17 Days Underground: How India Rescued 41 Workers from Silkyara Tunnel

📅 Last updated: 7 November 2026📖 22 dated entries, 2018 to 2026✎ By Nazish Fatima

View as Web Story

In short

Silkyara tunnel collapse timeline: 41 workers trapped on 12 November 2023, the auger failures, the rat-hole miners' breakthrough and rescue on 28 November.

Latest Story

At about 5:30 on the morning of Diwali, 12 November 2023, part of an unfinished road tunnel in Uttarakhand fell in and sealed 41 workers behind a wall of rock and steel. The Silkyara tunnel collapse set off one of India’s most closely watched rescues. A powerful auger drilled most of the way through and then broke; vertical shafts and side tunnels were started in parallel; and in the end a team of 12 rat-hole miners dug the last metres by hand. All 41 men came out alive on the evening of 28 November. The questions about how the tunnel was planned and built have lasted much longer.

💡 Short Answer

The Silkyara tunnel in Uttarkashi collapsed at about 5:30 am on 12 November 2023, trapping 41 workers. After an auger machine drilled about 47 metres and broke, rat-hole miners dug the final stretch by hand, and all 41 were rescued on 28 November 2023. A government panel later blamed lapses by NHIDCL, the contractor and the supervising engineer. The tunnel’s two ends met on 16 April 2025.

⚡ The Rescue at a Glance
Collapse~5:30 am, 12 Nov 2023
Workers trapped41 (first counted as 40)
RescuedAll 41, evening of 28 Nov 2023
Rescue pipe800 mm steel, ~57 m long
Final stretchDug by hand by 12 rat-hole miners
Tunnel4.531 km, NH-134, Char Dham project
⚡ Quick Answers — AI Overview Ready

Silkyara Tunnel Collapse: Key Questions

What happened at Silkyara?
On 12 November 2023 a section of the under-construction Silkyara bend-Barkot road tunnel in Uttarkashi collapsed about 200 metres from its entrance, trapping 41 workers in the finished stretch behind it. They were kept alive through pipes for 17 days and all were rescued on 28 November.
How were the workers rescued?
Rescuers pushed an 800 mm steel pipe through the debris with an auger. When the auger broke at about 47 metres, 12 rat-hole miners dug the rest by hand inside the pipe. NDRF teams then pulled the men out one by one on wheeled stretchers.
Why did it take 17 days?
The rubble contained steel girders, pipes and fallen supports that repeatedly stopped the auger, and fresh collapses made the area unstable. Vertical shafts and a side tunnel were started as backups, but each needed days of road-building and drilling.
Who was responsible?
No court has ruled. The government issued show-cause notices to the contractor, Navayuga Engineering, and the supervising consultant. An expert panel’s final report, as reported in October 2024, found lapses by NHIDCL, the contractor and the authority engineer.
📚 Key Takeaways

The Rescue in Ten Points

  • The collapse: about 5:30 am on 12 November 2023, Diwali morning.
  • The trapped: 41 workers from eight states, in a 2 km finished stretch.
  • The first lifeline: a 4-inch pipe carrying air, water and dry food.
  • The first setback: the auger stopped at 22 metres on 17 November.
  • The new strategy: five rescue plans run in parallel from 18 November.
  • The second lifeline: a 6-inch pipe with hot food and a camera, 20-21 November.
  • The breakdown: the auger broke on 25 November after about 47 metres.
  • The breakthrough: rat-hole miners dug the last metres by hand, 27-28 November.
  • The blame: an expert panel found lapses by NHIDCL, the contractor and the supervisor.
  • The tunnel: its two ends met on 16 April 2025; it was still being finished in 2026.

Timeline: From the Contract to the Tunnel’s Breakthrough

Newest first. Colour shows which phase each event belongs to.

AftermathBreakthroughSetbacksLifelineCollapse
16 Jul 2026

A worker is killed inside the same tunnel Aftermath 2023-2026

About 900 m in from the Barkot sideThe Wire, 17 July 2026

What happened: At about 2 am a block of the tunnel’s concrete lining collapsed and fell on a 21-year-old worker from Jharkhand. He was taken to hospital in Naugaon and died during treatment.

