Egypt New Administrative Capital: Timeline, Costs and the $60 Billion Question

📅 Updated 14 October 2026🏙️ ~30,000 residents⚠️ Latest: hydrogen tram MoU
Advertisement

View as Web Story

In short

Egypt New Administrative Capital timeline: the OECD's $60bn cost estimate, the 2023 ministry move, the 2026 monorail and why only 30,000 people live there.

Latest Story

East of Cairo, Egypt has spent a decade turning bare desert into a new seat of government. The Egypt New Administrative Capital, renamed ‘The New Capital’ in November 2025, now holds the ministries, parliament, the presidency, Africa’s tallest tower and the Octagon military command, and since May 2026 a monorail links it to Cairo. What it does not yet have is people. About 30,000 residents live in a city planned for 6.5 million, and the bill, put by the OECD at about $60 billion so far, has never been published in audited form. This guide follows the project year by year, decodes the competing cost figures and sets out how to judge whether it is working.

Advertisement

💡 Short Answer

Egypt’s New Administrative Capital is a planned city about 45 km east of Cairo, announced in March 2015 and run by ACUD, a company 51% owned by Defence Ministry entities. Ministries began working there in mid-2023 and it became the formal seat of government in April 2024. The OECD estimates costs so far at about US$60 billion, largely paid by developers. In October 2026 it had about 30,000 residents against a 6.5 million plan.

🏙️ Egypt’s New Capital: Quick Facts
Announced13 March 2015
Government movedMid-2023
Cost so far (OECD)~US$60 billion
Residents, Oct 2026~30,000
Planned population~6.5 million
Tallest buildingIconic Tower, 393.8 m
⚡ Quick Answers — AI Overview Ready

Egypt’s New Administrative Capital: Key Questions

How much has Egypt’s new capital cost?
About US$60 billion so far, according to the OECD’s 2024 survey, largely borne by developers. ACUD reported EGP 500 billion spent on phase-one infrastructure and buildings by January 2024. No audited project-wide total has been published.
Has the government moved there?
Yes. Ministries began working in the government district in mid-2023, and President Sisi was sworn in at the new parliament on 2 April 2024. The cabinet, parliament and the Octagon military command, opened on 4 July 2026, now operate there.
How many people live there?
About 30,000 in October 2026, according to ACUD. It targets 60,000 by the end of 2026 and 250,000 within three years, against a long-term plan of about 6.5 million residents.
Is it connected to Cairo by rail?
Yes. An electric light-rail line opened on 3 July 2022, and the East Nile Monorail began carrying passengers on 6 May 2026 between New Cairo and the capital’s Justice City, with fares from EGP 20 to EGP 80.
📚 Key Takeaways

Egypt’s New Capital in Nine Points

  • Announced in 2015: unveiled at the Sharm el-Sheikh investment conference on 13 March 2015.
  • Military-led: ACUD is 51% owned by Defence Ministry entities and 49% by the housing ministry’s NUCA.
  • Government first: ministries moved in mid-2023; Sisi’s 2 April 2024 oath made it the seat of government.
  • Cost unclear: about $60 billion so far (OECD), $58 billion (2019 reports), EGP 500 billion for phase one (ACUD).
  • Currency matters: EGP 500 billion was about $32bn before 2022 and about $10bn at mid-2026 rates.
  • Few residents: about 30,000 in October 2026, roughly 0.5% of the 6.5 million planned.
  • Transport arrived late: light rail in 2022, the monorail on 6 May 2026, a hydrogen tram only at study stage.
  • New name: officially ‘The New Capital’ since 8 November 2025.
  • The test now: occupancy, private jobs, affordable homes and transparent accounts, not more towers.

Egypt’s New Capital at a Glance

Figures have different dates and scopes. Planned capacity is not occupancy. Scroll sideways on a phone.

