombay DC19611,500 V DCChittaranjan
    WAP-4Passenger1993–94about 5,350 HPChittaranjan
    WAP-5Fast passenger1995about 5,450 HPABB import, later Chittaranjan
    WAG-9Heavy freight1996about 6,120 HPABB import, then Chittaranjan, Banaras, Patiala
    WAP-7Passenger2000about 6,350 HPChittaranjan, Banaras, Patiala
    WAG-12BHeavy freight2018 (in service 2020)12,000 HPAlstom joint venture, Madhepura
    9,000 HP (Siemens)Heavy freight20259,000 HPDahod, Gujarat

    The quiet enabler of mission-mode electrification was manufacturing. Chittaranjan Locomotive Works built a record 603 electric locomotives in 2025–26, and the former Diesel Locomotive Works at Varanasi, renamed Banaras Locomotive Works in 2020, built 572 locomotives, mostly WAG-9 and WAP-7 electrics. Two foreign partnerships added heavy freight power: Alstom at Madhepura (WAG-12B) and Siemens at Dahod (9,000 HP).

    Diesel vs Electric Traction

    Why the railways wanted the switch, and what it does not change.

    Diesel vs Electric on Indian Railways

    Diesel
    Power plant on board
    FuelRefined, moved, stored, burned
    vs
    Electric
    Power from the grid
    ~70%Cheaper to run, per the ministry
    Mostly imported crudeEnergy sourceDomestic grid, increasingly renewable
    At the locomotiveEmissionsAt power plants; falls as grid cleans
    NoneRegenerative brakingFeeds power back to the wire
    Runs anywhereFlexibilityNeeds wires and substations
    LowUp-front infrastructureHigh: masts, wire, substations
    Lower per unitPower for heavy freightUp to 12,000 HP per locomotive

    The headline comparison that often appears beside electrification, 11.5 g of CO₂ per tonne-km by rail against 101 g by road (NITI Aayog, 2021), is about rail versus road, not electric versus diesel trains. Electrification’s own climate benefit depends on the grid. India’s power is still mostly from coal, so an electric train today shifts emissions more than it removes them; as solar and wind grow, the same wires carry progressively cleaner power without any change to the trains.

    The Last 269 km

    Where the remaining broad gauge is, and how fast it is shrinking.

    StateLeft, Nov 2025Left, May 2026Share done, Nov 2025
    Karnataka151 route km120 route km96%
    Tamil Nadu1176897%
    Assam1975592%
    Goa161691%
    Rajasthan931099%
    Total57426999.2% (all India)

    In six months the unelectrified balance more than halved, from 574 to 269 route km. Assam made the biggest gain. Goa’s 16 km did not move at all between the two counts. The ministry’s general explanation for the final stretches is forest and statutory clearances, utility shifting, difficult terrain and short working seasons. Note that these figures cover broad gauge only. Heritage metre-gauge and narrow-gauge lines such as the Nilgiri, Darjeeling and Kalka–Shimla railways are outside the 100% target.

    Corrections and Clarifications

    Claims in the material this page was built from, and in common coverage.

    Wrong decade

    “1980s: 25 kV AC becomes India’s standard”

    India adopted 25 kV AC in 1957 and energised its first AC section on 11 August 1960. The 1980s were when the big trunk routes were completed on that standard.

    Timing

    “2014: the acceleration begins”

    Output roughly doubled from 2014, but the step change was 2017–18, when annual electrification jumped to 4,087 route km from roughly 1,400.

    Premature

    “About 99% by March 2025”

    The ministry put the share at more than 96% at the end of 2024 and reported 99.2% for November 2025. 99.6% came in March 2026.

    Misattributed

    “Vadodara’s WAP-7 era”

    The WAP-7 has been built at Chittaranjan since 2000, and later at Banaras and Patiala. Vadodara is one of the sheds where WAP-7s are based. Gujarat’s locomotive factory is at Dahod, and it builds 9,000 HP freight engines.

    Narrower than stated

    “WAG-12B is a Dedicated Freight Corridor locomotive”

    It was bought for heavy freight generally and mostly works the regular network, such as the Samalkot freight shown above, as well as feeder routes to the corridors.