The response: The Uttarkashi district magistrate asked the Barkot sub-divisional magistrate to find the cause and check whether the executing agency had followed safety standards, and to begin compensation for the family. NHIDCL ordered its own detailed investigation.

More than two years after the rescue, the tunnel was still under construction.
16 Apr 2025

Breakthrough: the two ends of the tunnel meet Aftermath 2023-2026

Silkyara bend-Barkot tunnel, NH-134Chief Minister Pushkar Singh Dhami present

The milestone: Excavation from the Silkyara and Barkot ends was joined, completing the bore of the 4.531 km two-lane tunnel. Road Transport Minister Nitin Gadkari called it a historic achievement that would save about an hour of travel and give all-weather access to Yamunotri and Gangotri.

The temple: Dhami attended the consecration of a temple to the local deity Baba Baukhnag at the tunnel mouth, credited the 2023 rescue to the deity’s blessings and said the tunnel would be renamed after it.

Still to do: A breakthrough is not an opening. Roadwork, lining and electrical and mechanical systems remained to be finished.

The breakthrough came 17 months after the 41 workers were brought out.
28 Nov 2024

A national workshop on the first anniversary Aftermath 2023-2026

National Institute of Disaster Management (NIDM)Proceedings published in 2025

The event: On the first anniversary of the rescue, NIDM held a national workshop and brainstorming session titled “Lessons Learnt from Silkyara Tunnel and other Tunnel Disasters” with disaster managers, tunnel engineers and officials.

The themes: Discussions covered geological investigation, monitoring during construction, emergency access, rescue preparedness and tunnel resilience.

The workshop was held in 2024; the proceedings carry a 2025 publication date.

The expert committee’s final report: “profound” negligence Aftermath 2023-2026

Five-member panel headed by R.K. Dhiman, ADG, Border Roads OrganisationReported by ThePrint, 12 October 2024

The finding: According to ThePrint, the report, submitted to the road ministry on 20 September, said NHIDCL, the contractor Navayuga Engineering Company and the authority engineer had all overlooked their responsibilities, and called the negligence “profound”.

The lapses: It reportedly found that bid parameters were fixed without a geotechnical investigation, that rock was classed as better than it was, that the tunnel had seen 21 collapses in four years, and that the 2020 design had no separate dedicated escape passage.

The recommendations: Officials responsible should be identified and penal action taken, and the delay should not be treated as force majeure, with costs borne by the contractor.

These are the findings of a government panel as reported, not a court verdict.
8 Aug 2024

Government says the contract provides for an escape passage Aftermath 2023-2026

Written reply, ParliamentMinister Nitin Gadkari

The statement: The road ministry said NHIDCL had included a provision for an escape passage in the contract for the Silkyara bend-Barkot tunnel.

The design: The government had told Parliament in December 2023 that the single-tube tunnel is split by a partition wall into two corridors, each meant to serve as an escape route for the other, with cross openings at intervals.

The expert panel later said the design had no separate dedicated escape passage.
25 Jul 2024

Show-cause notices, and compensation explained Aftermath 2023-2026

Lok Sabha, unstarred question 587Written reply by Nitin Gadkari

The probe: The ministry said the expert committee had submitted a preliminary report on 22 December 2023, that show-cause notices had been issued to the contractor and to the consultant supervising construction, and that final action would follow the committee’s recommendations.

The money: PTI reported the reply as saying each trapped worker was paid Rs 2 lakh plus bonus and salary by the contractor. The Uttarakhand government paid Rs 1 lakh to each worker separately.

The Rs 2 lakh came from the contractor, not from the government.
28 Feb 2024

A rescuer’s house is demolished in Delhi Aftermath 2023-2026

Khajoori Khas, DelhiDelhi Development Authority

What happened: The DDA demolished the home of Vakil Hasan, who had led the team of rat-hole miners, in an anti-encroachment drive. Hasan said he had asked for a house as his only reward.

The DDA’s account: The authority said the land was government land and that Hasan had refused the relief it offered, demanding a permanent house at or near the same spot.

The demolition came three months after the rescue made the miners national heroes.

