Jeddah Tower Timeline: How a Stalled Saudi Megaproject Is Racing Toward 1,000 Metres
Jeddah Tower construction timeline: the 2018 halt, the 2024 Saudi Binladin contract, January 2025 restart, and verified 2026 progress toward 1,000m.
For years, the unfinished concrete core rising out of Jeddah’s northern coastline was less a construction site than a monument to arrested ambition. Cranes sat still. Floors stopped counting at 63. A project once billed as the structure that would finally beat Dubai’s Burj Khalifa for the title of world’s tallest building had, by most outside appearances, been quietly shelved. Jeddah Tower was never officially cancelled — but for nearly seven years, that distinction barely mattered on the ground. The halt traced back to late 2017 and early 2018, a period when Saudi Arabia’s anti-corruption crackdown, contractor payment disputes and financial uncertainty collided, then compounded further when COVID-19 arrived. What changed the story wasn’t one announcement but a sequence of them: a 2023 tender process, an October 2024 completion contract worth SAR 7.2 billion, and finally, on 21 January 2025, concrete pouring resumed on the tower’s 64th floor with Kingdom Holding’s chairman, Prince Alwaleed bin Talal, on site. Since then, the tower has climbed faster than at almost any point in its history — past floor 100 by mid-2026, toward a still-unconfirmed final height above 1,000 metres. This is the story of how it stalled, and how it got moving again.

🔔 Latest Update — August 2026
Latest verified developer disclosure: Kingdom Holding’s Q2 2026 results, reported around 7 August 2026, with the underlying milestone confirmed on site by Prince Alwaleed bin Talal on 23 July 2026. Construction stands at approximately 430 metres, floor 106–107, with more than 300,000 cubic metres of concrete poured (≈67% of the total planned volume), a workforce of roughly 6,400, and more than 16 million work-hours logged without a lost-time incident. The most recent façade and MEP-specific figures available date to April 2026 (façade installed across 36+ floors, MEP first-fix on office levels 7–14) — no newer disclosure on those two specific items was found, so this article does not present them as current to August. No official Kingdom Holding or Jeddah Economic Company disclosure newer than the Q2 2026 results was identified at the time of writing.
🧠 AI Overview Summary
Jeddah Tower is a mixed-use skyscraper under construction in North Obhur, Jeddah, Saudi Arabia, designed to exceed 1,000 metres and become the world’s tallest building. Developed by Jeddah Economic Company (a Kingdom Holding subsidiary), it began construction in 2013, halted at roughly 63 floors in January 2018 amid Saudi Arabia’s anti-corruption campaign and contractor payment disputes, and restarted on 21 January 2025 under a new SAR 7.2 billion completion contract with Saudi Binladin Group. As of August 2026 it stands at approximately 430 metres and floor 106–107, targeting completion around 2028.
Jeddah Tower: Key Questions
What to Know About Jeddah Tower
- This is really three stories at once: the original 1,000-metre ambition, the seven-year halt, and the 2025 comeback — and conflating them is how most coverage of this project goes wrong.
- Construction reached roughly 63 floors before the January 2018 halt, connected to Saudi Arabia’s anti-corruption campaign, contractor payment disruption and financial uncertainty — not a single simple cause.
- The restart was a process, not an announcement: a September 2023 tender, an October 2024 completion contract, then the 21 January 2025 restart ceremony.
- The October 2024 contract is worth SAR 7.2 billion (≈$1.9bn), including roughly SAR 1.1bn recognising previously completed work — not the tower’s total lifetime cost.
- Since restarting, construction has moved fast: from floor 64 in January 2025 to floor 106–107 by mid-2026, roughly one floor every 3–4 days.
- The planned floor count is genuinely disputed — 157 vs. 167/168 — across real project-adjacent sources, and this article explains rather than picks a winner.
- No official final height beyond “1,000+ metres” has been disclosed, so any precise final figure circulating online is unverified.
- 2028 is a contractual/press target, not a guaranteed completion date — inferred from the October 2024 contract’s 42-month construction period.
- Jeddah Tower predates Saudi Vision 2030 (design work began 2009; Vision 2030 launched 2016) — it sits inside that investment climate, but wasn’t created by it.
Jeddah Tower Is Really Three Stories at Once
The original ambition, the long delay, and the comeback — told together, not separately
Most coverage of Jeddah Tower tells one of three stories: the original 1,000-metre ambition, the years it sat frozen at 63 floors, or the current construction sprint. Told alone, each is misleading. The ambition story alone reads as a press release. The halt story alone reads as failure. The current-progress story alone, without the other two, erases exactly what makes this project interesting: a supertall skyscraper that stalled for nearly seven years and is now rising faster than almost any comparable tower in the world.