    Omitted

    The missed targets and the DC systems

    The material left out the 388 km at Independence, Kolkata’s 3,000 V DC lines, Mumbai’s DC-to-AC switch (2012–16), 2 x 25 kV, and that the 2021–22 and December 2023 deadlines were both missed.

    What to Watch Next

    2026–27

    Declaring 100%

    Whether the last 269 km, led by Karnataka’s 120 km and Goa’s unchanged 16 km, are finished and the ministry formally declares broad gauge fully electric.

    Energy

    Round-the-clock renewables

    The 1,500 MW solar, wind and storage package in the pipeline, and how much traction power actually comes from renewables, the real test of the 2030 net-zero goal.

    Capacity

    Beyond the wires

    Kavach train protection on 24,400 more km, automatic signalling and new freight corridors. Electrification is the foundation, not the capacity fix.

    Fleet

    Diesel’s last role

    How many diesel locomotives stay on standby, shunting and border duty once the network is fully wired, and the RDSO hydrogen-train pilot.

    Did You Know?

    • Ghats before cities: the 1930 Kalyan–Poona electrification was driven by the Bhor Ghat incline, where electric locomotives outclimbed steam.
    • Metre-gauge first in Madras: the 1931 Beach–Tambaram line was electrified on metre gauge, not broad gauge.
    • Nehru at both ends: he inaugurated Kolkata’s first EMUs in 1957 and the first Indian-built electric locomotive, Lokmanya, in 1961.
    • Record wire height: a 7.45-metre contact wire was trialled in 2008 so double-stack container trains could run under it.
    • Solar growth: railway solar capacity rose from 3.68 MW in 2014 to 898 MW by November 2025, per the ministry.
    • Global context: the UIC’s June 2025 figures put the UK at 39% electrified, France at 60% and China at 82%.

    Quick Quiz

    1. Where did India’s first electric train run in 1925?
    A. Howrah–Burdwan · B. Bombay VT–Kurla · C. Madras Beach–Tambaram · D. Delhi–Ghaziabad
    B. Bombay VT to Kurla, on the Harbour branch, on 3 February 1925.
    2. In which year did India adopt 25 kV AC as its standard?
    A. 1925 · B. 1947 · C. 1957 · D. 1987
    C. 1957. The first 25 kV section opened in 1960.
    3. How many route km were electrified at Independence?
    A. 16 · B. 388 · C. 3,880 · D. 21,801
    B. 388 route km. (21,801 was the total before 2014.)
    4. What was the record annual electrification?
    A. 4,087 km · B. 6,015 km · C. 7,188 km · D. 12,000 km
    C. 7,188 route km, in 2023–24.
    5. How much broad gauge was left to electrify in May 2026?
    A. 0 km · B. 269 km · C. 2,701 km · D. 13,675 km
    B. 269 route km, in five states.

    Explore More Timelines

    People Also Ask

    Who started electric trains in India?
    The Great Indian Peninsula Railway, a British-era company, on 3 February 1925 in Bombay. The Government of India took the railway over in the same year.
    What voltage do Indian trains use?
    25,000 volts AC, 50 Hz, on almost all lines. Bombay began on 1,500 V DC and Kolkata on 3,000 V DC; both converted. Metros use 25 kV AC or 750 V DC third rail.
    Which state has the least railway electrification?
    As of May 2026 Assam, Karnataka, Tamil Nadu, Goa and Rajasthan were the only states below 100%. Goa had the lowest share in late 2025, at 91%.
    How long did it take to electrify Indian Railways?
    About a century: from 16 route km in 1925 to 99.6% of broad gauge in 2026. More than two-thirds of the network was wired after 2014.
    What is the most powerful locomotive in India?
    The 12,000 horsepower WAG-12B electric freight locomotive, built by Alstom at Madhepura, Bihar.