Rewards, compensation and a preliminary report Aftermath 2023-2026

Uttarakhand government; Rajya Sabha; road ministry20 to 22 December 2023

In Parliament: On 20 December the government told the Rajya Sabha that the executing agency had paid each worker Rs 2 lakh plus a month of paid leave, and that Uttarakhand had given Rs 1 lakh each.

The miners: On 21 December Chief Minister Dhami gave each of the 12 rat-hole miners a cheque for Rs 50,000. They accepted them but said they would not cash them, calling the amount inadequate and asking for jobs or homes.

The probe: On 22 December the expert committee submitted its preliminary report to the road ministry.

The contractor’s payment was described as one month’s paid leave in December 2023 and as two months’ bonus and salary in July 2024.
29 Nov 2023

Airlifted to AIIMS Rishikesh Breakthrough 27-29 Nov

Indian Air Force CH-47 ChinookFrom Chinyalisaur

The flight: After a night at the community health centre in Chinyalisaur, the 41 workers were flown to AIIMS Rishikesh for checks.

The result: After examination, 40 of them were declared fit to go home.

The men had spent about 400 hours behind the debris.
28 Nov 2023

All 41 workers come out alive Breakthrough 27-29 Nov

Silkyara portalOperation Zindagi ends

The breakthrough: Rat-hole miners cleared the last of the debris inside the 800 mm steel pipe and it was pushed through to the trapped section in the evening. The pipe ran for about 57 metres through the rubble.

The evacuation: NDRF teams brought the men out one at a time on wheeled stretchers. The first emerged at about 8 pm, and by about 8:50 pm the Uttarakhand government confirmed all 41 were out. Forty-one ambulances waited at the portal.

At the site: Chief Minister Pushkar Singh Dhami and Minister of State for Road Transport V.K. Singh greeted the workers.

Twelve men with hand tools finished what a heavy auger could not.
27 Nov 2023

The rat-hole miners go in Breakthrough 27-29 Nov

Inside the 800 mm rescue pipeTeam led by Vakil Hasan

Clearing the pipe: By the evening, welders had cut out the broken auger and a damaged section of pipe, and a lump of shotcrete was broken up. The decision was taken to dig the rest by hand.

The method: A team of 12 manual excavators, skilled in the rat-hole technique used in small coal mines, crawled into the pipe in shifts, dug with hammers, chisels and shovels and passed out debris on a trolley.

In parallel: SJVN’s vertical shaft had reached about 32 metres and THDC’s rescue drift from the Barkot end about 12 metres.

Officials stressed the men were experts in the technique; rat-hole coal mining itself was banned by the National Green Tribunal in 2014.
26 Nov 2023

Vertical drilling begins from the hilltop Setbacks 22-26 Nov

Satluj Jal Vidyut Nigam (SJVN)Drilling started at 12:05 pm

The shaft: SJVN began a 1-metre-wide vertical shaft from above the trapped section, which needed to go down about 86 metres. RVNL had already started a narrower 8-inch vertical bore for supplies.

The auger: A DRDO team flew in from Hyderabad with a plasma cutter to free the stuck auger, though gas cutting proved quicker on site.

The roads to the hilltop had been cut by the Border Roads Organisation in days.
25 Nov 2023

The auger breaks and is stuck in the pipe Setbacks 22-26 Nov

Silkyara endAbout 47 metres of pipe inserted

The failure: While the auger was being pulled back, a joint broke after 15 metres had come out, leaving about 32 metres of auger and blades jammed inside the rescue pipe.

The verdict: International tunnelling expert Arnold Dix told reporters the machine was “busted” and that manual digging and vertical drilling were now the options.

The pipe was by then roughly 9 to 12 metres short of the trapped men.
24 Nov 2023

Another obstruction at 46.9 metres Setbacks 22-26 Nov

Silkyara endGround-penetrating radar used

The work: The auger was withdrawn, a radar scan checked for more metal in the path, and welders cut away bent steel. The tenth pipe section was pushed in, taking the total to 46.9 metres.

The halt: Pipe-pushing stopped again at another obstruction.

Hopes of a rescue that night, raised on 22 November, faded.
22-23 Nov 2023

Steel girders in the debris Setbacks 22-26 Nov

Silkyara end800 mm pipes

Progress: The narrower 800 mm pipe had gone in without trouble from 22 to 44.1 metres.