The original ambition began in 2009, when Kingdom Holding Company and its project vehicle, Jeddah Economic Company, ran a design competition won by architect Adrian Smith and structural engineer Thornton Tomasetti — the same pairing behind Burj Khalifa. Early concepts reportedly explored a full mile-high (1,609 m) structure before soil mechanics on the coastal site ruled that out; the design that emerged instead targeted just over 1,000 metres, still enough to claim the world’s-tallest title by a comfortable margin over Dubai’s record-holder.
The long delay began in earnest around January 2018, when construction stopped at roughly the 63rd floor. The proximate trigger, documented across multiple retrospectives, was a period of upheaval following Saudi Arabia’s late-2017 anti-corruption campaign, which detained figures connected to the project’s contracting and financing chain, disrupting payment flows to the main contractor. Financial uncertainty extended the pause through 2019; COVID-19 extended it further through 2020 and 2021. The site was never formally cancelled — it was simply, for years, not moving.
The comeback didn’t happen in one announcement. Jeddah Economic Company opened a request-for-proposals process in September 2023 to find a contractor willing to finish the tower. That process produced an October 2024 completion contract with Saudi Binladin Group — the tower’s original contractor — worth SAR 7.2 billion. On 21 January 2025, Kingdom Holding’s chairman, Prince Alwaleed bin Talal, stood on site as concrete was poured on the 64th floor, formally restarting construction. Eighteen months later, the tower has climbed past floor 100 and roughly 430 metres, moving at a pace — about one floor every three to four days — that outstrips much of its pre-2018 construction rate.
Complete Timeline: From 2009 Design Competition to 2026 Construction Sprint
Newest first — every entry labeled by type and dated
Floor 106–107, ≈430 Metres — Kingdom Holding’s Q2 2026 Results
What happened: Prince Alwaleed bin Talal confirmed the milestone on site on 23 July 2026; Kingdom Holding’s Q2 2026 results, reported around 7 August 2026, put concrete poured above 300,000 m³ (≈67% of the planned total), workforce at ≈6,400, and cumulative work-hours above 16 million without a lost-time incident.
Level 99, ≈398 Metres — Kingdom Holding’s Q1 2026 Results
What happened: Kingdom Holding’s Q1 2026 earnings presentation disclosed Level 99, 274,000+ m³ of concrete poured (≈61% of plan), façade cladding installed across 36+ floors, MEP first-fix work across office levels 7–14, and a workforce of ≈6,000.
Floor 80 Confirmed
What happened: Trade press confirmed on 6 January 2026 that the tower had surpassed 80 floors by December 2025, underscoring the accelerating pace since restart.
Official Restart: Concrete Poured on Floor 64
What happened: Kingdom Holding held a restart ceremony on site; Prince Alwaleed bin Talal and company leadership attended as concrete was poured on the tower’s 64th floor — one floor above where construction had stalled in 2018.
SAR 7.2 Billion Completion Contract Signed
What happened: Jeddah Economic Company signed a completion contract with Saudi Binladin Group worth SAR 7.2 billion (≈$1.9bn), including roughly SAR 1.1bn recognising previously completed pre-2018 work, with a 42-month anticipated construction period.
Restart Process Begins: Request for Proposals
What happened: Jeddah Economic Company opened a tender process seeking a contractor to complete the tower, beginning renewed negotiation with Saudi Binladin Group — the first concrete step toward restarting in nearly six years.
The Long Stall
What happened: The site sat largely idle for roughly five years following the January 2018 halt; the 2020–2021 COVID-19 pandemic further disrupted any recovery planning during this window.
Construction Halts at Roughly 63 Floors
What happened: Work stopped amid contractor payment disruption and financial uncertainty, following upheaval connected to Saudi Arabia’s late-2017 anti-corruption campaign, which had detained figures tied to the project’s contracting and financing chain.
Construction Begins
What happened: Groundbreaking and early piling work started on the North Obhur site, four years after the design competition concluded — the formal start of the physical build.
Design Refined Toward 1,000+ Metres
What happened: After early mile-high (1,609 m) ambitions were ruled out on soil-mechanics grounds, the design settled on a target above 1,000 metres under the “Kingdom Tower” name.