DetailKey factSource / date
LocationEast of Cairo, toward Suez; usually given as ~45 km (OECD: 35 km)Varies by measuring point
Official name‘The New Capital’ (was New Administrative Capital)ACUD, 8 Nov 2025
Announced13 March 2015, Sharm el-SheikhEgypt Economic Development Conference
DeveloperACUD: 51% Defence Ministry entities, 49% NUCAOECD, 2024
Government movedMid-2023; formal seat from 2 Apr 2024OECD; Reuters
Planned area / people700–725 km²; ~6.5 millionOECD; ACUD
Residents now~30,000; target 60,000 by end-2026ACUD chairman, Oct 2026
Cost estimate~US$60bn ‘so far’, largely developer-borneOECD Economic Survey, Feb 2024
Phase-one spendingEGP 500bn (infrastructure and buildings)ACUD to Reuters, Jan 2024
LandmarksIconic Tower (393.8 m), Octagon, Green River, Arts and Culture City2019–2026
TransportLRT (Jul 2022), East Nile Monorail (6 May 2026)SIS; Reuters

Timeline: From Desert Blueprint to Working Capital

Newest first, from October 2026 back to the 2015 announcement. Tags mark building, openings, moves, plans, costs and 2026 developments.

Advertisement

Population becomes the test 2026

ACUD: ~30,000 residentsTargets: 60,000 by end-2026, 250,000 in three yearsHydrogen tram MoU, 7 Oct

In early October ACUD chairman Khaled Abbas said about 30,000 people now live in the capital. He set targets of about 60,000 by the end of 2026 and 250,000 within three years, and said the Central Bank of Egypt would move in within months, followed by 18 banks. These are targets, not counts: in January 2024 only about 1,200 families had moved in.

On 7 October the National Authority for Tunnels signed a memorandum with South Korea’s Hyundai Rotem to study a hydrogen-powered tram network of 44 trainsets on a route of roughly 28 km. No cost or financing was disclosed. The same week, official data showed urban inflation at 13.9% in September, with transport prices up 24.3% year on year.

Even at 60,000 residents, the city would hold under 1% of its planned 6.5 million people.

The Octagon opens Opens

State Strategic Command HQ inaugurated, 4 Jul 2026Eight buildings in an octagon30,000+ residents reported

President Abdel Fattah el-Sisi inaugurated the State Strategic Command Headquarters, known as the Octagon, on 4 July. Egypt’s State Information Service called it the largest complex of its kind in the Middle East, linking the armed forces’ leadership with ministries, governorates and field commands. In his speech Sisi said attacks around Bab el-Mandeb had cost Egypt more than $10 billion in lost Suez Canal revenue.

An Asharq Al-Awsat report on 16 July summed up the paradox: the city hosted cabinet meetings, conferences and even a World Cup fan zone, but residential occupancy remained limited, with about 70% of first-phase land sold to developers.

The Octagon is visible from space: NASA’s 2024 Landsat image labels it at the centre of the city’s circular plan.
NASA Landsat images of the same patch of desert on 14 August 2017 (left) and 9 August 2024 (right)
NASA Landsat images of the same patch of desert on 14 August 2017 (left) and 9 August 2024 (right): the government district, the Green River park and the Octagon site have appeared. NASA Earth Observatory images by Michala Garrison using Landsat data, public domain.

The monorail carries passengers Opens

East Nile Monorail opens, 6 May 202616 stations, New Cairo to Justice CityPM review of services, 19 May

The driverless East Nile Monorail welcomed its first public passengers on 6 May 2026, running 6 a.m. to 6 p.m. over 16 stations from Marshal Tantawi in New Cairo to Justice City. The full line is 56.6 km with 22 stations to Nasr City, cost roughly $2.8 billion and can carry 600,000 passengers a day at full capacity. Fares run from EGP 20 to EGP 80.

On 19 May Prime Minister Mostafa Madbouly told ACUD to speed up the opening of the Arts and Culture City, the Olympic City, the Green River and commercial outlets, and stressed road and building maintenance – an admission that finished infrastructure was not yet a working city.

The six Nasr City stations were due to follow within about two months; the West Nile line to 6th of October City is a separate project.

The Spine: a separate $27bn bet Plan

Talaat Moustafa Group and National Bank of Egypt, 18 Apr 2026EGP 1.4 trillionNext to Madinaty, east Cairo

Talaat Moustafa Group unveiled The Spine, a 2.4 million square metre mixed-use city with 165 towers, planned with the National Bank of Egypt and a paid-up capital of EGP 69 billion. Its projected investment of EGP 1.4 trillion (about $27 billion) equals roughly 1% of Egypt’s GDP.

The Spine is not part of the New Administrative Capital. It sits beside TMG’s Madinaty and competes for the same buyers. Its price tag must not be added to, or confused with, the capital’s cost.