The obstacle: The ninth pipe hit a lattice girder rib from the tunnel’s support system. NDRF and SDRF crews cut it with gas cutters by the afternoon of 23 November, and the auger platform needed repairs.

Officials said the pipe was about three-quarters of the way through.
20-21 Nov 2023

A 6-inch lifeline, hot food and the first video Lifeline 13-21 Nov

Silkyara end150 mm steel pipe

The pipe: On the third attempt, a 150 mm (6-inch) pipe was pushed through about 57 metres of debris. The case study by the Uttarakhand Academy of Administration dates its completion to 21 November; news reports say it went through on 20 November.

Food: Hot khichdi was sent in bottles for the first time, then dal, rice, roti, vegetables, fruit and medicines.

Sight: Early on 21 November an endoscopic camera pushed through the pipe sent out the first video of the men, all alive.

Until then the men had lived on dry fruit and puffed rice sent through a 4-inch pipe.
19-20 Nov 2023

Roads up the mountain Lifeline 13-21 Nov

Border Roads Organisation; ONGCBarkot and Silkyara ends

Roads: On 19 November the BRO built a 1.15 km road to the hillock above the tunnel for vertical drilling rigs.

ONGC: On 20 November an ONGC team visited the Barkot end to prepare a 24-inch vertical bore. Its approach road was still being built when the rescue ended.

The BRO had about 1,050 metres of a planned 5 km road done by 28 November.
18 Nov 2023

Five plans at once Lifeline 13-21 Nov

High-level meeting at the sitePMO, road ministry, state officials

The decision: After the auger halt, a meeting led by former PMO adviser Bhaskar Khulbe agreed to pursue several routes in parallel: horizontal drilling from Silkyara, vertical drilling from above by SJVN and RVNL, vertical drilling from the Barkot side by ONGC, and a rescue tunnel from the Barkot end by THDC.

The lifeline: Work also began on a second, 6-inch supply pipe.

The strategy changed from one plan to many, so that one failure would not end the rescue.
17 Nov 2023

The auger stops at 22 metres Lifeline 13-21 Nov

Silkyara endAmerican auger airlifted from Delhi

The problem: While the fifth pipe section was being positioned, after 22 metres of 900 mm pipe had gone in, the machine began to lift and its bearings were damaged.

The alarm: During further drilling a loud cracking sound caused panic among workers and police, and pipe-pushing was halted.

The pipe size was later cut to 800 mm to reduce vibration.
13-16 Nov 2023

Clearing debris and bringing in machines Lifeline 13-21 Nov

Silkyara endOperation Zindagi

First moves: Excavators cleared debris and shotcrete was sprayed to hold the loose roof, but more material kept falling.

The plan: Engineers decided to push wide steel pipes through the rubble with an auger to make an escape tube. The first auger proved unsuitable and a more powerful machine was flown in from Delhi.

Australian tunnel experts Arnold Dix and Chris Cooper later joined the advisers.
12 Nov 2023

The tunnel collapses on Diwali morning Collapse and background

Silkyara end, Uttarkashi districtAbout 5:30 am

The collapse: During the night shift, a section between about 203 and 240 metres from the Silkyara portal fell in, trapping 41 workers in the completed, roughly 2 km stretch beyond it.

Contact: Rescuers reached the men through an existing 100 mm water line and a 4-inch compressor pipe, which carried air, water, oxygen and dry food.

The count: The first official count was 40, taken from the contractor’s register; it was later corrected to 41. The men came from eight states, with the largest number, 15, from Jharkhand.

The workers were alive and in contact from the first day, which shaped the whole rescue.

The contract, and early warnings about the rock Collapse and background

NHIDCL; Navayuga Engineering CompanyChar Dham all-weather road project

The contract: NHIDCL awarded the tunnel to Navayuga Engineering Company on 31 May 2018 on an EPC basis for Rs 853.79 crore, below the tender estimate, according to ThePrint.

The warnings: An early authority engineer flagged very poor, Class V rock in March 2019. The pre-construction geological report put 30 per cent of the alignment in poor or very poor rock, with exploratory drilling at only three locations.

The rock near the Silkyara end is mostly phyllite, a weak, clay-rich rock.

How the Rescue Worked: Five Routes at Once

From 18 November, every backup was pursued in parallel.