Jeddah Economic Company Established; Design Competition Won
What happened: Adrian Smith and Thornton Tomasetti won a design competition commissioned by Kingdom Holding Company and its project vehicle, Jeddah Economic Company — the tower’s real institutional origin, then known as Kingdom Tower.
157 or 168 Floors? The Discrepancy, Explained
Two real numbers, from real project-adjacent sources — not resolved by picking one
Ask how many floors Jeddah Tower will have and you’ll get two different answers depending on the source, and this article does not pretend one of them is simply wrong. Jeddah Economic Company’s and Adrian Smith + Gordon Gill Architecture’s project specification material cites 157 floors, with the planned sky terrace observation deck positioned at floor 157, roughly 644 metres up. Other project-adjacent and press material — including some architect-firm documentation — cites 167 to 168 floors, alongside a separate figure of 252 total levels when mechanical and service floors are included.
The most plausible explanation is a counting-methodology difference — occupied/usable floors versus a fuller level count that includes mechanical and sky-lobby floors — rather than an actual design change to the tower’s height. But that is an inference, not a confirmed reconciliation: no single Kingdom Holding or JEC disclosure reviewed for this article directly addresses why the two numbers differ. Until one does, this article reports both figures, attributed to their respective source types, rather than silently picking the one that sounds more current.
Who Is Building Jeddah Tower
Developer, architect, engineer and contractor — verified roles only
Jeddah Economic Company
A Kingdom Holding Company subsidiary and the project’s development vehicle since 2009, overseeing Jeddah Tower as the centerpiece of the wider Jeddah Economic City masterplan.
Adrian Smith + Gordon Gill Architecture
Chicago-based firm led by Adrian Smith, the lead designer of Burj Khalifa, who won the original 2009 design competition alongside structural engineer Thornton Tomasetti.
Thornton Tomasetti
Engineered the tower’s buttressed-core structural system and wind-response design — the same structural engineering firm behind Burj Khalifa’s core.
Saudi Binladin Group
The original pre-2018 contractor, re-awarded the completion contract in October 2024 to finish construction under Jeddah Economic Company’s oversight.
Turner
Confirmed via CTBUH’s Skyscraper Center as the project manager overseeing construction following the 2025 restart.
KONE
Supplying elevator systems using UltraRope carbon-fibre hoisting technology, with double-deck cars reported for the tower’s upper reaches, including the planned sky terrace.
Why Jeddah Tower Stopped in 2018
A compounding disruption, not a single decreed event
Construction halted around January 2018 amid a period of political and contractual upheaval, including the Saudi government’s anti-corruption campaign. That single sentence is accurate, but it is also, on its own, too simple — and this article separates what is documented from what is inference.
Documented: In late 2017, Saudi Arabia’s anti-corruption crackdown detained a number of prominent business and government figures, including people connected to the project’s contracting and co-financing structure. Around the same period, payment disruptions to the main contractor and broader financial uncertainty are separately documented in retrospective reporting on the project. Construction had reached approximately the 63rd floor when work stopped.
Interpretation, not fact: No single official document reviewed for this article states a formal, singular reason for the halt. Coverage since has generally described the stoppage as resulting from the combined effect of the anti-corruption disruption, contractor payment problems and financial uncertainty — compounding factors rather than one traceable order to stop work. The pause then extended through the COVID-19 pandemic in 2020–2021, by which point restarting required not just resolving the original disputes but remobilising an entire construction operation from scratch.
| Period | What happened |
|---|---|
| 2017 | Saudi Arabia’s anti-corruption campaign detains figures connected to the project’s contracting/financing chain |
| Jan 2018 | Construction halts at approximately 63 floors |
| 2018–2019 | Contractor payment disputes, financial uncertainty, no active construction |
| 2020 | COVID-19 disrupts any recovery planning globally |
| 2021–2022 | Project status remains publicly uncertain |
| Sep 2023 | Request-for-proposals process begins |
| Oct 2024 | Completion contract signed with Saudi Binladin Group |
| Jan 2025 | Construction officially restarts |
How Tall Will Jeddah Tower Be?
1,000+ metres is the target — the exact final figure remains undisclosed
Jeddah Tower’s official target is “over 1,000 metres” (3,280+ feet). Kingdom Holding and Jeddah Economic Company have not published a precise final architectural height beyond that threshold figure in the material reviewed for this article — a level of imprecision that is itself notable for a project this closely watched, and this article does not fill that gap with a specific number pulled from unofficial sources.