TMG says The Spine could generate about EGP 818 billion in tax revenue over time and 55,000 direct jobs.
Nov 2025–
Feb 2026

A new name, and maybe another Plan

ACUD: ‘The New Capital’ in official use, 8 Nov 2025Draft law on special status and the name ‘Memphis’ reported, Feb 2026

ACUD announced that the city would be called ‘The New Capital’ in all official correspondence, dropping ‘Administrative’ to sell it as a place to live rather than an office park. In February 2026 a draft law was reported to propose a special-status province named Memphis, after Egypt’s ancient capital. It had not become law by October 2026.

Ancient Memphis, Egypt’s first capital, lies about 20 km south of modern Cairo – on the other side of the Nile from the new city.
2 Apr
2024

Sisi sworn in at the new parliament Move

Third presidential term beginsCity formally inaugurated as the seat of government

Abdel Fattah el-Sisi took the oath for his third term before the House of Representatives in its new building in the capital. The ceremony formally marked the city as Egypt’s seat of government, nine years after it was announced and four years after the original 2020 target.

Cairo remained the legal capital in daily life: most embassies, businesses and almost all residents were still there.

Africa’s tallest tower is finished Build

Iconic Tower, 393.8 m, 77 storeysBuilt by CSCEC since May 2018First three CBD towers handed over, 14 Jan 2024

The Iconic Tower in the Central Business District, 393.8 metres and 77 storeys, was completed and listed by the Council on Tall Buildings and Urban Habitat as among the tallest buildings finished worldwide in 2024. It holds offices, branded apartments and a hotel. China State Construction Engineering Corporation built it and the surrounding CBD towers.

At 393.8 m it stands about 160 m above Africa’s previous tallest building, the 234 m Leonardo in Johannesburg.
The Iconic Tower and Central Business District towers, June 2023
The Iconic Tower and Central Business District towers, June 2023. Mohamed Ouda, CC BY-SA 4.0, via Wikimedia Commons.

EGP 500 billion spent, the chairman says Cost

Reuters interview with ACUD’s Khaled Abbas48,000 employees a day1,200 families moved inMadbouly: financing outside the budget, 14 Jan

ACUD chairman Khaled Abbas told Reuters the company had spent EGP 500 billion on first-phase infrastructure and buildings and estimated the second phase’s infrastructure at EGP 250–300 billion. At early-2024 exchange rates EGP 500 billion was about $16 billion; before the 2022 devaluations it would have been about $32 billion.

About 48,000 employees commuted in daily, 100,000 housing units were finished, and about 1,200 families had moved in. On 14 January, handing over the first three CBD towers, Prime Minister Madbouly said financing was outside the state budget and ACUD’s profits had passed EGP 20 billion.

Abbas also said ACUD planned a stock-market flotation by the end of 2024; no listing had taken place by October 2026.

Ministries start work in the desert Move

Government district operating from mid-2023 (OECD)Ministries operating from July 2023 (Reuters)

After delays blamed on COVID-19, civil servants began working in the Government District, a long mall of ministry buildings around a central green. The OECD dates the district’s start to mid-2023; Reuters dates ministries’ operation from July 2023.

The move turned a construction site into an administrative centre, but most staff commuted from Cairo by bus and, from 2022, by light rail. A government that works there is not the same as a city that lives there.

The original target for moving ministries was 2020, slipping to 2022 and then 2023.
Ministry buildings in the Government District, May 2023
Ministry buildings in the Government District, May 2023, weeks before ministries began working there. Abdelrhman 1990, CC BY-SA 4.0, via Wikimedia Commons.
3 Jul
2022

The light rail arrives Opens

Cairo LRT, 70 km, 12 stationsAdly Mansour to the new capital and 10th of RamadanBuilt with Chinese contractors

Sisi and China’s ambassador opened the first 70 km of the Cairo Light Rail Transit, an electric line from Adly Mansour station in eastern Cairo to the new capital and 10th of Ramadan City. It came from a $1.24 billion contract signed in August 2017 with China Railway Engineering Corporation and AVIC International.

The LRT was designed for 360,000 passengers a day, built for a city that did not yet have residents.

The $58 billion headline Cost

Reuters cites $58bn price tagMada Masr questions ‘outside the budget’ claim, May 2019Cathedral and mosque open, 6 Jan

Reporting in 2019 put the capital’s overall price at about $58 billion, the figure still repeated in news coverage in 2026. In May 2019 the independent outlet Mada Masr asked whether a project said to be ‘outside the state budget’ was also outside public accountability, since ACUD’s accounts went unpublished.