The rescue routes at Silkyara: horizontal pipe-pushing with an auger through about 57 metres of debris from the Silkyara portal, finished by rat-hole miners; a 1-metre vertical shaft by SJVN from the hill above, which reached about 32 of 86 metres; a narrow vertical bore and micro-tunnelling by RVNL; a 24-inch vertical bore prepared by ONGC from the Barkot side; and a rescue drift from the Barkot end by THDC, which reached about 12 metres
Only one route had to succeed; the others were insurance.

The first plan was simple: push wide steel pipes through the rubble with an auger and let the men crawl out. When the machine stopped at 22 metres on 17 November and a cracking sound sent people running, officials stopped relying on one method. A meeting on 18 November set out five routes. The horizontal pipe from Silkyara stayed the fastest bet. SJVN would drill a 1-metre shaft from the hilltop, RVNL a narrow supply bore and a horizontal approach, ONGC a 24-inch bore from the Barkot side, and THDC a rescue drift from the Barkot end. The BRO cut roads up the slope in days so that the rigs could reach their sites.

In the end the horizontal route won, but not by machine. After the auger broke on 25 November, welders spent two days cutting it out of the pipe, and on the night of 27 November a team of rat-hole miners crawled in with hand tools. They broke through on the evening of 28 November, while the vertical shaft was still about 50 metres short.

How the Trapped Workers Were Kept Alive

How the trapped Silkyara workers were kept alive: a 100 mm water line and a 4-inch compressor pipe from day one for air, water, oxygen and dry food; a 6-inch pipe pushed through about 57 metres on 20 to 21 November for hot meals, fruit, medicines and an endoscopic camera; walkie-talkies for contact; and doctors, ambulances and a temporary hospital waiting outside
The workers were in contact with rescuers from the first day.

The men were lucky in one respect: they were trapped in a completed, roughly 2 km stretch of tunnel with lighting and water. Rescuers made contact on the first day through an existing water line, and a 4-inch compressor pipe carried air, oxygen, dry fruit and puffed rice. The turning point was the 6-inch pipe pushed through on the third attempt, on 20-21 November. It carried bottles of hot khichdi, then dal, rice, roti, vegetables, fruit and medicines, as well as an endoscopic camera that sent out the first pictures of the men on 21 November. Doctors stayed on call at the portal, and 41 ambulances and a temporary hospital at Chinyalisaur waited for the end.

The Auger: Metre by Metre

How far the rescue pipe got, and what stopped it.

Progress of the Silkyara rescue pipe: 22 metres on 17 November when the auger lifted and was halted; 44.1 metres on 22 November before steel girders blocked it; 46.9 metres on 24 November before another obstruction; the auger broke on 25 November; about 57 metres reached by hand on 28 November
The last 10 metres took four days and twelve pairs of hands.
DatePipe insertedWhat happened
17 Nov22 m (900 mm pipe)Machine lifted, bearings damaged, cracking sound; halted
22 Nov44.1 m (800 mm pipe)Ninth pipe hit a lattice girder rib
23 Nov~46 mGirder cut; bent steel tangled in the auger
24 Nov46.9 mRadar scan, tenth pipe; halted again
25 Nov46.9 mAuger broke while being withdrawn; ~32 m jammed in the pipe
26-27 Nov46.9 mAuger cut out by gas cutters
28 Nov~57 mRat-hole miners break through; all 41 out

The Agencies and People Behind the Rescue

Agency or personRole
NDRFFinal evacuation through the pipe; cutting obstructions
SDRF and Uttarakhand PoliceRescue support, site security and coordination
NHIDCL and NavayugaProject authority and contractor; first response on site
Border Roads OrganisationAccess roads for the vertical drilling rigs
Indian ArmyEngineers and welders; frames for the rescue drift
Indian Air ForceAirlifted machinery; flew the workers to AIIMS Rishikesh
SJVN1-metre vertical shaft from the hilltop
RVNLNarrow vertical supply bore and horizontal micro-tunnelling
ONGC24-inch vertical bore from the Barkot side (prepared)
THDCRescue drift from the Barkot end
Arnold Dix and Chris CooperAustralian tunnelling experts advising on site
Rat-hole minersTwelve men led by Vakil Hasan dug the final stretch

Why Did the Silkyara Tunnel Collapse?