    Frequently Asked Questions

    When did railway electrification start in India?
    On 3 February 1925, when the Great Indian Peninsula Railway ran India’s first electric train between Bombay Victoria Terminus and Kurla on the Harbour branch, a 16-route-km line using 1,500 V DC. Electrification spread to Bombay’s western suburbs in 1928, the Kalyan–Poona main line in 1930 and Madras in 1931.
    How much of Indian Railways is electrified in 2026?
    As of 31 May 2026, 70,002 of 70,271 route kilometres of broad-gauge line, or 99.6%, were electrified, according to the Ministry of Railways. Only 269 route km remained, in Karnataka, Tamil Nadu, Assam, Goa and Rajasthan. Twenty-five states and Union Territories are fully electrified.
    Is Indian Railways 100% electrified?
    Not yet. The broad-gauge network stood at 99.6% in mid-2026, with 269 route km left. The ministry had earlier targeted full electrification by 2021–22 and then December 2023. The figure also refers only to broad gauge; metre-gauge and narrow-gauge heritage lines, including the hill railways, are mostly not electrified.
    Which was the first electric train in India?
    An electric multiple unit of the Great Indian Peninsula Railway that ran from Bombay VT to Kurla on 3 February 1925, inaugurated by the Governor of Bombay, Sir Leslie Wilson. Its motor coaches were built in Britain by Cammell Laird and ran on 1,500 V DC from overhead wires.
    Why did India choose 25 kV AC?
    In 1955 French National Railways demonstrated that single-phase 25 kV AC at the standard 50 Hz grid frequency could be fed straight from the public grid with fewer substations than low-voltage DC, making long-distance electrification cheaper. Indian Railways adopted it in 1957, with SNCF as initial consultants.
    Where was India’s first 25 kV AC line?
    The 75-route-km Rajkharswan–Dongoaposi section of the South Eastern Railway, energised on 11 August 1960. It was an iron-ore route in present-day Jharkhand and Odisha, chosen because heavy mineral traffic gave the best return on electric traction.
    How many kilometres were electrified at Independence?
    388 route kilometres, all on 1,500 V DC, around Bombay and Madras, according to the Central Organisation for Railway Electrification. That was barely 1% of the network; steam hauled almost everything else.
    When was the Delhi–Howrah line electrified?
    The electrified Delhi–Howrah trunk route, 1,445 route km, was commissioned on 7 January 1977. It was the first of the Golden Quadrilateral and diagonal trunk routes to be wired end to end. Delhi–Bombay via the Western Railway followed in 1987.
    When were all the main trunk routes electrified?
    Delhi–Howrah in January 1977, Delhi–Bombay via Western Railway in March 1987, Howrah–Bombay in January 1991, Delhi–Chennai in March 1991 and Delhi–Bombay via Central Railway in January 1992. The Howrah–Chennai route was completed in November 2005, when the Kharagpur–Waltair gap was closed.
    How fast is Indian Railways electrifying lines now?
    Electrification peaked at a record 7,188 route km in 2023–24, up from 6,565 km in 2022–23 and 6,366 km in 2021–22. It fell to 2,701 km in 2024–25 because little network was left. The ministry says the pace averaged 1.42 km a day in 2004–14 and more than 15 km a day in 2019–25.
    How much was electrified before and after 2014?
    21,801 route km were electrified in about 60 years before 2014, and 46,900 route km between 2014 and 2025, according to a ministry reply in Parliament in December 2025. The sharp jump came from 2017–18, when annual electrification rose to 4,087 route km.
    What is Mission 100% Electrification?
    The government’s programme to electrify the entire broad-gauge network. In September 2018 the Cabinet approved electrifying the remaining 13,675 route km for about ₹12,134 crore, with a 2021–22 deadline. All new lines and doubling projects are now sanctioned with electrification built in.
    Which states are not fully electrified yet?
    As of May 2026, five: Karnataka (120 route km left), Tamil Nadu (68), Assam (55), Goa (16) and Rajasthan (10). In November 2025 the same five states had 574 route km left. The ministry blames forest clearances, utility shifting, terrain and short working seasons for the delays.
    When did Mumbai stop using DC traction?
    Mumbai’s 1,500 V DC system was converted to 25 kV AC in stages: Western Railway finished on 5 February 2012, Central Railway’s main line on 8 June 2015, and the Harbour line in 2016. The conversion allowed longer, more powerful trains and ended India’s last large DC railway system.
    Did Kolkata use a different system?