On 6 January, Coptic Christmas Eve, Sisi opened the Cathedral of the Nativity of Christ, then the largest church in the Middle East, and the Al-Fattah Al-Aleem Mosque on the same day, a statement of national unity built into the new city’s first finished landmarks.

The $58 billion figure was an estimate, not an audited total, and it predates Egypt’s three devaluations of 2022–2024.
The Al-Fattah Al-Aleem Mosque, opened with the Cathedral of the Nativity on 6 January 2019, photographed
The Al-Fattah Al-Aleem Mosque, opened with the Cathedral of the Nativity on 6 January 2019, photographed during a US Secretary of State visit on 10 January 2019. U.S. Department of State, public domain, via Wikimedia Commons.

The Central Business District rises Build

CSCEC begins the Iconic Tower20 towers in the CBDChinese financing and contractors

China State Construction Engineering Corporation, which had signed a memorandum on the capital in September 2015, began the Central Business District: some 20 office, residential and hotel towers led by the Iconic Tower. Chinese banks financed much of the package.

The CBD was meant to give private business a reason to follow the government east.
Towers under construction in the Central Business District, built by China State Construction Engineering Corporation, May 2023
Towers under construction in the Central Business District, built by China State Construction Engineering Corporation, May 2023. Abdelrhman 1990, CC BY-SA 4.0, via Wikimedia Commons.

Desert, roads and a plan Build

NASA Landsat, 14 Aug 2017: mostly bare desertLRT contract, Aug 2017Government district and housing under way

A NASA satellite image from August 2017 shows little more than graded road rings and building pads on bare desert. Over the next seven years roads, utilities, the government district, the first residential districts and the Green River park would fill the frame.

The first two phases each cover about 40,000 feddans (168 km²), roughly the size of a large existing Egyptian city.
21 Apr
2016

ACUD is created Plan

Joint-stock company51% Ministry of Defence entities, for the land49% New Urban Communities Authority, EGP 20bn cash

The Administrative Capital for Urban Development company was set up to own and develop the land. According to the OECD, entities of the Ministry of Defence took 51% in return for contributing the land, and the New Urban Communities Authority took 49% for a EGP 20 billion injection.

The model: ACUD plans and services land, then sells or auctions plots to developers who build within set deadlines. It made the military the project’s senior partner and kept its accounts off the state budget.

The OECD notes that ACUD’s financial statements, balance sheet and contingent liabilities are not publicly available.
13 Mar
2015

A new capital is announced Plan

Egypt Economic Development Conference, Sharm el-SheikhInitial pitch about $45bnEmirati-led partner deal later falls through

At an investment conference in Sharm el-Sheikh, the government unveiled plans for a new capital between Cairo and Suez, pitched with an Emirati-led developer, Capital City Partners, at around $45 billion. That partnership did not proceed, and the state and military took the lead instead.

The promise: ministries, parliament, a presidential palace, embassies, a business district, parks and housing for millions, relieving a Greater Cairo of about 20 million people.

The capital was announced less than two years after Sisi, then defence minister, led the military’s removal of President Mohamed Morsi in July 2013.
Advertisement

Who Will Live Here?

A government can move by decree. Residents have to choose to come.

People in the new capital: today vs the plan (log scale)10k100k1m10mResidents, Oct 2026~30,000Daily commuting staff, Jan 2024~48,000Target, end-202660,000Target, ~2029250,000Phase one projection1.5 millionFull plan6.5 millionSources: ACUD chairman Khaled Abbas (Oct 2026 targets; Jan 2024 to Reuters). Commuters work there but mostly live elsewhere.30,000 residents is about 0.5% of the 6.5 million planned.
The gap that matters: the city has been built for millions and is lived in by tens of thousands.
🏙️ Interactive: Who Will Live Here?

Pick a milestone. How full is the city?

The meter shows each figure as a share of the 6.5 million people the capital is planned for. Targets are targets, not counts.

How Much Does Egypt’s New Capital Cost?

There is no single published bill. Here is what each headline number means.