Expert assessments, not court findings.

Why the Silkyara tunnel collapsed, according to expert assessments: weak, fractured phyllite rock near the Silkyara portal; water seepage weakening the rock; geological investigation limited to three drilling points; rock reportedly classed as better than it was; 21 earlier collapses in four years reported by the expert panel; and no separate dedicated escape passage in the 2020 design
The panel’s findings are as reported; no court has ruled on liability.

The Uttarakhand Academy of Administration’s case study, written after a site visit in January 2024, points to a hidden patch of fractured or weak rock about 200 to 300 metres from the portal, water seepage weakening it, and problems that are hard to detect during construction. The rock there is mostly phyllite, a clay-rich, weak metamorphic rock. The pre-construction geological report classed about 30 per cent of the route as poor or very poor rock, and exploratory drilling was done at only three locations.

The government’s expert committee, headed by BRO additional director general R.K. Dhiman, went further. According to ThePrint’s account of its final report, it found that bid parameters were set without a geotechnical investigation, that rock-mass ratings were altered to keep sections in a less demanding class, that the tunnel had suffered 21 collapses in four years, and that the 2020 redesign left no separate escape passage. It recommended penal action against those responsible.

Often claimed

  • The government paid each worker Rs 3 lakh.
  • The collapse was an unforeseeable natural event.
  • The contractor has been punished.
  • The tunnel opened after the rescue.

What the record shows

  • Rs 1 lakh came from Uttarakhand; Rs 2 lakh came from the contractor.
  • Weak rock was flagged before construction, and the panel found lapses.
  • Show-cause notices were issued; no final penalty is on the public record.
  • The bore broke through in April 2025; work was still going on in 2026.

Compensation, Rewards and Notices

Money and action after the Silkyara rescue: Rs 2 lakh to each worker from the contractor plus paid leave or bonus and salary; Rs 1 lakh to each worker from the Uttarakhand government; Rs 50,000 cheques to each of the 12 rat-hole miners, which they declined to cash; show-cause notices to the contractor and supervising consultant by July 2024
The contractor, not the government, paid the larger share.
ItemAmount or actionSource
From the contractorRs 2 lakh per worker, plus one month’s paid leave (Dec 2023) or two months’ bonus and salary (Jul 2024)Parliament replies
From UttarakhandRs 1 lakh per workerRajya Sabha reply, Dec 2023
Rat-hole minersRs 50,000 each; cheques not cashedPTI, Dec 2023
Preliminary reportSubmitted 22 Dec 2023Lok Sabha reply, Jul 2024
Show-cause noticesContractor and supervising consultantLok Sabha reply, Jul 2024
Final reportSubmitted 20 Sep 2024; penal action recommendedThePrint, Oct 2024

What the Silkyara Rescue Taught India

The Silkyara arc: contract awarded May 2018; collapse 12 November 2023; auger halt at 22 metres 17 November; 6-inch lifeline 20 to 21 November; auger breaks 25 November; all 41 rescued 28 November; expert report September 2024; tunnel breakthrough 16 April 2025; fatal lining collapse 16 July 2026
A rescue that took 17 days, and a tunnel that took years longer.
Before

Know the ground

  • Drill more than three points.
  • Classify rock honestly.
  • Monitor movement daily.
Design

Build a way out

  • Dedicated escape passages.
  • Clear emergency access.
  • Alarms and ventilation.
Response

Many plans, clear roles

  • Run backups in parallel.
  • One command centre.
  • Value skilled hands.

The rescue showed what Indian agencies can do together under pressure, and the NIDM workshop on its first anniversary tried to turn that into lasting practice: better geological investigation, continuous monitoring, emergency access and agreed roles before a crisis rather than during it. The aftermath shows how much remains. A panel found that warnings about weak rock and repeated small collapses were not acted on, final accountability has not been publicly settled, and in July 2026 a worker was killed inside the same tunnel. The 41 men came out alive; the lesson is that they should never have needed rescuing.