    Yes. The Howrah–Burdwan electrification of 1954–58 used 3,000 V DC, and Jawaharlal Nehru inaugurated EMU services to Sheoraphulli on 14 December 1957. Those sections were converted to 25 kV AC in 1966 and 1968, once India had standardised on AC.
    What is 2 x 25 kV electrification?
    An autotransformer system that feeds 50 kV between the contact wire and a separate feeder wire, while trains still draw 25 kV. It allows longer gaps between substations and higher power for heavy trains. India first used it on the Bina–Katni and Katni–Bishrampur coal routes in 1994–95, and it is standard on the dedicated freight corridors.
    What is the WAG-12B?
    A 12,000 horsepower, two-section electric freight locomotive built by Alstom with Indian Railways at Madhepura in Bihar under an order for 800 locomotives. It can haul about 6,000 tonnes at up to 120 km/h. It made its first commercial run on 18 May 2020, and Alstom delivered the 500th in March 2025.
    What is the 9,000 HP locomotive made at Dahod?
    A Siemens-designed electric freight locomotive assembled at the Indian Railways plant at Dahod, Gujarat, which Prime Minister Modi dedicated on 26 May 2025. The contract covers 1,200 locomotives, each able to haul about 5,800 tonnes at up to 120 km/h, with most components made in India.
    Which is India’s most common electric passenger locomotive?
    The WAP-7, a 6,350 horsepower three-phase locomotive first built at Chittaranjan Locomotive Works in 2000, which now hauls most express trains. Banaras Locomotive Works built 143 WAP-7s in 2025–26 alone, alongside 401 WAG-9 freight locomotives.
    Does electrification make Indian Railways carbon-free?
    No. Electric trains burn no fuel on board, but India’s grid still relies heavily on coal, so emissions move to power stations. The benefit grows as the grid gets cleaner. Indian Railways aims to be a net-zero carbon emitter by 2030 and had commissioned 812 MW of solar and 93 MW of wind for traction by December 2025.
    Is electric traction cheaper than diesel?
    The ministry says electric traction is about 70% more economical than diesel. The exact saving depends on electricity tariffs, how intensively locomotives are used and the cost of the wires. Indian Railways spent ₹29,614 crore on traction energy of all kinds in 2023–24.
    How does India compare with other countries?
    According to the International Union of Railways (UIC) report of June 2025, quoted by the ministry, Switzerland is 100% electrified, China 82%, Spain 67%, Japan 64%, France 60%, Russia 52% and the United Kingdom 39%. India’s broad gauge, at over 99%, is among the most electrified large networks.
    Are diesel locomotives still used in India?
    Yes, in smaller numbers. They work unelectrified sections, shunting, some freight and emergency standby, and Banaras Locomotive Works (formerly Diesel Locomotive Works) still builds a few. Steam survives only on heritage mountain railways and special charters, the ministry says.
    Does electrification solve congestion on Indian Railways?
    No. Wires replace diesel but do not add track. Congestion depends on line capacity, signalling, terminals and freight sidings. That is why electrification is paired with dedicated freight corridors, automatic signalling and the Kavach train-protection system, which covered more than 3,100 route km by early 2026.

    The Bottom Line

    India did not electrify its railways in one project. For 90 years it wired the places where electric traction paid for itself fastest: Bombay’s suburbs, the ghats, the coal and iron-ore belt and the trunk routes between the metros. Then, from 2017, it decided the whole broad-gauge network should be electric, and wired more track in a decade than in the previous nine.

    The result is a railway that is now physically part of India’s power system. That makes the next questions less about wires and more about what flows through them: how clean the electricity becomes, and whether signalling, freight corridors and safety systems can make full use of a network that is, after a century, almost entirely electric.

    Related AiTimeline Stories

    ⚠️ Editorial Note

    Last updated 6 October 2026. Historical milestones and trunk-route dates are from the Central Organisation for Railway Electrification. Electrification totals, annual figures and state balances are from Ministry of Railways releases and parliamentary replies (April 2021, December 2025, January and April 2026, and data to 31 May 2026). Percentages for different years use the network size published at the time, which has grown as new lines open. Locomotive horsepower figures are approximate nominal ratings.

    Advertisement
    Pulwama Attack Anniversary: How India’s Security Doctrine Changed, From Balakot to PRAHAAR Tariff Walls and Trade Bridges: The Hidden Forces Reshaping Global Trade
    →
    Next Article