FigureDateWhat it measuresCan it be added?
~US$45 billion2015Launch pitch with Capital City PartnersNo: superseded plan
~US$58 billion2019Reported overall price tagNo: an estimate, pre-devaluation
EGP 500 billionJan 2024Phase-one infrastructure and buildings spent (ACUD)Part of the total
EGP 250–300 billionJan 2024Phase-two infrastructure, estimated (ACUD)Forecast only
~US$60 billionFeb 2024Cost associated so far, largely developer-borne (OECD)Best whole-project figure; unaudited
~US$2.8 billionMay 2026East Nile Monorail (whole 56.6 km line)Separate transport budget
EGP 1.4 trillion (~US$27bn)Apr 2026The Spine, TMG’s separate cityNo: a different project
💰 Interactive: The $60 Billion Question

Pick a number from the headlines. What does it really measure?

Cost figures for the new capital come from different years, currencies and scopes. They cannot simply be added together.

Who pays?

ACUD’s model is to turn state land into money. It services land with roads and utilities, then sells or auctions plots to private and state-linked developers, who finance their own towers and compounds. The government says this keeps the capital outside the state budget, and Prime Minister Madbouly said in January 2024 that ACUD’s profits had passed EGP 20 billion.

The OECD’s 2024 survey of Egypt accepts that the cost has been ‘borne to a large extent by developers’, but adds that ACUD’s financial statements and balance sheet are not public, and neither are the related budget outlays and contingent liabilities. State banks lend to developers, state agencies buy offices, and public money builds the rail links. Without published accounts, outsiders cannot check how much risk sits with the public.

Why the dollar figure keeps moving

Egypt devalued its pound several times between 2022 and 2024, and the currency traded near EGP 50 to the dollar in mid-2026. Spending in pounds does not change when the exchange rate moves, but its dollar headline does.

The same EGP 500 billion, three dollar figures$0bn$10bn$20bn$30bnAt pre-2022 rate (~EGP 15.7/$)~$32bnAt Jan 2024 rate (~EGP 31/$)~$16bnAt mid-2026 rate (~EGP 50/$)~$10bnPhase-one spending reported by ACUD, January 2024: EGP 500 billionPre-2022 and Jan 2024 conversions as reported by Reuters; mid-2026 rate as cited by Asharq Al-Awsat (July 2026).Illustrative: spending happened over years at different rates, so no single conversion is ‘correct’.
Why dollar headlines about the capital disagree: Egypt’s pound lost about two-thirds of its value between 2022 and 2026.

Why Is Egypt Building a New Capital?

Congestion

Relieve Cairo

Greater Cairo holds about 20 million people. Moving ministries out was meant to cut traffic and free central land, though most staff still commute.

Growth

Room for a bigger population

Egypt passed 100 million people in 2020. New desert cities are the state’s answer to housing demand outside the Nile Valley.

Administration

Modern offices

Purpose-built ministries and digital systems in one district; reform of how government works is a separate, harder task.

Investment

Land as revenue

Plot sales to developers fund infrastructure and generate profit for ACUD and its state shareholders.

Security

A defensible seat of power

Critics note the capital moved government away from Cairo’s squares, where the 2011 uprising unfolded. The Octagon centralises military command there.

Prestige

A national statement

Africa’s tallest tower, the largest church and mosque complexes and an Olympic City signal ambition to investors and Egyptians alike.

The Biggest Challenges Facing the New Capital

1. Cost and accountability

The project competes with schools, hospitals, existing-city infrastructure and debt service for national attention. The OECD’s point is not that the capital has failed financially, but that limited disclosure makes it impossible to tell.

2. Occupancy

About 30,000 residents in October 2026 is small for infrastructure designed for millions. Asharq Al-Awsat reported apartment prices around EGP 50,000 per square metre in July 2026, far above what most civil servants earn, so many keep commuting from Cairo.

3. Water and climate

The capital draws on the Nile through treatment plants that ACUD said would together use about 1% of Egypt’s share of the river. The 35 km Green River park and other landscaping need efficient irrigation and treated wastewater to be sustainable in one of the world’s most water-stressed countries.

4. Transport and daily life

The light rail and monorail now exist, but the monorail runs only 6 a.m. to 6 p.m. and a full-line daily commute costs about 22% of the minimum wage. Residents also need schools, clinics, shops and night-time life before the city feels like one.

5. Competition from other megaprojects

Private schemes such as The Spine, New Alamein on the coast and dozens of east-Cairo compounds compete for the same buyers and the same state attention.