Burj Khalifa, the current record-holder, stands at 828 metres, completed and operational since 2010. If Jeddah Tower reaches its planned 1,000+ metre target, it would surpass Burj Khalifa by more than 170 metres, becoming the tallest completed building on Earth. As of August 2026, Jeddah Tower’s constructed height is approximately 430 metres — a real, verified construction milestone, but well short of even Burj Khalifa’s completed height, let alone the tower’s own final target. Jeddah Tower is not the world’s tallest building yet. It is a building under construction that is designed to become the tallest completed building, if and when it finishes at its planned height.
Jeddah Tower vs. Burj Khalifa
Only comparable on completed status — one of these buildings isn’t finished
Jeddah Tower (Under Construction) vs. Burj Khalifa (Completed)
| Building | Height | Status | Location | Year |
|---|---|---|---|---|
| Burj Khalifa | 828 m | Completed | Dubai, UAE | 2010 |
| Merdeka 118 | 678.9 m | Completed | Kuala Lumpur, Malaysia | 2023 |
| Jeddah Tower | 1,000+ m planned; ≈430 m built | Under construction | Jeddah, Saudi Arabia | Target 2028 |
Engineering a Kilometre-High Tower
Structure, foundation, concrete and wind — the four real constraints
Jeddah Tower is built around a buttressed-core structural system — the same structural family Adrian Smith and Thornton Tomasetti used on Burj Khalifa: a hexagonal central concrete core braced by three wings radiating outward, each wing acting as a buttress against the others. High-strength reinforced concrete is pumped from ground level through the core using pumps rated for extreme vertical lift; as the tower has climbed past 400 metres, pumping distance and concrete curing time in Jeddah’s heat are both live engineering constraints, not settled ones. Construction advances on a jump-form cycle for the core, with tower cranes climbing alongside it, while façade and MEP installation trail well behind the leading concrete pour — which is why façade cladding had reached only floor 36+ as of April 2026 even as the core was already past floor 99.
The tower sits on a hybrid piled-raft foundation: reportedly 270 piles, 1.5–1.8 metres in diameter, driven to depths of roughly 105 metres, topped by a 5-metre-thick concrete raft spanning approximately 3,200 m², engineered to keep differential settlement under 25 mm across the load given the site’s coastal, sandy soil conditions.
Above roughly 300–400 metres, wind — not gravity — becomes a supertall tower’s dominant design problem. Sustained high-altitude wind can trigger vortex shedding, where alternating low-pressure pockets peel off a tall, uniform cross-section and induce rhythmic sway. Jeddah Tower’s three-wing, Y-shaped footprint is engineered specifically to disrupt this: by varying the building’s cross-section as it tapers upward, the design prevents wind vortices from synchronising into a single resonant sway pattern — the same wind-engineering principle Adrian Smith applied on Burj Khalifa, and a documented design rationale rather than a generic architectural flourish.
What Will Be Inside Jeddah Tower
Mixed-use program, hotel and observation deck — design targets, not open facilities
Vertical Mixed-Use City
Planned uses span luxury residences, Class-A office space and retail — consistent with megatall precedent like Burj Khalifa. Exact unit counts from pre-2018 material aren’t reconfirmed post-restart.
Four Seasons (Design-Stage)
A Four Seasons hotel component — commonly cited at roughly seven floors and 200 rooms — was part of the original design. No post-restart confirmation of the exact allocation was found; it is not open.
Sky Terrace, ≈644 Metres
A cantilevered observation platform planned at floor 157 per JEC specification material, reported as intended to be the world’s highest observation deck once operational. Not open, not under confirmed active fit-out.
KONE UltraRope, Double-Deck
Carbon-fibre hoist ropes replace steel cables at extreme height, with double-deck cars reportedly planned to serve the tower’s upper floors and sky terrace.
Jeddah Tower Is More Than a Skyscraper
The centerpiece of a 5.3 million square metre masterplan
Jeddah Tower is the centerpiece and first phase of Jeddah Economic City, a roughly 5.3 million square metre mixed-use masterplan on the North Obhur coastline. Kingdom Holding and Jeddah Economic Company frame the tower as the anchor investment around which the surrounding development — residential, commercial and supporting infrastructure — is built out, requiring coordinated water, electricity, sewage, drainage and connectivity infrastructure alongside the tower rather than after it. Reported figures place the full masterplan’s development value around $20 billion, a figure distinct from — and far larger than — the tower’s own construction contract values (see the cost section below).
Why North Obhur: the site sits on Jeddah’s Red Sea coastline, giving the tower and its surrounding development direct waterfront access. Jeddah itself is Saudi Arabia’s historic Red Sea trade and pilgrimage gateway, home to a major international airport and port — a commercial and tourism hub independent of this one project, which is part of why the site was chosen for a development intended to draw international investment and visitors.