Explore More Timelines

People Also Ask

How long were the Silkyara workers trapped?
From about 5:30 am on 12 November 2023 to the evening of 28 November 2023. That is usually described as 17 days because it spans 17 calendar dates; the elapsed time was just under 16 and a half days, so some official accounts say 16 days.
Who rescued the workers from the Silkyara tunnel?
Many agencies together: the NDRF, SDRF, Uttarakhand Police, the Army, the Border Roads Organisation, NHIDCL, SJVN, RVNL, ONGC and THDC, advised by experts including Arnold Dix. The final stretch of debris was dug by hand by a team of 12 rat-hole miners led by Vakil Hasan.
Why did the Silkyara tunnel collapse?
A section about 203 to 240 metres from the Silkyara portal fell in, in weak, fractured phyllite rock with water seepage. A government expert panel's final report, as reported by ThePrint in October 2024, blamed lapses by NHIDCL, the contractor and the supervising engineer, including inadequate geological investigation.
Is the Silkyara tunnel complete?
Not as of the latest reports. The two ends of the bore met on 16 April 2025, but lining, roadwork and systems were still being built, and a worker was killed by a falling lining block inside the tunnel on 16 July 2026.

Frequently Asked Questions

Dated facts from official records and contemporary reports, 2018 to 2026.