How Should the Project’s Success Be Measured?

1

Population

Do people choose to live there permanently, beyond the 60,000 and 250,000 targets?

2

Occupancy

Are the finished flats and offices lived in and used, not just sold?

3

Employment

Do private firms create durable jobs beyond construction and government?

4

Affordability

Can ordinary workers afford homes and the daily commute?

5

Public finances

Are ACUD’s accounts, liabilities and returns disclosed?

6

Sustainability

Can water, energy and transport keep up as the city grows?

Explore More Timelines

People Also Ask

Is Egypt moving its capital from Cairo?
Government functions have moved: ministries, cabinet, parliament and the presidency now work in the new capital, east of Cairo. Cairo remains the country’s largest city and economic centre.
What is the new capital of Egypt called?
Officially ‘The New Capital’ since 8 November 2025; it is still widely called the New Administrative Capital (NAC). A 2026 draft law reportedly proposed the name Memphis.
How tall is the Iconic Tower in Egypt?
393.8 metres and 77 storeys, the tallest building in Africa, completed in 2024 by CSCEC.
How many people live in Egypt’s new capital in 2026?
About 30,000 in October 2026, against a target of 60,000 by end-2026 and a long-term plan of 6.5 million.
Is the new capital funded by the state budget?
The government says no: it is financed through land sales and developers. But ACUD’s accounts and any public liabilities are not published.