Saudi Vision 2030: Context, Not Cause
The tower predates Vision 2030 — the relationship is climate, not origin
Jeddah Tower’s design origin dates to 2009; Saudi Arabia’s Vision 2030 economic-diversification programme launched in 2016. The tower was not conceived as a Vision 2030 project, and this article does not claim Vision 2030 built it. What is accurate: the tower’s 2024–2025 restart occurred inside a period when Saudi Arabia has aggressively prioritised giga-projects and urban-development investment as part of Vision 2030, and Kingdom Holding’s own public framing situates the tower within that broader national development narrative. The relationship is contextual and financial-climate, not causal-origin — a distinction worth holding onto given how often the two get blurred in casual coverage.
Cost: Three Numbers, Not One
Original estimate, completion contract, and full masterplan value are not interchangeable
| Figure | Amount | What it actually covers |
|---|---|---|
| Original tower construction estimate | ≈$1.2 billion | Pre-2018 budget estimate for the tower alone; not an audited final cost, since the tower was never finished at this budget |
| October 2024 completion contract | SAR 7.2 billion (≈$1.9bn) | Saudi Binladin Group’s contract to finish the tower, including ≈SAR 1.1bn recognising prior work and ≈SAR 6.1bn in new committed spend |
| Jeddah Economic City masterplan value | ≈$20 billion | The full mixed-use development around the tower — the tower is one phase within this, not the whole figure |
None of these three figures is “the cost of Jeddah Tower.” Reporting that mixes them — treating SAR 7.2 billion as the tower’s total lifetime cost, for instance — is a common but avoidable error this article does not repeat.
Key Facts Table
Every figure dated and sourced
| Fact | Latest verified information | Date |
|---|---|---|
| Planned height | 1,000+ metres (exact final figure undisclosed) | Ongoing target |
| Current height | ≈430 metres, floor 106–107 | ~7 Aug 2026 (Q2 2026 results) |
| Planned floor count | 157 (JEC/AS+GG spec) vs. 167–168 (other sources) | Unresolved discrepancy |
| Location | North Obhur, Jeddah, Makkah Province | — |
| Developer | Jeddah Economic Company | — |
| Contractor | Saudi Binladin Group | Contract signed Oct 2024 |
| Construction restarted | 21 January 2025, floor 64 | Jan 2025 |
| Completion contract value | SAR 7.2 billion (incl. ≈SAR 1.1bn prior work) | Oct 2024 |
| Planned completion | 2028 (target, not guaranteed) | — |
| Observation deck | ≈644 m, at floor 157 per spec | Design target |
Jeddah Tower: What Is Confirmed and What Is Still a Target
Claim vs. fact, classified
| Claim | Status |
|---|---|
| Jeddah Tower will be over 1,000 metres | OFFICIAL PROJECT TARGET |
| Jeddah Tower will become the world’s tallest building | EXPECTED IF COMPLETED AT PLANNED HEIGHT |
| Jeddah Tower will open in 2028 | TARGET/SCHEDULE, NOT GUARANTEED |
| Jeddah Tower is at floor 106–107, ≈430 m | DATED OFFICIAL FIGURE, ~7 AUG 2026 |
| Jeddah Tower has 157 floors | DISPUTED / SOURCE-DEPENDENT |
| Jeddah Tower cost SAR 7.2 billion | 2024 CONTRACT VALUE ONLY, NOT TOTAL COST |
| Jeddah Tower halted solely due to the anti-corruption campaign | PARTIAL FACTOR, NOT SOLE CAUSE |
| Jeddah Tower has a Four Seasons hotel | DESIGN-STAGE TARGET, NOT RECONFIRMED |
| Jeddah Tower’s observation deck is operating | NOT OPEN — DESIGN TARGET ONLY |
Worth Knowing
- Jeddah Tower’s architect, Adrian Smith, also led the design of the current record-holder, Burj Khalifa
- The project’s foundation reportedly uses 270 piles driven roughly 105 metres deep — among the deepest pile foundations of any supertall building
- Saudi Binladin Group is both the tower’s original pre-2018 contractor and its post-2024 completion contractor
- Kingdom Holding has reported zero fatalities and 16 million-plus work-hours without a lost-time incident since the January 2025 restart
- Jeddah Tower is not part of NEOM — a separate, geographically distinct Saudi giga-project in Tabuk Province