What is the Silkyara tunnel?
The Silkyara bend-Barkot tunnel is a 4.531 km two-lane road tunnel on NH-134 in Uttarkashi district, Uttarakhand, built by NHIDCL as part of the Char Dham all-weather road project. It is meant to cut about an hour off the journey to Yamunotri.
When did the Silkyara tunnel collapse?
At about 5:30 am on 12 November 2023, which was Diwali, during the night shift. A section between about 203 and 240 metres from the Silkyara portal collapsed.
How many workers were trapped in the Silkyara tunnel?
Forty-one. The first official count was 40, based on the contractor's entry register, and was corrected to 41. All 41 were rescued alive on 28 November 2023.
Where were the trapped workers from?
They came from eight states. Reported figures were 15 from Jharkhand, 8 from Uttar Pradesh, 5 each from Odisha and Bihar, 3 from West Bengal, 2 each from Uttarakhand and Assam, and 1 from Himachal Pradesh.
How did the trapped workers survive?
They were in a completed, roughly 2 km section with lighting and water. Air, water and dry food reached them through an existing 4-inch compressor pipe, and from 20 November a 6-inch pipe carried hot meals, fruit, medicines and a camera.
What was Operation Zindagi?
The name given to the Silkyara rescue operation, coordinated by the Uttarakhand government with central agencies, which ran from the collapse on 12 November to the rescue of all 41 workers on 28 November 2023.
What went wrong with the auger machine?
The American auger stopped at 22 metres on 17 November when it lifted and its bearings were damaged. Restarted with smaller 800 mm pipes, it hit steel girders and obstructions, and on 25 November it broke while being pulled back, leaving about 32 metres of it jammed in the pipe.
How far did the auger drill?
About 47 metres. The pipe reached 46.9 metres on 24 November before it was halted by another obstruction. The remaining stretch, to a total of about 57 metres, was dug by hand.
Who are rat-hole miners?
Workers skilled in digging very narrow tunnels by hand, a technique used in small coal mines. Rat-hole coal mining was banned by the National Green Tribunal in 2014, but the skill proved ideal for working inside an 800 mm pipe at Silkyara.
How did the rat-hole miners clear the debris?
Working in shifts inside the 800 mm steel pipe, they broke debris with hammers, chisels and shovels and pulled it out on a small trolley. They started late on 27 November and broke through on the evening of 28 November.
Who led the rat-hole miners at Silkyara?
Vakil Hasan, whose 12-man team cleared the final stretch. In February 2024 the Delhi Development Authority demolished his house in Khajoori Khas, saying it stood on government land, a move he protested.
What time were the workers rescued?
The first worker came out at about 8 pm on 28 November 2023, and the Uttarakhand government confirmed at about 8:50 pm that all 41 were out. NDRF teams brought them through the pipe one at a time on wheeled stretchers.
What was the role of the NDRF?
The National Disaster Response Force led the final evacuation, sending its personnel into the pipe and bringing the workers out one by one on specially adapted wheeled stretchers. NDRF and SDRF crews also cut obstructions inside the pipe.
What did SJVN do in the rescue?
Satluj Jal Vidyut Nigam drilled a 1-metre-wide vertical shaft from the hill above the trapped section, starting at 12:05 pm on 26 November. It had reached about 32 metres of the roughly 86 needed when the horizontal route broke through.
What were the other rescue plans?
RVNL drilled a narrow vertical supply bore and prepared horizontal micro-tunnelling, ONGC prepared a 24-inch vertical bore from the Barkot side, and THDC drove a rescue drift from the Barkot end, which had reached about 12 metres by 27 November.
Who is Arnold Dix?
An Australian tunnelling and underground-safety expert, president of the International Tunnelling and Underground Space Association, who advised the rescue on site. On 25 November he described the broken auger as busted.
Where were the rescued workers taken?
First to a temporary facility at the community health centre in Chinyalisaur, then on 29 November by an Indian Air Force Chinook helicopter to AIIMS Rishikesh. After checks, 40 were declared fit to go home.
How much compensation did the workers get?
Each worker received Rs 2 lakh from the contractor, plus paid leave or bonus and salary, and Rs 1 lakh from the Uttarakhand government, according to replies in Parliament. The rat-hole miners were each given Rs 50,000 cheques, which they declined to cash.
Who built the Silkyara tunnel?
NHIDCL, the National Highways and Infrastructure Development Corporation, awarded the work to Navayuga Engineering Company in May 2018 on an EPC contract worth Rs 853.79 crore, according to ThePrint.
Was anyone punished for the Silkyara collapse?
Show-cause notices were issued to the contractor and to the supervising consultant by July 2024, and the expert panel's final report reportedly recommended penal action. We have found no public record of final penalties; a notice is not a finding of guilt.
What did the expert committee find?
Its preliminary report was submitted on 22 December 2023. The final report, submitted on 20 September 2024 according to ThePrint, said all stakeholders overlooked their responsibilities, noted 21 collapses in four years and said the design lacked a separate escape passage.
Did the Silkyara tunnel have an escape passage?
The government said the single-tube tunnel is split by a partition wall so each side can serve as an escape route for the other, and that the contract provides for an escape passage. The expert panel reportedly said there was no separate dedicated escape passage.
Were there warnings about the rock?
Yes. The pre-construction geological report rated about 30 per cent of the alignment as poor or very poor rock, with exploratory drilling at only three points, and an authority engineer flagged very poor Class V rock in March 2019.
When did the Silkyara tunnel achieve breakthrough?
On 16 April 2025, when the excavation from the Silkyara and Barkot ends met, in the presence of Chief Minister Pushkar Singh Dhami. He said the tunnel would be renamed after the local deity Baba Baukhnag.
Has anyone died in the Silkyara tunnel since the rescue?
Yes. On 16 July 2026 a block of concrete lining fell about 900 metres in from the Barkot side, killing a 21-year-old worker from Jharkhand. NHIDCL and the district administration ordered inquiries.
What lessons did the Silkyara rescue teach?
Run several rescue plans in parallel, investigate geology properly before tunnelling, monitor ground movement during construction, build escape routes and emergency access, assign clear roles to agencies, and value skilled manual workers when machines fail.

⚠️ Editorial Note

This account draws on the Uttarakhand Academy of Administration’s 2024 case study, the NIDM workshop proceedings, Parliament replies as reported by PTI, ThePrint’s October 2024 report on the expert committee’s findings, and contemporary reporting by PTI, The Tribune, Deccan Herald, Scroll and The Wire. We have not read the expert committee’s report itself. Checking the brief this page began from against those records: the NIDM workshop was held on 28 November 2024, the first anniversary, not in 2025 (its proceedings were published in 2025); the Rs 2 lakh per worker was paid by the contractor, not by the government, so total government assistance was Rs 1 lakh per worker, not Rs 3 lakh; and the 6-inch lifeline was pushed through on 20 November by news accounts, with first video on 21 November. We added events the brief omitted: the contract and early rock warnings, the expert panel’s final report, the rewards row and the demolition of Vakil Hasan’s house, the tunnel’s April 2025 breakthrough and the fatal collapse of July 2026. We left out the brief’s February 2024 Rajya Sabha entry because we could not confirm its wording.