Frequently Asked Questions

What is Egypt’s New Administrative Capital?
It is a planned city east of Cairo, built since 2015 to house Egypt’s ministries, parliament, presidency, embassies, a business district and housing for millions. Its managing company renamed it ‘The New Capital’ in official use on 8 November 2025, but ‘New Administrative Capital’ remains the common name.
When was the New Administrative Capital announced?
It was unveiled on 13 March 2015 at the Egypt Economic Development Conference in Sharm el-Sheikh. The Administrative Capital for Urban Development company (ACUD) was set up on 21 April 2016 to run the project.
How far is the new capital from Cairo?
Roughly 35 to 60 km east of central Cairo, depending on where you measure from; 45 km is the figure most often quoted. The OECD puts it 35 km east of Cairo along the Cairo–Suez/Red Sea highway corridor, between New Cairo and Suez.
How much does Egypt’s new capital cost?
There is no single audited total. The OECD’s 2024 survey said the cost ‘associated so far’ was estimated at US$60 billion, borne largely by developers. Reuters reported a US$58 billion price tag in 2019, and ACUD said in January 2024 it had spent EGP 500 billion on first-phase infrastructure and buildings.
Is the $60 billion figure the final cost?
No. The OECD described it as the cost associated with the project so far, not a final bill. It covers a project still under construction, mixes public and private spending, and the company’s accounts are not published, so the real total cannot be independently checked.
Who pays for the new capital?
Mostly land sales and private developers, according to the government. ACUD sells or auctions land to developers who build towers and housing. Prime Minister Mostafa Madbouly said in January 2024 that financing is outside the state budget, but contingent public liabilities are not disclosed.
Who owns ACUD?
Per the OECD, the Ministry of Defence, through the National Service Projects Organisation and the Armed Forces Land Projects Agency, holds 51% in return for contributing the land. The New Urban Communities Authority under the housing ministry holds 49% for a EGP 20 billion cash injection in 2016.
When did ministries move to the new capital?
The government district began working in mid-2023; Reuters reported ministries started operating there in July 2023. By January 2024 about 48,000 employees were commuting in daily. President Sisi took his third-term oath at the new parliament on 2 April 2024, formally marking it as the seat of government.
How many people live in the new capital?
About 30,000 residents, according to ACUD chairman Khaled Abbas in early October 2026. He said the population should reach about 60,000 by the end of 2026 and 250,000 within three years. In January 2024 only about 1,200 families had moved in.
What is the planned population?
About 6.5 million people at full build-out, on 700–725 square kilometres. The first two phases are each planned for about 40,000 feddans (168 square kilometres). Some official materials cite up to 7 million or more.
Why was the city renamed ‘The New Capital’?
ACUD said on 8 November 2025 that ‘The New Capital’ would be used in all official correspondence, dropping the word ‘Administrative’ to present it as a full city rather than an office park. A February 2026 draft law reportedly proposed making it a special-status province named Memphis; it has not been enacted.
What is the Iconic Tower?
The tallest building in Africa: a 77-storey, 393.8-metre tower in the Central Business District, built by China State Construction Engineering Corporation (CSCEC). Work began in May 2018 and the CTBUH listed it as completed in 2024.
Is there public transport to the new capital?
Yes. An electric light-rail line (LRT) from Adly Mansour station opened on 3 July 2022. The East Nile Monorail began passenger service on 6 May 2026 between New Cairo and Justice City in the capital. Long-distance high-speed rail is planned but delayed.
When did the monorail open?
The East Nile Monorail carried its first public passengers on 6 May 2026, running 16 stations from Marshal Tantawi in New Cairo to Justice City in the capital. The full 56.6 km line to Nasr City has 22 stations and a design capacity of 600,000 passengers a day.
How much does the monorail cost to ride?
Fares start at EGP 20 for up to five stations and rise to EGP 80 for the full line, with 50% off for subscribers. Al Jazeera calculated that a daily full-line commute would cost about 22% of the EGP 8,000 monthly minimum wage.
What is The Octagon?
The State Strategic Command Headquarters, a vast military and crisis-management complex in the new capital with eight main buildings arranged in an octagon. President Sisi inaugurated it on 4 July 2026; it centralises the armed forces’ command alongside other state bodies.
What is The Spine and is it part of the new capital?
The Spine is a separate EGP 1.4 trillion (about US$27 billion) mixed-use city announced by Talaat Moustafa Group with the National Bank of Egypt on 18 April 2026. It sits east of Cairo next to TMG’s Madinaty, not inside the new capital, and its cost should not be added to the capital’s.
Why is Egypt building a new capital?
To ease congestion in Greater Cairo, home to roughly 20 million people, to give the state modern purpose-built offices, to create land for housing and business, and to signal ambition. Critics say it mainly serves government and elite real estate while existing Cairo needs investment.
What are the main criticisms of the project?
Cost and transparency (ACUD’s accounts are unpublished), the military’s dominant role, low occupancy, high property prices, desert water use, and opportunity cost while Egypt faces debt pressure and inflation. Supporters point to jobs, modern infrastructure and land revenue.
How much does housing cost in the new capital?
Asharq Al-Awsat reported in July 2026 that apartments sold for about EGP 50,000 per square metre and villas about EGP 85,000, at roughly EGP 50 to the dollar. That puts a 100-square-metre flat well beyond most Egyptian households.
Where does the new capital get its water?
From the Nile, via large treatment plants. ACUD said in January 2024 that two plants of 800,000 and 700,000 cubic metres a day would together use about 1% of Egypt’s Nile share. Landscaping such as the 35 km Green River depends on treated water and irrigation discipline.
Has the Central Bank moved to the new capital?
Its new headquarters, with a currency printworks and automated cash centre, stands in the capital, and ACUD said in October 2026 the Central Bank would relocate in the coming months, followed by 18 banks. A completed move had not been announced as of 14 October 2026.
What happened in October 2026?
On 7 October Egypt’s National Authority for Tunnels signed a memorandum with Hyundai Rotem to study a 44-train, roughly 28 km hydrogen tram network for the capital, and ACUD set targets of 60,000 residents by year-end and 250,000 within three years.
Will the new capital succeed?
It is too early to say. The government side works: ministries, parliament, the presidency and the military command are there. Success as a city depends on residents, private employment, affordable housing and transport, which in October 2026 are still far below plan.

Conclusion: A Capital Built Ahead of Its People

In eleven years Egypt has moved its government into the desert, built Africa’s tallest tower, two rail links and a vast military command, and sold most of the first phase’s land. As a project to relocate the state, the New Administrative Capital has largely been delivered.

As a city, it has barely begun. The question is no longer whether Egypt can build a new capital, but whether tens of thousands of residents can become hundreds of thousands at prices Egyptians can afford, and whether the public will ever see accounts that show what the $60 billion question really costs.

Related AiTimeline Stories

⚠️ Editorial Note

Cost and population figures come from the OECD’s 2024 Economic Survey of Egypt, ACUD statements reported by Reuters (January 2024) and Egyptian media (October 2026), Egypt’s State Information Service and Asharq Al-Awsat. They have different dates and scopes, and estimates are not audited totals; targets are not counts. Distances to Cairo vary by source. Developments are current to 14 October 2026. This is general information, not investment or property advice.